ME Well Driller · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Well Construction and Siting

  • Map the well construction sequence from siting through completion, listing the decision points where casing, screen, and grout choices are fixed

  • Explain how overburden geology, bedrock fracture zones, and expected yield drive casing diameter, depth, and screen or open-hole design

  • Identify the setback and separation distances that constrain a drilling site before the rig moves in

  • Practice sizing casing and annulus dimensions for a typical residential bedrock well and check the arithmetic

Your checkpoint

A one-page siting and construction decision flowchart plus three worked casing/annulus sizing problems with answers

Week 2

Well Construction and Siting

  • Compare drive-point, gravel-pack, and bedrock open-hole completions by cost, yield expectation, and failure mode

  • Describe well development methods and judge when each is appropriate after drilling

  • Interpret a pump test or yield estimate and state what it does and does not prove about long-term capacity

  • List the common construction defects inspectors cite and the corrective action for each

Your checkpoint

A comparison table of four completion types with development method, expected yield range, and typical defect for each

Week 3

Maine Well Drilling Law and Rules

  • Outline the licensing structure for well drillers in Maine, including license categories, apprentice or journeyman pathways, and renewal obligations

  • Summarize the statutory authority and rule chapters that govern well construction, pump installation, and abandonment

  • State the notification, permit, and reporting duties that attach before, during, and after drilling a well

  • Identify the enforcement consequences of unlicensed practice or rule violations

Your checkpoint

A citation index of the statutes and rule chapters you must know, with a two-sentence plain-language summary of each

Week 4

Maine Well Drilling Law and Rules & Business Practices, Contracts, and Reporting

  • Draft a compliant well completion report from a set of field notes, capturing depth, casing, grout, yield, and static water level

  • Explain recordkeeping and retention duties and who may access submitted reports

  • List the contract terms a residential well agreement should contain, including scope, change orders, and payment schedule

  • Describe how to handle a disputed yield or a dry hole under a typical contract and under the rules

Your checkpoint

A complete sample well completion report and a one-page residential drilling contract checklist

Week 5

Grouting, Sealing, and Abandonment

  • Specify the grout type, mix, and placement method for annular seals in different hole conditions, including artesian and fractured bedrock

  • Explain the purpose of each seal element: annular grout, casing shoe, packer, and surface seal

  • Sequence an abandonment procedure for a flowing well and for a dry well, naming materials and verification steps

  • Identify the documentation and notification required when a well is abandoned or sealed

Your checkpoint

Two written abandonment procedures, flowing and dry, each with materials list, step sequence, and verification method

Week 6

Pumps, Pump Systems, and Water Treatment

  • Match pump type and horsepower to well yield, total dynamic head, and household demand

  • Read a pump curve and select an operating point that stays off the upthrust and downthrust ends

  • Diagnose common pump system faults such as cycling, low pressure, sand damage, and loss of prime, and state the test for each

  • Compare treatment options for iron, hardness, arsenic, and bacteria by mechanism and maintenance burden

Your checkpoint

A pump selection worksheet solved for one scenario plus a treatment decision table covering four contaminants

Week 7

Safety, Equipment, and Jobsite Practice

  • Build a pre-drilling jobsite hazard checklist covering rig setup, overhead lines, pit and fall hazards, and traffic control

  • State the required personal protective equipment and the confined-space and lockout practices that apply to pump and pit work

  • Describe safe handling and containment for drilling fluids, fuel, and grout on site

  • Outline the response steps for a struck utility, a rig instability event, and a wellhead injury

Your checkpoint

A pre-drilling jobsite safety checklist you could actually use, with at least twenty items and an emergency contact block

Week 8

Well Construction and Siting & Maine Well Drilling Law and Rules & Grouting, Sealing, and Abandonment & Pumps, Pump Systems, and Water Treatment & Safety, Equipment, and Jobsite Practice & Business Practices, Contracts, and Reporting

  • Take two full-length timed practice exams and log every missed question by domain

  • Re-study only the two weakest domains using your own notes and the citation index

  • Recite from memory the setback distances, grout requirements, and reporting deadlines

  • Review contract and reporting checklists one final time and confirm exam-day logistics

Your checkpoint

A scored practice exam log with a targeted review list and a one-page final cheat sheet of numbers and deadlines

Milestones

Week 2: Can sketch a well from siting to completion and justify each casing, screen, and grout decision without notes

Week 4: Can produce a complete, rule-compliant well completion report and cite the authority for each required field

Week 6: Can select a pump from a curve and write an abandonment procedure from memory

Week 8: Score at or above 80 percent on both timed practice exams with no domain below 70 percent