Well Construction and Siting
Map the well construction sequence from siting through completion, listing the decision points where casing, screen, and grout choices are fixed
Explain how overburden geology, bedrock fracture zones, and expected yield drive casing diameter, depth, and screen or open-hole design
Identify the setback and separation distances that constrain a drilling site before the rig moves in
Practice sizing casing and annulus dimensions for a typical residential bedrock well and check the arithmetic
Your checkpoint
A one-page siting and construction decision flowchart plus three worked casing/annulus sizing problems with answers
Well Construction and Siting
Compare drive-point, gravel-pack, and bedrock open-hole completions by cost, yield expectation, and failure mode
Describe well development methods and judge when each is appropriate after drilling
Interpret a pump test or yield estimate and state what it does and does not prove about long-term capacity
List the common construction defects inspectors cite and the corrective action for each
Your checkpoint
A comparison table of four completion types with development method, expected yield range, and typical defect for each
Maine Well Drilling Law and Rules
Outline the licensing structure for well drillers in Maine, including license categories, apprentice or journeyman pathways, and renewal obligations
Summarize the statutory authority and rule chapters that govern well construction, pump installation, and abandonment
State the notification, permit, and reporting duties that attach before, during, and after drilling a well
Identify the enforcement consequences of unlicensed practice or rule violations
Your checkpoint
A citation index of the statutes and rule chapters you must know, with a two-sentence plain-language summary of each
Maine Well Drilling Law and Rules & Business Practices, Contracts, and Reporting
Draft a compliant well completion report from a set of field notes, capturing depth, casing, grout, yield, and static water level
Explain recordkeeping and retention duties and who may access submitted reports
List the contract terms a residential well agreement should contain, including scope, change orders, and payment schedule
Describe how to handle a disputed yield or a dry hole under a typical contract and under the rules
Your checkpoint
A complete sample well completion report and a one-page residential drilling contract checklist
Grouting, Sealing, and Abandonment
Specify the grout type, mix, and placement method for annular seals in different hole conditions, including artesian and fractured bedrock
Explain the purpose of each seal element: annular grout, casing shoe, packer, and surface seal
Sequence an abandonment procedure for a flowing well and for a dry well, naming materials and verification steps
Identify the documentation and notification required when a well is abandoned or sealed
Your checkpoint
Two written abandonment procedures, flowing and dry, each with materials list, step sequence, and verification method
Pumps, Pump Systems, and Water Treatment
Match pump type and horsepower to well yield, total dynamic head, and household demand
Read a pump curve and select an operating point that stays off the upthrust and downthrust ends
Diagnose common pump system faults such as cycling, low pressure, sand damage, and loss of prime, and state the test for each
Compare treatment options for iron, hardness, arsenic, and bacteria by mechanism and maintenance burden
Your checkpoint
A pump selection worksheet solved for one scenario plus a treatment decision table covering four contaminants
Safety, Equipment, and Jobsite Practice
Build a pre-drilling jobsite hazard checklist covering rig setup, overhead lines, pit and fall hazards, and traffic control
State the required personal protective equipment and the confined-space and lockout practices that apply to pump and pit work
Describe safe handling and containment for drilling fluids, fuel, and grout on site
Outline the response steps for a struck utility, a rig instability event, and a wellhead injury
Your checkpoint
A pre-drilling jobsite safety checklist you could actually use, with at least twenty items and an emergency contact block
Well Construction and Siting & Maine Well Drilling Law and Rules & Grouting, Sealing, and Abandonment & Pumps, Pump Systems, and Water Treatment & Safety, Equipment, and Jobsite Practice & Business Practices, Contracts, and Reporting
Take two full-length timed practice exams and log every missed question by domain
Re-study only the two weakest domains using your own notes and the citation index
Recite from memory the setback distances, grout requirements, and reporting deadlines
Review contract and reporting checklists one final time and confirm exam-day logistics
Your checkpoint
A scored practice exam log with a targeted review list and a one-page final cheat sheet of numbers and deadlines
Milestones
Week 2: Can sketch a well from siting to completion and justify each casing, screen, and grout decision without notes
Week 4: Can produce a complete, rule-compliant well completion report and cite the authority for each required field
Week 6: Can select a pump from a curve and write an abandonment procedure from memory
Week 8: Score at or above 80 percent on both timed practice exams with no domain below 70 percent