CISRM study materials
CISRM study resources

CISRM: Risk Treatment and Control Selection

CISRM · Work through your exam, one topic at a time.

All guide sections

Risk Treatment and Control Selection

Domain 5 tests how you choose and justify risk responses. The exam expects control categories, cost-benefit reasoning, and residual-risk acceptance.

Core rules

  • Treatment options are avoid, reduce, transfer or share, and accept; acceptance must be explicit and owned.
  • Control types include preventive, detective, corrective, and compensating; layer them for defense in depth.
  • Map each control to the risk it addresses and the threat or vulnerability path it interrupts.
  • Control selection compares cost with expected risk reduction, not with the size of the risk alone.
  • Frameworks such as NIST SP 800-53, CIS Controls, and ISO/IEC 27001 Annex A provide control catalogs; tailoring is still required.

Worked example

A remote-access risk has an ALE of $1.2 million. MFA costs $150,000 per year and is expected to reduce the ALE to $300,000, a $900,000 benefit and a 6:1 ratio. A full network redesign costs $2 million and reduces ALE to $200,000, a $1 million benefit but a poor first-year ratio. The team selects MFA, records residual risk of $300,000 within tolerance, and schedules the redesign as a longer-term project. The reasoning weighs risk reduction against cost and timing, not control prestige.

Traps

  • Calling insurance risk elimination; transfer shares financial impact but not accountability.
  • Selecting a control without linking it to a specific risk.
  • Assuming a control operates effectively without testing it.
  • Ignoring compensating controls when a primary control is impractical.