Silence of Administration and a Late, Conditional Permit

On 1 March a company filed a complete application with the Municipality of Vardar for a construction permit for a 600 m² warehouse. The applicable law sets a 30-day deadline for a decision. The company paid the fee and submitted all required documents. By 15 May the municipality had issued nothing; the applicant sent a written reminder on 16 May. On 20 May the municipality issued a permit, but the decision contained no statement of reasons and imposed a new condition: the company must pay €9,000 for road-widening works before starting construction. The condition had not been mentioned in the request or in any bylaw shown to the applicant. The municipality also refused a requested oral hearing, saying the file was 'routine'. The company wants to challenge both the delay and the conditions and asks whether it must pay the €9,000 first.

1. What are the legal effects of the municipality's failure to decide by 15 May, and what remedies were open to the applicant at that point?

Read the worked answer

The municipality was required to decide within the 30-day period. When it did not, the silence of administration arose. The applicant could treat that silence as a rejection of the request and use the remedies available against a refusal:

  • appeal to the second-instance administrative body, and
  • if the appeal does not produce a lawful decision, seek an administrative dispute before the competent court.

The applicant should not wait indefinitely for a late act. A prompt appeal or request for a decision creates a record and preserves procedural positions. The fact that the municipality later issued a permit does not erase the earlier delay; it may affect how the court frames the case, but the applicant can still challenge the final act.

If the applicable law allows a request for a certificate of silence, the applicant should also obtain it. The certificate helps prove the date on which the silence began and supports a claim for delay.

2. Analyze the permit issued on 20 May: is it valid, and can the applicant challenge the €9,000 condition without paying it first?

Read the worked answer

The permit is an administrative act and must satisfy formal and substantive requirements. Three defects are apparent:

  • No statement of reasons. A reasoned decision is essential so that the party can understand the legal and factual basis and exercise appeal rights.
  • Refusal of a requested hearing, if the law required one or if the facts were disputed, is a procedural violation.
  • The €9,000 road-widening condition appears to lack a legal basis in the request or in a bylaw communicated to the applicant. An administrative body may impose conditions only within its legal powers and for purposes connected to the permit.

The permit is therefore vulnerable to annulment, at least as to the condition. The applicant can appeal the permit and ask the second-instance body to remove the unlawful condition. Filing an appeal does not ordinarily require prior payment of the disputed sum; payment is a separate obligation and its enforceability depends on the act. The applicant should expressly request suspension of execution if payment is demanded before the appeal is decided. Paying first may weaken the practical position, so the better course is to appeal, seek suspension, and document the financial harm.