MEngC PE Electrical Building Services study plan
MEngC PE Electrical Building Services · Give each week a clear focus.
8 weeks · About 7 hours per week
Electrical power systems and distribution design for buildings
Derive and compare the design current, voltage drop and protective-device rating for a three-phase submain feeding a mixed office and plant load, and justify each choice in writing.
Explain how TN-S, TN-C-S and TT supply arrangements in a building change the fault path and the required protective measure, using a one-line sketch you draw yourself.
Size a distribution board schedule by allocating final circuits to ways and totalling connected load and diversified demand per board.
State the key selection and erection requirements you would apply to a main switchboard and rising busbar in a multi-storey building, and note where you would verify against the local wiring code.
Your checkpoint
A hand-drawn single-line diagram with a board schedule for a 6-storey building, including design currents, voltage drop at the furthest load, and a written justification of each protective device rating.
Electrical power systems and distribution design for buildings & Protection, switching, cables and fault current calculations
Calculate prospective short-circuit current at two points in a radial distribution system from transformer impedance and cable impedance, showing each step.
Select cable cross-sectional area for a given load using current-carrying capacity, derating factors for grouping and ambient temperature, and voltage drop, then check the earth fault loop impedance against the disconnection time.
Compare the operating characteristics of MCBs, MCCBs and fuses for overload and short-circuit protection and state where each is appropriate in a building distribution system.
Explain discrimination and cascading between upstream and downstream devices and identify one arrangement in your own design where discrimination is critical.
Your checkpoint
A fault-current and cable-sizing calculation sheet for one radial feeder showing Ib, In, Iz, voltage drop percentage and Zs against the maximum permitted value.
Building services electrical loads, demand and energy management
Build a maximum demand estimate for a building using diversity after diversity, and compare the result with a direct VA-per-square-metre method.
Assess the impact of large motor loads on demand and starting current and propose a starting method that keeps voltage dip within an acceptable limit.
Identify the main opportunities for energy reduction in a building services load profile, including power factor correction and load shifting, and estimate the saving for one measure.
Explain how sub-metering and energy monitoring data would be used to verify a design assumption about demand.
Your checkpoint
A one-page maximum demand and diversity calculation for a mixed-use building with a table of connected load, diversity factor applied and resulting demand per board.
Lighting design, controls and energy efficiency
Calculate the maintained illuminance, number of luminaires and uniformity for an office using the lumen method, and state the assumptions for maintenance factor and reflectance.
Select luminaire types and control strategies for an office, a circulation area and a plant room, and justify each against visual task and energy use.
Explain the requirements for emergency lighting in escape routes and open areas and size a battery-backed luminaire set for a given duration.
Describe how daylight linking and occupancy sensing interact with manual switching and where the control strategy would conflict with occupant needs.
Your checkpoint
A lighting design calculation for one office room including luminaire schedule, lumen method calculation, control narrative and emergency lighting provision.
Earthing, bonding, lightning protection and electrical safety & Fire detection, alarm and life safety electrical systems
Design an earthing and bonding arrangement for a building with a TN-C-S supply and a separate structural steel earth, and identify the main protective bonding conductors required.
Explain the principle of a lightning protection system, the role of the air termination, down conductor and earth termination, and how you would determine the need for protection.
Trace the sequence of operation of a fire detection and alarm system from detector activation to sounder operation and interface with other systems.
Describe the electrical requirements for life safety systems, including fire-rated cable routes and the supply arrangement for fire pumps and smoke control.
Your checkpoint
An earthing and bonding schematic plus a fire alarm cause-and-effect matrix for a simple three-storey building, covering detection zones, sounders and one interface to a door release.
Standby and emergency power, UPS and generators
Size a standby generator for a building load that includes motors and a UPS, accounting for starting kVA, step loading and derating for altitude and temperature.
Compare the operating principles and appropriate applications of an online double-conversion UPS and a line-interactive UPS, and state the battery autonomy you would specify for a given duty.
Design the changeover arrangement between utility and generator supply, including interlocking and the neutral earthing arrangement, and explain the risk of parallel operation.
Explain the testing and maintenance regime you would require for a standby generator and a UPS system.
Your checkpoint
A standby power single-line diagram with generator and UPS sizing calculations, changeover arrangement and a written test and maintenance schedule.
Building automation, controls and ELV/ICT systems & Codes, standards, contracts, ethics and professional practice
Describe the layered architecture of a building automation system and explain how a field bus, a controller and a supervisory layer exchange data.
Specify the points list for a small plant room, covering temperature, pressure, status and command points, and state the alarm and trending requirement for each.
Explain the contractual roles of employer, engineer, contractor and subcontractor in a building services project and identify where design responsibility sits for a design-and-build element.
Apply a professional ethics scenario about a design change that reduces cost but compromises safety, and set out the action you would take and to whom you would report.
Your checkpoint
A building automation points list for one plant room with a short written answer to an ethics scenario, citing the applicable standard or code clause you would rely on.
Electrical power systems and distribution design for buildings & Protection, switching, cables and fault current calculations & Codes, standards, contracts, ethics and professional practice
Re-solve two fault-current and cable-sizing problems under timed conditions without notes and check against your earlier calculation sheets.
Review your weak areas from weeks 1 to 7 and rewrite the two weakest topics as concise reference notes you can revise from.
Work through a full building services electrical design scenario that combines distribution, protection, standby power and life safety, and state the interfaces between them.
Confirm the current edition of each standard you rely on and note any clause numbers you are unsure of for further checking.
Your checkpoint
A timed mock design exercise completed in one sitting with a self-marked error log listing every mistake, its cause and the reference note that fixes it.
Milestones
Week 2: Can complete a fault-current and cable-sizing calculation unaided from transformer to final circuit and state Zs against the maximum permitted value without referring to notes.
Week 4: Can produce a full maximum demand estimate and an office lighting calculation from blank paper, with all assumptions stated and defensible.
Week 6: Can draw the earthing, fire alarm and standby power interfaces for a three-storey building on one sheet and explain the sequence of operation for each.
Week 8: Scores at least 70 percent on the timed mock design exercise and has a written error log with no unresolved clause references.