Warehouse Defects, Retention, and a Late Counterclaim

Mongolian Bar Exam · Put your knowledge to work in context.

All case studies

Warehouse Defects, Retention, and a Late Counterclaim

Erdenet-based 'Munkh' LLC hired 'Tavan' LLC to build a 2,400-square-metre warehouse for 480 million MNT. The contract set a 12-month defects liability period, 10% retention (48 million MNT), and required the employer to give written notice of defects within 14 days of discovery. The warehouse was accepted on 15 March 2024 with a protocol stating 'no visible defects.' On 20 November 2024, after heavy snow, the roof began leaking and damaged stored goods worth 35 million MNT. Munkh notified Tavan on 22 November and demanded repair within 30 days. Tavan replied that the leak was caused by Munkh's failure to clear snow and by a design change Munkh ordered. Munkh sued on 10 February 2025 for 48 million MNT retention, 35 million MNT damages, and repair costs of 60 million MNT. Tavan filed a counterclaim for the retention on 3 March 2025, six days after the court's deadline for counterclaims. Tavan also argues the claim is time-barred. The court has not yet held a hearing.

1. Should the court accept Tavan's counterclaim filed six days after the deadline? Explain the procedural test.

Read the worked answer

Rule and purpose. A counterclaim is a procedural defence and a separate claim arising from the same relationship. Courts should decide related claims together to avoid inconsistent judgments and repeated litigation. Lateness is a factor, not an automatic bar. Application. The counterclaim concerns the same construction contract and the same retention money that Munkh is suing for. Refusing it would force Tavan to bring a second action and could produce conflicting findings on the same defects. The delay is only six days, and no prejudice is shown; Munkh already knows the retention issue because it sued for that sum. The court can accept the counterclaim and adjourn briefly for preparation. Conclusion. The court should accept the counterclaim, or at minimum treat the retention claim as a set-off defence. A peremptory deadline does not override the court's duty to resolve the whole dispute fairly.

2. Who bears the burden of proof on the cause of the leak? How does the defects liability period affect that burden?

Read the worked answer

Employer's burden. Munkh must prove that a defect existed, that it appeared within the 12-month defects liability period, that notice was given within 14 days of discovery, and the amount of loss. The acceptance protocol saying 'no visible defects' does not waive latent defects; it only records the visible condition on 15 March 2024. Contractor's burden. Once a defect appears within the defects period, Tavan is presumed responsible unless it proves an exempting cause, such as employer misuse, normal wear, or a design change imposed by Munkh. Tavan's allegations about snow clearing and design change are affirmative defences, so Tavan must prove causation. Application. Notice on 22 November was two days after discovery and within 12 months of acceptance. Munkh has met the threshold notice burden. Tavan must now show that the leak came from Munkh's failure to clear snow or from the design change; if it proves only part, liability may be apportioned. The court should order an expert examination if the evidence conflicts.

3. Is Munkh's claim time-barred? Calculate the relevant periods and explain the effect of the retention and notice clauses.

Read the worked answer

Limitation. The general limitation period is three years from when the claimant knew or should have known of the violation. Munkh sued on 10 February 2025. The retention claim arose on or after acceptance on 15 March 2024, so it is well within three years. The defect damages arose on 20 November 2024 when the leak was discovered, also within three years. Defects period. The 12-month defects liability period expired on 15 March 2025, but the defect appeared and notice was given in November 2024, so the claim was preserved. The 14-day notice clause is a contractual condition; notice two days after discovery satisfies it. Conclusion. The claim is not time-barred. The retention is not a penalty but security for performance; Munkh may set it off against proven repair costs and damages. Tavan's limitation defence should fail, though the court must still decide causation and quantum.