MoR Practitioner · Keep the key ideas within reach.

Quick reference

Management of risk principles and concepts

  • Risk is the combination of the probability of an event and its consequence; uncertainty that matters either way (threat or opportunity).

  • Risk = f(likelihood, impact). Exposure = likelihood × impact; use it to rank, not to predict a single outcome.

  • Inherent risk is assessed before controls; residual risk after controls; target risk is the acceptable level the organisation aims for.

  • Risk appetite is the amount and type of risk an organisation is willing to seek or retain; risk tolerance is the acceptable variation around that appetite.

  • Three lines model: first line owns and manages risk, second line sets framework and oversight, third line gives independent assurance.

  • Threat exploits a vulnerability to produce an impact on an asset; a control reduces likelihood, impact, or both.

  • Risk can be positive (opportunity) as well as negative (threat); both are managed through the same process with different responses.

  • Gross versus net: gross risk ignores controls, net risk includes control effectiveness; control effectiveness is judged by design and operating evidence.

  • Risk owner is accountable for a specific risk; risk action owner is accountable for delivering a specific response.

Quick reference

Management of risk approach and framework

  • Framework components: mandate and commitment, framework design, risk management process, and continual improvement - the four elements of ISO 31000-style frameworks.

  • A risk management policy states objectives, scope, accountabilities, appetite, and reporting requirements; it is approved at governing-body level.

  • The framework must be proportionate to the organisation's size, sector, and complexity; a small entity uses simpler artefacts than a large one.

  • Risk architecture (roles, committees, escalation routes) is distinct from risk process (identify, assess, respond, monitor) and from risk protocol (meetings, reports, templates).

  • Escalation rules define thresholds: risks above appetite or above a defined exposure score go to the next governance tier.

  • Risk taxonomy provides a consistent set of categories (strategic, operational, financial, compliance, reputational) so risks are comparable across units.

  • A risk register records risk description, cause, event, consequence, owner, inherent/residual scores, controls, and response actions with dates.

  • Three-point or range estimates are preferred over single-point estimates when assessing uncertain impacts.

  • Framework review cadence is set in the policy; annual review plus event-driven review after incidents or major change is typical.

Quick reference

Risk management processes

  • Process sequence: establish context → identify → analyse → evaluate → treat → monitor and review → communicate and consult (communication is continuous, not a final step).

  • Establishing context sets scope, objectives, stakeholders, external and internal factors, and the risk criteria (appetite, thresholds) used later to evaluate.

  • Identification techniques include workshops, interviews, SWOT, PESTLE, bow-tie analysis, fault tree, FMEA, and scenario analysis; use more than one.

  • A well-formed risk statement follows cause → event → consequence, e.g. 'Because X may occur, Y could happen, leading to Z'.

  • Analysis separates likelihood and impact ratings using a defined scale; the matrix must be calibrated so the same score means the same thing everywhere.

  • Evaluation compares analysed risk against criteria to decide: accept, treat, or escalate; it is a decision step, not another assessment.

  • Treatment options: avoid, reduce (mitigate), transfer (share, e.g. insurance), accept (retain), and exploit or enhance for opportunities.

  • Residual risk after treatment is compared with target risk; if residual exceeds tolerance, further treatment or escalation is required.

  • Bow-tie links threats and consequences through a top event, with preventive controls on the left and mitigating controls on the right.

Quick reference

Embedding and reviewing risk management

  • Embedding means risk is part of normal decision-making (strategy, projects, procurement, change), not a separate compliance exercise.

  • Indicators: risk appears in board and management agendas, in business cases, and in performance objectives; owners can explain their risks without prompting.

  • Key risk indicators (KRIs) are leading metrics with defined thresholds that signal rising exposure; key control indicators (KCIs) evidence control health.

  • Maturity models describe progression (e.g. ad hoc → repeatable → defined → managed → optimised); use them to plan improvement, not to score for its own sake.

  • Assurance mapping shows which controls are covered by which assurance source (management, compliance, internal audit) and where gaps or duplication exist.

  • Training and communication must be role-specific: boards need appetite and oversight, managers need assessment and treatment, staff need reporting routes.

  • Review triggers: scheduled cycle, incidents and near misses, audit findings, regulatory change, mergers, new systems, and shifts in appetite.

  • Risk culture is evidenced by escalation without fear, challenge of assumptions, and incentives that do not reward unmanaged risk-taking.

  • Performance measures for risk management should include timeliness of action closure and quality of risk information, not only counts of risks logged.