MS General Contractor study materials
MS General Contractor study resources

MS General Contractor key terms

MS General Contractor · Get comfortable with the vocabulary.

Sole Proprietorship

A business owned and operated by one person with no separate legal entity; the owner reports business income on personal taxes and is personally liable for all debts and claims.

Related: Limited Liability Company (LLC), Joint Venture
Limited Liability Company (LLC)

A state-chartered business form that separates owners from company liabilities; profits pass through to members' personal tax returns unless corporate taxation is elected. Mississippi requires registration with the Secretary of State.

Related: Sole Proprietorship, Joint Venture
Joint Venture

An agreement in which two or more firms combine resources and share risk on a single project. It may be a separate entity or a contractual collaboration and usually ends at project closeout.

Related: Limited Liability Company (LLC), Performance Bond
Working Capital

Current assets minus current liabilities; it measures the cash and near-cash a contractor has to fund payroll, materials, and overhead between progress payments. Thin working capital is a common cause of construction failure.

Related: Pay Application, Schedule of Values
Bid Bond

A surety instrument submitted with a bid that guarantees the bidder will enter the contract and furnish required bonds if selected. If the bidder defaults, the surety pays the owner up to the stated penalty.

Related: Performance Bond, Payment Bond
Performance Bond

A surety bond protecting the owner if the contractor fails to complete the work according to the contract. The surety must finish the job or pay the owner's cost of completion, up to the bond amount.

Related: Payment Bond, Bid Bond
Payment Bond

A surety bond guaranteeing the contractor will pay subcontractors, suppliers, and laborers. It gives unpaid claimants a route to recover from the surety when the contractor defaults on payment obligations.

Related: Mechanic's Lien, Performance Bond
Certificate of Responsibility

A Mississippi credential issued by the State Board of Contractors that lets a firm bid on and perform construction contracts above the statutory threshold. It records the contractor's classification and board-approved contract limit.

Related: Mississippi State Board of Contractors
Mississippi State Board of Contractors

The state agency that licenses general and specialty contractors, administers the certificate of responsibility, investigates complaints, and can suspend or revoke a contractor's right to bid or work in Mississippi.

Related: Certificate of Responsibility
Change Order

A written modification signed by the owner and contractor that changes contract scope, price, or time. Without a signed change order, disputed work is harder to collect and may become a constructive change claim.

Related: Constructive Change, Substantial Completion
Substantial Completion

The stage at which work is sufficiently complete for its intended use so the owner can occupy it. It usually starts warranty periods, shifts insurance responsibility, and reduces retainage.

Related: Punch List, Change Order
Mechanic's Lien

A statutory claim against real property that secures payment for labor, materials, or services that improved the property. Filing and enforcement deadlines are strict and vary by state.

Related: Lien Waiver, Payment Bond
Lien Waiver

A document in which a claimant gives up lien rights, usually in exchange for payment. Conditional waivers take effect only when payment clears; unconditional waivers take effect on signing.

Related: Mechanic's Lien, Pay Application
Indemnification

A contract clause where one party agrees to cover the other's losses or claims arising from specified events. Broad clauses may be limited by state anti-indemnity statutes, especially for a party's own negligence.

Related: Certificate of Insurance
Pay-When-Paid Clause

A subcontract provision making the subcontractor's payment due only after the owner pays the general contractor. Courts often interpret it narrowly, and some states limit its enforceability.

Related: Payment Bond, Mechanic's Lien
Constructive Change

Work the contractor is directed to perform, or must perform, that differs from the contract but was never formalized through a change order. It can support a claim for extra cost or time.

Related: Change Order, Request for Information
Critical Path Method

A scheduling technique that links tasks by logic and duration to identify the longest path through the project. Activities on that path have no slack and drive the completion date.

Related: Total Float, Baseline Schedule
Total Float

The amount of time an activity can slip without delaying project completion. Weather, owner changes, and sequencing affect float, and contracts may specify who owns it.

Related: Critical Path Method, Baseline Schedule
Baseline Schedule

The approved project schedule against which actual progress is measured. It supports delay analysis and is typically updated monthly while the original baseline stays frozen for comparison.

Related: Critical Path Method, Look-Ahead Schedule
Look-Ahead Schedule

A short-interval schedule, often two to four weeks, prepared by the superintendent to plan crews, materials, and equipment in detail. It rolls forward weekly and supports the master schedule.

Related: Baseline Schedule, Critical Path Method
Punch List

A list of minor incomplete or defective items identified near substantial completion. The contractor must correct them before final payment and final acceptance are granted.

Related: Substantial Completion
Request for Information

A written question from the contractor to the design team asking for clarification of unclear drawings or specifications. Responses become part of the contract record and may lead to change orders.

Related: Submittal, Change Order
Submittal

Shop drawings, product data, samples, or mock-ups the contractor sends for the designer's review to confirm the work will meet the specifications. Review time is often a contract milestone.

Related: Request for Information, Performance Specification
Schedule of Values

An itemized breakdown of the contract sum by work category, used to support progress payments. Each pay application bills against the completed percentages listed in the schedule.

Related: Pay Application, Quantity Takeoff
Quantity Takeoff

A systematic measurement of the materials and work items shown on the drawings, used to price a project. Errors here carry through the entire estimate, so careful checking is essential.

Related: Schedule of Values, Contingency
Lump Sum Contract

A contract with a fixed total price for a defined scope of work. The contractor absorbs cost overruns unless the scope changes through a change order.

Related: Unit Price Contract, Change Order
Unit Price Contract

A contract that pays a set amount per unit of work actually performed, such as per cubic yard of excavation. It is common where quantities are uncertain at bidding.

Related: Lump Sum Contract, Quantity Takeoff
Addendum

A written change to the bidding documents issued after drawings and specifications are released and before bids are opened. Contractors must acknowledge addenda in their bids.

Related: Alternates, Request for Information
Alternates

Specific changes in scope, materials, or methods priced separately in a bid so the owner can accept or reject them. They let the owner compare options before awarding the contract.

Related: Addendum, Contingency
Contingency

A reserve in the estimate or budget for known risks and unknowns. It is drawn down with owner approval and tracked against specific exposures rather than treated as spare cash.

Related: Alternates, Quantity Takeoff
Performance Specification

A specification that states the required result or function and leaves means and methods to the contractor. Prescriptive specifications, by contrast, dictate products and installation details.

Related: Submittal, Addendum
Competent Person

Under OSHA, someone capable of identifying hazards and authorized to take prompt corrective action. Construction standards require one for excavations, scaffolding, and fall protection.

Related: Job Hazard Analysis, Fall Protection
Job Hazard Analysis

A pre-task review that breaks a job into steps and identifies hazards and controls for each. Supervisors use it to plan safe work and brief the crew.

Related: Competent Person, Fall Protection
Fall Protection

Systems and practices that prevent workers from falling from heights, such as guardrails, personal fall arrest, and safe access. OSHA requires protection above six feet in construction.

Related: Competent Person, Job Hazard Analysis
Certificate of Insurance

A form from an insurer or broker summarizing a policy's coverage limits and dates. It is evidence of coverage, not the policy itself, and creates no contractual rights by itself.

Related: Builders Risk Insurance, Indemnification
Builders Risk Insurance

Property coverage for a project under construction, including materials, equipment, and sometimes soft costs. It typically covers fire, wind, theft, and other listed perils until completion.

Related: Certificate of Insurance
Pay Application

The monthly billing package a contractor submits to request progress payment, including the schedule of values, stored materials, and lien waivers. The architect or owner certifies it before payment.

Related: Schedule of Values, Lien Waiver
Certified Payroll

A weekly payroll report required on federally funded projects showing each worker's classification, hours, and wages. It demonstrates compliance with prevailing wage and overtime rules.

Related: Prevailing Wage
Prevailing Wage

The minimum wage and benefit rates set by law for workers on public projects, based on local labor market surveys. Contractors must pay these rates and document them.

Related: Certified Payroll
Stormwater Pollution Prevention Plan

A site plan required under NPDES permits that describes erosion controls, sediment barriers, and inspection procedures to keep construction runoff out of waterways.