This domain tests how the contract documents are assembled, interpreted, changed, paid, and closed out. Expect questions on notice, change orders, payment applications, retainage, and the difference between a promise and an enforceable written modification.

Core rules

  • The contract documents usually include the agreement, general and supplementary conditions, specifications, drawings, addenda, and executed change orders.
  • Follow the order-of-precedence clause when documents conflict; do not silently choose the cheapest interpretation.
  • Most changes require written authorization before work. Oral direction should be confirmed in writing immediately.
  • Pay applications are certified by the contractor and reviewed by the owner or architect; retainage is withheld under the contract or statute.
  • Substantial completion triggers warranty, punch-list, and retainage consequences; final payment follows closeout documents and lien waivers.

Worked example. A contract has $1,000,000 original value and 5% retainage. The contractor has earned $400,000 to date and has been paid $300,000. Current payment: $400,000 earned minus $20,000 retainage = $380,000 due, minus $300,000 previous payments = $80,000. Reasoning: retainage is calculated on cumulative earned value, not only the current month; subtracting prior payments avoids double billing.

Traps. Performing extra work on a handshake; missing a notice deadline for delay or differing site conditions; sending an unconditional lien waiver before payment clears; confusing substantial completion with final acceptance.