MS General Contractor: Project Management, Scheduling, and Supervision

MS General Contractor · Work through your exam, one topic at a time.

All guide sections

Project Management, Scheduling, and Supervision

Project Management, Scheduling, and Supervision

This domain tests planning and control: critical path schedules, submittals and RFIs, daily documentation, supervision, and coordination. The exam rewards practical understanding of how schedule logic and field records affect time and money.

Scheduling and control

  • A CPM schedule links activities by predecessors and durations; the critical path is the longest path and has zero total float.
  • Total float is the time an activity can slip without delaying project completion; free float is slip without delaying the next activity.
  • Update schedules with actual starts, finishes, and remaining durations; document delays contemporaneously.

Supervision

  • Maintain daily reports, RFIs, submittal logs, meeting minutes, and inspection records.
  • Coordinate subcontractors, verify work against plans and specs, and correct defects promptly.
  • Integrate safety into supervision: hazards observed in the field must be corrected and documented.

Worked example. Activity A (5 days) precedes B (3 days) and C (4 days); B precedes D (2 days); C precedes D. Path A-B-D = 10 days; A-C-D = 11 days, so A-C-D is critical and total float on B is one day. Reasoning: compare complete paths; the longest controls completion, and B can slip one day without moving D.

Traps. Treating total float and free float as identical; failing to update a schedule after changes; relying on memory instead of daily records; letting a subcontractor's delay become undocumented.