MS Roofing Contractor key terms
MS Roofing Contractor · Get comfortable with the vocabulary.
- Certificate of Responsibility
- Related: Monetary Limit, Mississippi State Board of Contractors, Bid
A license issued by the Mississippi State Board of Contractors that authorizes a contractor to bid on or perform covered construction work. The dollar value of the project must fall within the certificate's approved monetary limit.
- Mississippi State Board of Contractors
- Related: Certificate of Responsibility, Monetary Limit
The state agency that licenses and regulates construction contractors in Mississippi. It administers exams, issues certificates of responsibility, sets monetary limits, and handles complaints, violations, and disciplinary actions.
- Monetary Limit
- Related: Certificate of Responsibility, Financial Statement
The maximum project value a certificate holder may contract for, set by the Board based on the contractor's demonstrated financial capacity and experience. Bidding or working above this limit is a licensing violation.
- Bid
- Related: Certificate of Responsibility, Bid Bond
A written offer to perform specified work at a stated price. In Mississippi, covered public and private projects require the bidder to hold a valid certificate of responsibility and to note the certificate number on the bid.
- Bid Bond
- Related: Performance Bond, Payment Bond, Bid
A surety guarantee submitted with a bid that promises the bidder will enter the contract if awarded. If the bidder defaults, the surety pays the owner up to the bond amount, typically a percentage of the bid.
- Performance Bond
- Related: Bid Bond, Payment Bond
A surety bond that protects the owner if the contractor fails to complete the work according to the contract. The surety may pay the loss or arrange completion by another contractor.
- Payment Bond
- Related: Performance Bond, Mechanics' Lien
A surety bond that guarantees payment to subcontractors, laborers, and suppliers on a project. It protects the owner from mechanics' liens filed by unpaid parties.
- Mechanics' Lien
- Related: Payment Bond, Lien Waiver
A legal claim against real property filed by a party who supplied labor, materials, or services and was not paid. It can cloud title and force sale of the property if unresolved.
- Lien Waiver
- Related: Mechanics' Lien, Progress Payment
A written document in which a party gives up the right to file a lien, usually in exchange for payment. Conditional waivers take effect only when payment clears; unconditional waivers take effect on signing.
- Retainage
- Related: Progress Payment, Substantial Completion, Punch List
A percentage of each progress payment withheld by the owner until the work is substantially complete. It provides leverage to ensure correction of defects and completion of punch list items.
- Progress Payment
- Related: Retainage, Schedule of Values, Pay Application
A periodic payment to the contractor based on the value of work completed and materials stored during a billing period. It is supported by a pay application and typically reduced by retainage.
- Schedule of Values
- Related: Pay Application, Progress Payment
A breakdown of the contract sum allocated among work items, used to evaluate pay applications. Each line shows the value of that portion of the work and the percentage completed.
- Pay Application
- Related: Schedule of Values, Progress Payment, Retainage
The contractor's formal request for payment on a project, showing work completed, materials stored, and amounts due. It is reviewed by the architect or owner's representative before payment is certified.
- Punch List
- Related: Substantial Completion, Retainage
A list of incomplete or defective items identified during a walkthrough near completion. The contractor must correct these items before final payment or release of retainage.
- Substantial Completion
- Related: Punch List, Retainage, Warranty Period
The stage when the work is sufficiently complete for its intended use, even though minor items remain. It typically starts warranty periods and allows the owner to occupy the project.
- Change Order
- Related: Request for Information, Contract Documents
A written modification to the contract signed by the owner and contractor that changes the scope, price, or schedule of the work. It becomes part of the contract documents once executed.
- Request for Information
- Related: Change Order, Contract Documents
A formal written question from the contractor to the design professional seeking clarification of drawings, specifications, or contract terms. Responses are documented and may lead to a change order.
- Contract Documents
- Related: Specifications, Change Order
The complete set of documents defining the project, including the agreement, general and supplementary conditions, specifications, drawings, addenda, and executed change orders. They govern the rights and duties of the parties.
- Specifications
- Related: Contract Documents, Shop Drawing
The written portion of the contract documents describing materials, standards, workmanship, and installation methods. Specifications work together with drawings; written requirements generally control in conflicts unless stated otherwise.
- Shop Drawing
- Related: Submittal, Specifications
A detailed drawing prepared by a contractor, manufacturer, or fabricator showing how a component will be built or installed. It is submitted for review and approval before fabrication or installation.
- Submittal
- Related: Shop Drawing, Specifications
Product data, samples, shop drawings, or certificates sent to the design professional for review and approval before installation. Approved submittals confirm that materials meet the specified requirements.
- As-Built Drawing
- Related: Shop Drawing, Punch List
A marked-up drawing revised to show actual installed conditions, dimensions, and locations at the end of a project. It is delivered to the owner for future maintenance and renovation reference.
- Underlayment
- Related: Ice Dam Membrane, Roof Deck, Roof Slope
A layer of material installed beneath the roofing to provide a secondary weather barrier and separate the roof covering from the deck. Synthetic and felt products are common; ice dam membranes are used in vulnerable areas.
- Ice Dam Membrane
- Related: Underlayment, Valley, Roof Slope
A self-adhering waterproof membrane installed along eaves and in valleys to prevent water backup from ice dams. It is required in certain locations by code and must be applied over a clean, dry deck.
- Roof Slope
- Related: Low-Slope Roof, Underlayment, Roof Pitch
The incline of a roof expressed as the ratio of vertical rise to horizontal run, such as 4:12. Slope determines which roofing materials and installation methods are permitted.
- Roof Pitch
- Related: Roof Slope, Rafter
The incline of a roof expressed as a fraction of total rise over total span, such as 1/3 pitch. It is related to slope but calculated differently, so the two terms should not be confused.
- Low-Slope Roof
- Related: Roof Slope, Single-Ply Membrane, Flashing
A roof with a slope of 3:12 or less, often called a flat roof in practice. It typically uses membrane systems such as built-up, modified bitumen, EPDM, or TPO.
- Single-Ply Membrane
- Related: Low-Slope Roof, Flashing, Seam
A flexible sheet roofing material installed in one layer, such as EPDM, TPO, or PVC. Sheets are joined by adhesive, tape, or heat welding and are common on low-slope roofs.
- Built-Up Roof
- Related: Low-Slope Roof, Modified Bitumen
A low-slope roof system made of alternating layers of bitumen and reinforcing ply felt, topped with a surfacing. It is durable and common on commercial buildings.
- Modified Bitumen
- Related: Built-Up Roof, Low-Slope Roof
A roofing membrane made from asphalt modified with polymers to improve flexibility and durability. It is supplied in rolls and applied with heat, adhesive, or torching on low-slope roofs.
- Flashing
- Related: Counterflashing, Valley, Roof Penetration
Metal or membrane material used to seal roof edges, penetrations, walls, and valleys against water entry. Proper flashing is critical at transitions and is a common source of leaks.
- Counterflashing
- Related: Flashing, Roof Penetration
A metal cap attached to a wall or penetration that overlaps the base flashing to shed water. It protects the top edge of the flashing and prevents water from entering behind it.
- Valley
- Related: Flashing, Ice Dam Membrane, Roof Slope
The internal angle where two roof planes meet, channeling water off the roof. Valleys require special flashing or lining and careful installation because they carry concentrated water flow.
- Roof Deck
- Related: Underlayment, Rafter
The structural surface that supports the roofing system, commonly wood sheathing, concrete, or steel. The deck must be sound, properly attached, and able to accept the specified underlayment and covering.
- Roof Penetration
- Related: Flashing, Counterflashing
Any object passing through the roof surface, such as a vent, pipe, skylight, or chimney. Each penetration must be flashed and sealed to prevent water intrusion.
- Fall Protection
- Related: Personal Fall Arrest System, Guardrail, Competent Person
Systems and practices that prevent workers from falling from heights, including guardrails, safety nets, personal fall arrest, and warning lines. OSHA requires fall protection above specified heights on construction sites.
- Personal Fall Arrest System
- Related: Fall Protection, Competent Person
Equipment including a harness, lanyard, and anchor point that stops a worker's fall and limits forces on the body. It must be inspected before use and anchored to a suitable point.
- Competent Person
- Related: Fall Protection, Personal Fall Arrest System
A person capable of identifying existing and predictable hazards and authorized to take prompt corrective action. OSHA requires one for activities such as fall protection and scaffolding.
- Guardrail
- Related: Fall Protection, Competent Person
A barrier along an edge or opening to prevent falls, typically with a top rail, midrail, and toe board. It must meet height and strength requirements where workers are exposed to falls.