One Plan, Three Mines: Sorting Part 46 from Part 48

MSHA New Miner Training · Put your knowledge to work in context.

All case studies

One Plan, Three Mines: Sorting Part 46 from Part 48

You are the new safety director for a family-owned aggregates company with three sites: a surface limestone quarry producing 600,000 tons per year, an underground limestone mine entered by a decline with 22 miners, and a sand and gravel pit acquired three months ago. All three currently use the same 12-page training plan, which the previous director labeled 'Part 46.' The plan lists four competent persons, provides eight hours of annual refresher, and has no MSHA approval letter. Next month the company will hire 15 new miners and wants to train them all at the surface limestone quarry using this plan. Underground miners have been getting 24 hours of new miner training, but the plan contains no separate underground module. The owner asks whether one plan can cover all three sites, what must change before the hiring wave, and whether the lack of an approval letter is a problem.

1. Which of the three operations are subject to Part 46, and which are subject to Part 48? Explain the jurisdictional line and the consequence for the training plan.

Read the worked answer

Jurisdiction: Part 46 covers the surface limestone quarry and the sand and gravel pit because those are surface stone and sand-and-gravel operations listed in Part 46. The underground limestone mine is not Part 46; it is a Part 48 mine because it is underground. Consequence: A single Part 46 plan cannot govern the underground mine. The surface sites may use an operator-maintained Part 46 plan; the underground mine needs an MSHA-approved Part 48 plan. Training hours: Part 46 new miners need at least 4 hours before work and a total of at least 8 hours within 90 days; Part 48 underground new miners need 40 hours before work; annual refresher is 8 hours under both parts. The existing plan's 'Part 46' label is therefore misleading for the underground site.

2. The company wants to train the 15 new hires at the surface limestone quarry. What training hours and plan approvals must be in place before each new hire begins work at each site?

Read the worked answer

Before any new hire begins work at the surface limestone quarry or sand and gravel pit, the operator must provide the Part 46 initial 4 hours and have an operator-maintained plan on site. The remaining Part 46 hours (total at least 8) must be completed within 90 days. Before any new hire begins work at the underground limestone mine, the operator must complete the Part 48 40-hour new miner training under an MSHA-approved plan; 24 hours is not enough. Training at the surface quarry cannot be counted automatically toward the underground requirement unless the approved Part 48 plan incorporates it and it covers underground hazards. The company should separate the hiring cohorts and not train all 15 at one site under one plan.

3. What specific deficiencies in the existing plan would you flag for the underground mine, and what are the risks of continuing to use it?

Read the worked answer

Flag: (1) no MSHA-approved Part 48 plan for the underground mine; (2) 24 hours of new miner training is below the 40-hour underground requirement; (3) the plan does not identify underground-specific hazards, escapeways, ventilation, or ground control; (4) Part 48 training must be delivered by MSHA-approved instructors, while the plan names 'competent persons' in Part 46 language; (5) annual refresher content is not site-specific. Risks include MSHA citations under Part 48, invalidation of training records, and a withdrawal order if miners are assigned without required training. The operator should prepare a separate Part 48 plan and submit it to MSHA for approval before assigning anyone underground.