Question 1MSP programme management (content domains not enumerated in source)
In MSP, which governance body typically owns the programme mandate and holds ultimate accountability for the programme's alignment with corporate strategy?
- The Programme Office
- The Programme Board Correct answer.
- The Service Delivery team
- The Project Assurance function
Explanation
The Programme Board is the top-level governance forum, sponsored by the senior responsible owner, and is accountable for the programme mandate, strategic alignment and continued business justification. Other bodies support it operationally or provide assurance but do not own the mandate.
Question 2MSP programme management (content domains not enumerated in source)
Which MSP principle states that programmes must be shaped by and remain responsive to their strategic context rather than being applied as a fixed template?
- Envisioning and communicating a better future
- Remaining aligned with corporate strategy Correct answer.
- Adding value
- Leading change
Explanation
Remaining aligned with corporate strategy requires the programme to stay connected to the organisation's direction and adjust when that direction changes. The other principles address leadership, vision and benefit realisation, not contextual alignment.
Question 3MSP programme management (content domains not enumerated in source)
A programme has delivered its projects but the business areas have not yet embedded the new working practices. In MSP terms, what does this situation most clearly indicate?
- The programme has exceeded its tolerance for scope
- The programme has failed its tranche gate
- The programme should immediately close and release resources
- The programme has achieved its outcomes but not yet realised the benefits Correct answer.
Explanation
Outcomes are the new capabilities or states that projects deliver, while benefits are the measurable improvements that arise once outcomes are adopted and embedded. Delivering projects without adoption means outcomes exist but benefits are not yet realised.
Question 4MSP programme management (content domains not enumerated in source)
In MSP, what is the primary purpose of a Programme Blueprint?
- To document the audit findings from the last assurance review
- To describe the target operating state and the capabilities required to achieve it Correct answer.
- To record the detailed project schedule and resource assignments
- To list the risks transferred to suppliers under contract
Explanation
The Blueprint models the future state of the organisation, covering processes, organisation, technology and information, and identifies the capabilities needed to reach that state. It is a design artefact, not a schedule, audit record or risk register.
Question 5MSP programme management (content domains not enumerated in source)
Which document in MSP sets out the vision, the Blueprint summary and the benefits that justify investment, and is used to secure approval to proceed?
- The Benefits Profile
- The Business Case Correct answer.
- The Risk Register
- The Programme Mandate
Explanation
The Business Case is the decision-support document that brings together the vision, Blueprint summary, benefits, costs and risks to justify continued investment. The Mandate initiates the programme but is not the full justification.
Question 6MSP programme management (content domains not enumerated in source)
What distinguishes a programme from a portfolio in MSP terms?
- A programme coordinates related projects to deliver outcomes and benefits; a portfolio is the totality of an organisation's investment in change Correct answer.
- A programme is temporary while a portfolio is permanent in every organisation
- A programme is always larger in budget than a portfolio
- A portfolio delivers benefits while a programme only delivers outputs
Explanation
A programme is a temporary, flexible organisation created to coordinate related projects and transformational activities to deliver outcomes and benefits of strategic importance. A portfolio is the coordinated collection of all change investment, providing the strategic context in which programmes sit.
Question 7MSP programme management (content domains not enumerated in source)
A programme manager needs a single view of the major threats and opportunities facing the programme, with owners and response actions. Which MSP information product should be used?
- The Quality Register
- The Benefits Map
- The Issue Register
- The Risk Register Correct answer.
Explanation
The Risk Register records each risk with its cause, effect, owner, assessment and agreed response, giving the consolidated view of threats and opportunities. Other registers track issues, benefits or quality actions rather than risk.
Question 8MSP programme management (content domains not enumerated in source)
Which MSP principle emphasises that programmes must define and measure the value they add, ensuring that change is worthwhile?
- Leading change
- Remaining aligned with corporate strategy
- Adding value Correct answer.
- Learning from experience
Explanation
Adding value requires the programme to demonstrate that its activities and investments produce worthwhile benefit relative to cost and disruption. The other principles concern strategic alignment, leadership and organisational learning.
Question 9MSP programme management (content domains not enumerated in source)
During the Defining a Programme process, a team is identifying the projects and activities needed to build the capabilities in the Blueprint. Which output are they primarily producing?
- The Benefits Realisation Plan
- The Vision Statement
- The Programme Plan Correct answer.
- The Communication Plan
Explanation
Defining a Programme produces the Programme Plan, which sets out the projects, activities, tranches and dependencies needed to deliver the Blueprint. The Vision and Benefits Realisation Plan are also created but are distinct products with different purposes.
Question 10MSP programme management (content domains not enumerated in source)
What is the purpose of a tranche in MSP?
- To group work into manageable delivery steps, each ending in a review of progress and continued viability Correct answer.
- To separate projects from business-as-usual activities permanently
- To divide the programme budget equally across financial years
- To define the programme's permanent organisational structure
Explanation
A tranche is a group of projects and activities delivered together, ending at a tranche boundary where progress, benefits and continued viability are reviewed. It provides control points rather than a budgetary or structural division.
Question 11MSP programme management (content domains not enumerated in source)
A programme's Business Case shows that forecast benefits have fallen below the threshold for continued investment. What is the most appropriate MSP response?
- Instruct the projects to increase scope to recover the benefits
- Escalate to the Programme Board for a decision to continue, change or stop the programme Correct answer.
- Continue delivering projects unchanged until the next scheduled tranche review
- Remove the underperforming benefits from the Benefits Register
Explanation
The Business Case is a living document reviewed at tranche boundaries and when material change occurs. A significant fall in forecast benefits is a decision point for the Programme Board, which may re-scope, re-plan or close the programme.
Question 12MSP programme management (content domains not enumerated in source)
In MSP, what is the role of the Senior Responsible Owner (SRO)?
- To provide day-to-day management of projects and their deliverables
- To own the programme's business case and be accountable for delivery of the outcomes and benefits Correct answer.
- To independently audit the programme's compliance with standards
- To chair the programme office and manage its staff
Explanation
The SRO is accountable for the programme's success, owning the Business Case and ensuring outcomes and benefits are delivered. Day-to-day project delivery, office management and independent audit sit with other roles.
Question 13MSP programme management (content domains not enumerated in source)
A programme is designing how it will move the organisation from current to future state, including communication and readiness activities. Which MSP process covers this?
- Delivering the Capability
- Managing the Tranches
- Closing a Programme
- Realising the Benefits Correct answer.
Explanation
Realising the Benefits covers the transition from projects into business operations, including preparing the business, managing readiness and measuring benefits. Managing the Tranches governs delivery, Delivering the Capability builds outputs, and Closing a Programme ends the programme.
Question 14MSP programme management (content domains not enumerated in source)
Which statement best describes the relationship between a benefits map and the Blueprint in MSP?
- The benefits map replaces the Blueprint once the programme is approved
- The Blueprint is a subset of the benefits map showing only financial benefits
- The benefits map records risks while the Blueprint records issues
- The benefits map shows the dependency chain from outputs through outcomes to benefits, while the Blueprint describes the future operating state Correct answer.
Explanation
The benefits map traces how project outputs enable outcomes and how outcomes deliver benefits, while the Blueprint models the target operating state and required capabilities. They are complementary artefacts, not substitutes.
Question 15MSP programme management (content domains not enumerated in source)
A programme has a dependency where the new customer database must be live before the sales training project can begin. How should this be managed in MSP?
- Convert it into a benefit in the Benefits Register
- Treat it as a project-level issue for the sales training project only
- Ignore it because dependencies are managed only within projects
- Record it in the Programme Plan as a dependency and monitor it through tranche governance Correct answer.
Explanation
Inter-project dependencies are captured in the Programme Plan and actively managed through tranche governance and progress reporting. Handling them only at project level risks the programme discovering the constraint too late.
Question 16MSP programme management (content domains not enumerated in source)
What does the MSP concept of 'capability' refer to in the context of the Blueprint?
- The ability of the organisation to perform a function or achieve an outcome, delivered through a combination of processes, people, information and technology Correct answer.
- The authority delegated to the Programme Board
- The financial capacity of the programme to fund its projects
- The technical skill level of individual project managers
Explanation
Capabilities are the abilities the organisation needs in its future state, delivered through changes to processes, organisation, technology and information described in the Blueprint. They are organisational abilities, not funding, individual skills or governance authority.
Question 17MSP programme management (content domains not enumerated in source)
Which MSP principle addresses the need to capture lessons during the programme and feed them back into the organisation and future work?
- Envisioning and communicating a better future
- Remaining aligned with corporate strategy
- Adding value
- Learning from experience Correct answer.
Explanation
Learning from experience requires the programme to seek out, capture and apply lessons throughout its life, sharing them beyond the programme. The other principles concern vision, value and strategic alignment.
Question 18MSP programme management (content domains not enumerated in source)
A programme is approaching closure but some benefits are only expected to be realised by the business two years later. What is the appropriate MSP treatment?
- Remove the unrealised benefits from the Business Case at closure
- Delay closure until all benefits have been realised
- Close the programme and transfer responsibility for realising and measuring the remaining benefits to the business Correct answer.
- Extend the programme indefinitely and keep all staff in place
Explanation
Closing a Programme includes handing over responsibility for benefits realisation and measurement to the business, with agreed arrangements for tracking. Keeping the programme open until every benefit is realised is not the intent of closure.
Question 19MSP programme management (content domains not enumerated in source)
What is the main purpose of a programme's stakeholder engagement strategy?
- To define the technical architecture of the programme's IT systems
- To record the audit trail of board decisions
- To list the names of all staff who will be made redundant
- To identify stakeholders, assess their influence and interest, and plan how to engage them to support programme outcomes Correct answer.
Explanation
Stakeholder engagement identifies who is affected or influential and sets out planned approaches to communication and involvement in support of the programme's objectives. It is not a redundancy list, architecture document or decision log.
Question 20MSP programme management (content domains not enumerated in source)
During Managing the Tranches, a project reports that it will exceed its agreed time tolerance. What should happen first under MSP governance?
- The programme office updates the Benefits Register
- The project manager silently re-baselines the project plan
- The SRO closes the programme
- The project manager escalates the forecast breach to the programme for a decision on corrective action Correct answer.
Explanation
Tolerance breaches are escalated to the next level of management for a decision, in line with the principle that authority is delegated within defined limits. Silent re-baselining removes transparency, and closing the programme is disproportionate.
Question 21MSP programme management (content domains not enumerated in source)
Which statement best explains why MSP treats the Business Case as an iterative product rather than a one-off approval document?
- Because the finance department requires annual paperwork
- Because the Blueprint changes only once at the start
- Because programmes are long and uncertain, so benefits, costs and risks must be reassessed at tranche boundaries to confirm continued viability Correct answer.
- Because the Business Case must be rewritten by each project manager
Explanation
Programmes operate over extended periods with evolving risk and benefit forecasts, so the Business Case is reviewed and updated at tranche boundaries and on material change to confirm the investment remains justified. This is a governance need, not a bureaucratic formality.
Question 22MSP programme management (content domains not enumerated in source)
A programme's Quality and Assurance strategy distinguishes between quality planning, quality control and assurance. Which activity belongs to assurance rather than quality control?
- Independent review of whether the programme's governance and processes are fit for purpose Correct answer.
- Inspecting a delivered product against its acceptance criteria
- Correcting a defect found during a project review
- Recording the results of a product test in the Quality Register
Explanation
Assurance provides independent scrutiny of the programme's governance, processes and overall health, whereas quality control checks specific products against defined criteria. Testing, recording results and fixing defects are control activities.
Question 23MSP programme management (content domains not enumerated in source)
A programme's Vision Statement is vague and stakeholders interpret it differently. Which MSP principle is most directly undermined?
- Remaining aligned with corporate strategy
- Learning from experience
- Envisioning and communicating a better future Correct answer.
- Adding value
Explanation
Envisioning and communicating a better future requires a clear, compelling and shared picture of the target state that stakeholders understand consistently. Ambiguity in the Vision directly undermines this principle, even if alignment and value remain intact.
Question 24MSP programme management (content domains not enumerated in source)
A programme has strong project delivery but weak engagement with business operations, and benefits are not being adopted. Which MSP principle most directly addresses this weakness?
- Leading change Correct answer.
- Adding value
- Envisioning and communicating a better future
- Learning from experience
Explanation
Leading change emphasises visible leadership and active engagement of the business in adopting the change, which is exactly what is missing when operations do not take up the new capability. Adding value, learning and vision do not directly address the leadership and engagement gap.
Question 25MSP programme management (content domains not enumerated in source)
In MSP, how should the programme's information management approach treat the relationship between the Programme Plan and project plans?
- Project plans are not used once the Programme Plan exists
- The Programme Plan consolidates project plans and adds programme-level dependencies, tranches and controls; project plans remain the detailed delivery plans Correct answer.
- The Programme Plan must contain every project task in full detail
- Project plans are owned by the Programme Board and cannot be changed
Explanation
The Programme Plan is a higher-level consolidation that adds tranche structure, cross-project dependencies and programme controls, while project plans retain the detailed delivery content. This layered approach keeps information proportionate and avoids duplication.
Question 26MSP programme management (content domains not enumerated in source)
In MSP, which governance body is accountable for the overall direction and success of a programme and typically chairs the programme board?
- The Business Change Manager
- The Programme Manager
- The Senior Responsible Owner Correct answer.
- The Project Assurance function
Explanation
MSP assigns accountability for programme success to the Senior Responsible Owner, who chairs the programme board and provides the single point of accountability to the sponsoring group. The Programme Manager runs the programme day to day but does not hold that ultimate accountability.
Question 27MSP programme management (content domains not enumerated in source)
Which MSP principle requires programmes to be driven by the delivery of benefits to the organisation rather than by the completion of projects for their own sake?
- Envisioning and communicating a better future
- Remaining aligned with corporate strategy
- Business-led Correct answer.
- Leading change
Explanation
The Business-led principle states that programmes must be driven by the organisation's needs and the delivery of benefits, so projects are only justified by the value they release. It keeps focus on outcomes rather than on activity.
Question 28MSP programme management (content domains not enumerated in source)
Which MSP principle is most directly demonstrated when a programme board actively reviews progress against the programme's Business Case at each tranche boundary?
- Learning from experience
- Remaining aligned with corporate strategy
- Adding value Correct answer.
- Designing and delivering a coherent set of projects
Explanation
Adding value requires the programme to demonstrate that it continues to be worth the investment, which is why the Business Case is revisited and challenged at tranche boundaries. Reviewing it at those points is the practical expression of that principle.
Question 29MSP programme management (content domains not enumerated in source)
What is the primary purpose of the Programme Brief in MSP?
- To secure approval and resources to run the Defining a Programme process Correct answer.
- To document lessons learned from previous programmes for the sponsoring group
- To authorise the start of the first project in the programme
- To record the detailed benefits realisation plan for the first tranche
Explanation
The Programme Brief is the early document used to obtain the mandate to proceed into Defining a Programme, capturing the initial vision, outline Business Case and expected benefits. It is deliberately high level because detail is developed during the defining process.
Question 30MSP programme management (content domains not enumerated in source)
Which product in MSP describes the capabilities that the future state will need, the changes required to ways of working, and how the transition will be achieved?
- The Programme Plan
- The Benefits Profile
- The Benefits Map
- The Blueprint Correct answer.
Explanation
The Blueprint is the model of the future organisation, describing the target operating model, the capabilities required and the transition states. It provides the reference point against which projects and benefits are aligned.
Question 31MSP programme management (content domains not enumerated in source)
Which process in MSP covers the activities of delivering the capability incrementally through projects and work packages while maintaining governance control?
- Delivering the Capability Correct answer.
- Defining a Programme
- Identifying a Programme
- Managing the Tranches
Explanation
Delivering the Capability is the process where projects are commissioned, coordinated and delivered to build the capability described in the Blueprint. Managing the Tranches provides the governance envelope around it rather than the delivery activity itself.
Question 32MSP programme management (content domains not enumerated in source)
In MSP, what is the purpose of the programme's risk management approach?
- To record only risks that affect the Business Case
- To ensure every project follows an identical risk register format
- To define how risks and issues will be identified, assessed, owned and escalated across the programme Correct answer.
- To transfer all programme risk to delivery suppliers
Explanation
The risk management approach sets out the standards, processes and responsibilities for managing risk and issues consistently across projects and the programme. It enables aggregation and escalation rather than imposing uniformity for its own sake.
Question 33MSP programme management (content domains not enumerated in source)
Which statement best describes the relationship between the Vision Statement and the Blueprint in MSP?
- The Blueprint is produced first and the Vision Statement is derived from it at closure
- The Vision Statement describes the desired future in inspirational terms, while the Blueprint describes how that future will operate Correct answer.
- The Vision Statement is a detailed schedule and the Blueprint is its summary
- The two products are alternatives and a programme should choose one
Explanation
The Vision Statement communicates the end state in a compelling, accessible way, whereas the Blueprint provides the detailed model of the future operating state needed to plan delivery. They are complementary, with the Blueprint giving substance to the vision.
Question 34MSP programme management (content domains not enumerated in source)
A Business Change Manager reports that operational staff are resisting a new way of working introduced by a completed project. Which MSP role is accountable for ensuring the change is embedded and benefits are realised?
- The Programme Manager
- The Senior Responsible Owner
- The Programme Office
- The Business Change Manager Correct answer.
Explanation
The Business Change Manager is accountable for preparing the business, embedding the change and tracking benefit realisation in the operational area. Resistance to new ways of working is a transition issue that falls squarely within that accountability.
Question 35MSP programme management (content domains not enumerated in source)
During Managing the Tranches, a project forecasts that a benefit will be realised later than planned but the capability will still be delivered within the tranche. What is the most appropriate programme-level response?
- Close the project early because the benefit is delayed
- Escalate directly to the sponsoring group without involving the programme board
- Review the effect on the Benefits Map and Business Case and agree revised realisation arrangements with the benefit owner Correct answer.
- Reallocate the project's budget to another project without further review
Explanation
A delay in benefit realisation is assessed against the Benefits Map and Business Case to understand the impact on the overall case and on dependent benefits. The benefit owner then agrees revised measurement and realisation arrangements through governance.
Question 36MSP programme management (content domains not enumerated in source)
A programme is designing its assurance arrangements. Which activity belongs to programme assurance rather than to project quality control?
- Testing software modules before release
- Reviewing whether the programme's governance and controls are fit for purpose and providing an independent view to the board Correct answer.
- Inspecting completed deliverables against acceptance criteria
- Signing off a work package as complete
Explanation
Assurance provides independent scrutiny of whether the programme's arrangements and controls are adequate, reporting to governance. Quality control, by contrast, checks that specific deliverables meet defined criteria.
Question 37MSP programme management (content domains not enumerated in source)
Which product in MSP is used to define what success looks like for a specific benefit, including its owner, measures and the capabilities it depends on?
- The Risk Register
- The Tranche Plan
- The Benefits Profile Correct answer.
- The Programme Brief
Explanation
The Benefits Profile captures the detail needed to manage an individual benefit, including its owner, the measures and baselines, and the capabilities and projects it depends on. It supports the Benefits Map by adding the management detail for each benefit.
Question 38MSP programme management (content domains not enumerated in source)
A programme has a dependency in which the new data warehouse must be operational before the analytics project can deliver its reporting capability. How should this dependency be managed in MSP?
- Record it only in the analytics project's risk log
- Capture it in the programme dependency arrangements, agree it with both project managers and monitor it through tranche governance Correct answer.
- Remove the dependency once both projects are authorised
- Assume the data warehouse project will inform the analytics project when ready
Explanation
Inter-project dependencies are programme-level information that must be recorded, agreed between the affected parties and actively monitored through governance. This allows the programme to intervene if either side slips.
Question 39MSP programme management (content domains not enumerated in source)
What distinguishes a programme's stakeholder engagement strategy from a simple communications plan in MSP terms?
- It replaces the need for a Vision Statement
- It lists the dates of project board meetings
- It sets out how stakeholders will be identified, analysed, engaged and their concerns addressed to support the change Correct answer.
- It focuses only on internal staff audiences
Explanation
The stakeholder engagement strategy addresses who the stakeholders are, how they are affected, and how the programme will engage them to build commitment and manage resistance. Communications activity is one part of that broader engagement approach.
Question 40MSP programme management (content domains not enumerated in source)
In MSP, how does the programme's information management approach treat the Programme Plan and project plans?
- Project plans are independent documents that need no programme oversight
- The Programme Plan is produced only at closure as a record of what happened
- The Programme Plan sets the programme-level schedule and controls, and project plans must align with and report against it Correct answer.
- Project plans replace the Programme Plan once delivery starts
Explanation
The Programme Plan provides the programme-level schedule of tranches, projects and key milestones, and project plans are aligned to it so progress can be aggregated and controlled. This alignment is what allows governance to see the whole picture.
Question 41MSP programme management (content domains not enumerated in source)
A programme's Quality and Assurance strategy defines quality planning, quality control and assurance. Which statement correctly matches an activity to its purpose?
- Quality planning defines the standards and criteria that deliverables must meet Correct answer.
- Assurance tests individual deliverables against acceptance criteria
- Quality control provides independent scrutiny to the sponsoring group
- Quality control sets the programme's overall standards framework
Explanation
Quality planning determines the standards, criteria and responsibilities that will govern quality across the programme and its projects. Control then checks conformance, while assurance independently reviews whether the arrangements are working.
Question 42MSP programme management (content domains not enumerated in source)
During Defining a Programme, the team is refining the Blueprint. Which input is most important for ensuring the Blueprint reflects what the organisation actually needs?
- The programme's vision and the corporate strategy it must align with Correct answer.
- The project managers' resource availability
- The supplier contract payment schedule
- The programme office's filing conventions
Explanation
The Blueprint must describe a future state that delivers the vision and remains aligned with corporate strategy, so those are the primary reference points during design. Delivery and administrative details are secondary to that strategic fit.
Question 43MSP programme management (content domains not enumerated in source)
A programme's sponsoring group wants confidence that the programme remains aligned with a newly revised corporate strategy. Which action best reflects the relevant MSP principle?
- Defer any review until the next scheduled programme closure
- Review the Blueprint, Business Case and benefits against the revised strategy and agree any changes through governance Correct answer.
- Delegate the review to the programme office without board involvement
- Freeze the Blueprint to protect delivery stability
Explanation
Remaining aligned with corporate strategy requires the programme to reassess its Blueprint, Business Case and benefits when the strategy changes, and to agree adjustments through governance. Stability of delivery must not override continued strategic fit.
Question 44MSP programme management (content domains not enumerated in source)
A programme is preparing for a tranche boundary. Which set of activities is most consistent with the end-of-tranche review in MSP?
- Closing all projects and disbanding the programme board
- Re-baselining every project without reference to the Blueprint
- Confirming benefits realised to date, reviewing the Business Case and approving the next tranche plan Correct answer.
- Transferring remaining benefits to the programme office
Explanation
At the end of a tranche the programme assesses progress, confirms what has been delivered and realised, reassesses the Business Case and seeks approval for the next tranche. This is the mechanism that keeps investment under review.
Question 45MSP programme management (content domains not enumerated in source)
Which statement best explains why MSP treats the Business Case as a living product that is reviewed throughout the programme?
- Because the balance of costs, risks and benefits changes as delivery and the external environment evolve Correct answer.
- Because it removes the need for a Benefits Map
- Because it transfers accountability for benefits to the finance function
- Because funding bodies require a document to be filed at every meeting
Explanation
Costs, risks, benefits and strategic context change over the life of a programme, so the Business Case must be updated and challenged to confirm the investment still represents value. It is a decision tool, not a one-off approval document.
Question 46MSP programme management (content domains not enumerated in source)
A programme is closing and several benefits will only be realised by the business over the following two years. What should the programme put in place before disbanding?
- Cancel the outstanding benefits because the programme no longer exists
- Hand all benefit tracking to the delivery suppliers
- Transfer benefit ownership and measurement arrangements to the business with clear accountability and reporting Correct answer.
- Retain the full programme team until every benefit is realised
Explanation
MSP recognises that benefits often continue after the programme closes, so ownership, measures and reporting arrangements must be formally transferred to the business. This ensures benefits remain actively managed once programme governance ends.
Question 47MSP programme management (content domains not enumerated in source)
A programme has delivered its projects well but operational adoption is weak and benefits are not materialising. Which analysis best reflects MSP's view of where the deficiency lies?
- In the sponsoring group's meeting frequency
- In the project managers' technical competence, which is the sole determinant of benefits
- In the programme office's document control procedures
- In the programme's management of the transition and business change, which sits with the Business Change Manager Correct answer.
Explanation
MSP separates the delivery of capability from the realisation of benefits, placing responsibility for preparing the business and embedding change with the Business Change Manager. Strong project delivery without transition management typically produces exactly this outcome.
Question 48MSP programme management (content domains not enumerated in source)
A programme board is considering a change request that would alter a capability in the Blueprint and affect two projects already in delivery. What is the most appropriate MSP treatment?
- Approve it locally within one project to avoid delay
- Refer it to the suppliers to decide
- Reject it because Blueprints cannot change after Defining a Programme
- Assess the impact on the Blueprint, Business Case, dependencies and affected projects, then decide through the programme's change control Correct answer.
Explanation
Changes affecting the Blueprint and multiple projects must be assessed for their impact across the programme and decided through programme-level change control. This protects coherence between projects and continued justification of the investment.
Question 49MSP programme management (content domains not enumerated in source)
In MSP, how should the programme's approach to lessons differ from a simple post-implementation review at closure?
- Lessons should be captured and acted upon throughout the programme and shared with the wider organisation as they arise Correct answer.
- Lessons should be restricted to the programme office for confidentiality
- Lessons should only be recorded once all projects are complete
- Lessons should focus solely on supplier performance
Explanation
Learning from experience is a continuous principle: lessons are captured as work proceeds, applied to current activity and shared so the organisation benefits. A closure-only review would be too late to improve the programme itself.
Question 50MSP programme management (content domains not enumerated in source)
A programme's Vision Statement is interpreted differently by different stakeholder groups. Which MSP principle is most directly compromised, and what is the appropriate corrective action?
- Remaining aligned with corporate strategy; the strategy should be changed
- Envisioning and communicating a better future; the vision should be clarified and communicated consistently Correct answer.
- Adding value; the Business Case should be rewritten
- Designing a coherent set of projects; the project briefs should be reissued
Explanation
A vision that stakeholders read differently fails the principle of envisioning and communicating a better future. The corrective action is to sharpen the vision and communicate it consistently so a shared understanding is established.