Solar Farm on Garigue: Overriding Interest and Public Participation

MATSEC SEC European Studies · Put your knowledge to work in context.

All case studies

Solar Farm on Garigue: Overriding Interest and Public Participation

A 48 MW solar photovoltaic farm is proposed on 60 hectares of garigue in Gozo, adjacent to a Natura 2000 site designated for a rare endemic orchid and for steppic habitat. The land is not inside a 'renewables acceleration area' in Malta's draft designation. The developer argues that under RED III the project enjoys a presumption of overriding public interest as a renewable energy project, and that the permit must be decided within 24 months. The local council has received a petition with 1,200 signatures opposing the project. An environmental NGO has requested full access to the developer's bird and flora surveys. The government wants the project to count towards its 2030 renewable target, and the planning authority must decide how to run public participation. Three alternative sites exist, all with lower grid capacity. The residents' group has threatened to challenge any permit in court and to complain to the European Commission.

1. Can the developer rely on 'overriding public interest' to justify damage to a Natura 2000 site? Explain what must still be shown before a permit can be issued.

Read the worked answer

Not automatically. RED III provides that renewable energy projects are presumed to be in the overriding public interest for permitting purposes, and that presumption can be used in a Habitats Directive assessment. It does not replace the sequence of tests.

First, an appropriate assessment under Article 6(3): if adverse effects on the integrity of the site cannot be excluded, the project may proceed only under Article 6(4) - no less damaging alternatives, benefits that clearly outweigh the harm, and compensatory measures secured. Because the garigue habitat type is a priority habitat, the Commission's opinion would also be required. The three alternative sites must be examined and reasoned rejection given for each, or the 'no alternatives' test fails.

The 24-month deadline governs the permitting decision; it does not licence skipping the assessment. The petition does not decide the merits, but it is potential evidence in a challenge, and the NGO's surveys are exactly what makes the assessment defensible. A candidate who simply says 'renewables override nature' has missed the structure of Article 6.

2. Advise the planning authority on the minimum public participation it must provide to be legally and politically defensible, given the petition and the survey request.

Read the worked answer

Legal floor: early and effective public participation before the decision, with the application, the appropriate assessment and the developer's surveys available for inspection at least a month before any hearing; a reasonable period to comment (three to four weeks is defensible at this scale); and reasoned responses to substantive points. Aarhus obligations include access to environmental information on request and access to justice for NGOs and residents, so refusing the bird and flora surveys is the single riskiest choice available.

Beyond the minimum, structure two stages: a technical session for the NGO and residents' group with the developer's ecologist present, then a public hearing in Gozo, with a published decision document explaining why the alternatives were rejected and how compensation was designed.

The 1,200 signatures do not settle the planning merits, but ignoring them invites judicial review and a complaint to the Commission, which can open infringement proceedings if the Habitats Directive is applied incorrectly. Participation is cheaper than litigation.