The island generates about 260,000 tonnes of municipal solid waste a year. The only engineered landfill has 2.5 years of permitted capacity left. Current performance: 74% landfilled, 14% recycled, 12% composted or otherwise recovered. Organic waste is 38% of the total; construction and demolition waste is managed separately. The government is considering a €190 million incinerator with a 25-year contract, capacity 160,000 tonnes/year, generating 14 MW of electricity, producing 22% ash by mass, and requiring landfill for ash. Alternatively, a circular-economy package would cost €70 million: separate collection of organics, a composting plant for 90,000 tonnes/year, recycling upgrades to reach 50%, and a residual landfill extension. The EU requires 55% municipal recycling by 2025 and limits landfilling of biodegradable waste. Residents near the proposed incinerator oppose it; the finance ministry fears contract lock-in. The decision must be made this year.

1. Using the waste hierarchy, assess whether the incinerator is the best option.

Read the worked answer

The waste hierarchy places prevention first, then reuse, recycling, recovery and disposal. Incineration is recovery, below recycling. It can treat residual waste and generate 14 MW, but a 25-year contract for 160,000 tonnes/year may lock in waste generation and compete with recycling for combustible material. Organic waste is 38% of 260,000 = 98,800 tonnes/year; the circular package moves this up the hierarchy through separate collection and composting. The incinerator does not by itself improve the 14% recycling rate, and at full capacity it produces 22% ash = 35,200 tonnes/year that still needs landfill. Therefore the incinerator is not automatically the best option. It could be a residual treatment after recycling, but it should not substitute for separate collection and composting.

2. Calculate the net landfill tonnage under the incinerator at full capacity with current recycling, and under the circular package at 50% recycling/composting. Which meets the EU targets?

Read the worked answer

Incinerator scenario: current recycling is 14% of 260,000 = 36,400 tonnes. Incinerator burns 160,000 tonnes and produces 35,200 tonnes of ash. Unburned residual to landfill is 260,000 − 36,400 − 160,000 = 63,600 tonnes. Net landfill is 63,600 + 35,200 = 98,800 tonnes. Circular package: 50% recycling/composting = 130,000 tonnes diverted, so landfill is 130,000 tonnes. The incinerator sends less to landfill, but recycling stays at 14%, far below the 55% EU target. The circular package reaches 50%, still 5 percentage points short, so an extra 13,000 tonnes must be captured. Neither option alone meets both the recycling and landfill-reduction goals; the best route is high recycling plus a smaller residual treatment or landfill extension. The main uncertainty is the actual capture rate of organics and recyclables.

3. Recommend a decision with conditions, addressing contract lock-in and public opposition.

Read the worked answer

Recommend the circular-economy package first, with a residual landfill extension to cover the transition. Do not sign a 25-year take-or-pay incinerator contract now. Conditions: roll out separate organics collection, secure a market for compost, meet annual recycling milestones towards 55%, and publish landfill tonnage. If residual waste still exceeds capacity after recycling, procure a smaller incinerator with a shorter contract and a capacity cap, so it cannot compete with recycling. Address public opposition through an independent health and emissions assessment, a community liaison group and monitoring of ash and air quality. This sequence follows the waste hierarchy, avoids lock-in and keeps the island compliant with EU targets.