QETPP study materials
QETPP study resources

QETPP key terms

QETPP · Get comfortable with the vocabulary.

Insulation resistance test

A DC voltage is applied between an insulated conductor and ground (or between windings) to measure resistance; low values suggest moisture, contamination, or degradation.

Related: Polarization index, Dielectric withstand test
Polarization index

Ratio of insulation resistance at 10 minutes to 1 minute; indicates insulation condition and moisture susceptibility; typically >2 acceptable for rotating machines, but limits vary by class.

Related: Insulation resistance test, Step voltage test
Dielectric withstand test

Applies a specified AC or DC overvoltage for a set time to verify insulation can withstand transient or operating stress without breakdown; can be destructive if misapplied.

Related: Insulation resistance test, Partial discharge test
Step voltage test

Applies incremental DC test voltages in steps and records insulation resistance at each step; a downward trend can reveal insulation weakness that a single-voltage test misses.

Related: Insulation resistance test, Polarization index
Contact resistance test

Injects a high DC current through closed contacts and measures the micro-ohm voltage drop; compares results to manufacturer limits or previous baseline to detect pitting, contamination, or loose joints.

Related: Circuit breaker timing test, Thermographic survey
Circuit breaker timing test

Records open/close times, simultaneity, bounce, and travel of breaker contacts using a timing analyzer; verifies mechanical and trip-coil performance against manufacturer specifications.

Related: Contact resistance test, Protective relay
Protective relay

A device that monitors current, voltage, frequency, or other quantities and initiates trip or alarm signals when settings are exceeded; coordination depends on correct settings and testing.

Related: Secondary injection test, Coordination study
Secondary injection test

Applies simulated current and voltage signals to relay terminals to verify pickup, timing, and logic without energizing primary equipment; requires accurate source and lead connections.

Related: Protective relay, Primary injection test
Primary injection test

Injects current through the primary conductor and current transformer to verify the entire protection chain, including CT ratio, wiring, relay response, and trip circuit.

Related: Secondary injection test, Current transformer ratio and polarity test
Current transformer ratio and polarity test

Verifies the turns ratio and relative polarity of a current transformer by injecting a known primary or secondary signal and measuring the output; errors affect metering and protection.

Related: Primary injection test, Burden test
Burden test

Measures the connected secondary load (VA and impedance) on a current transformer to ensure it does not exceed the CT's rated burden, which could cause saturation and protection misoperation.

Related: Current transformer ratio and polarity test, Secondary injection test
Coordination study

Analyzes protective device time-current characteristics to select settings that isolate faults with minimal outage while preserving upstream selectivity and limiting equipment damage.

Related: Protective relay, Short-circuit study
Short-circuit study

Calculates available fault currents at each bus under defined system conditions; results set equipment ratings and protective device interrupting requirements.

Related: Coordination study, Arc flash study
Arc flash study

Estimates incident energy and arc flash boundary at working distances, enabling selection of PPE and labeling under standards such as NFPA 70E and IEEE 1584.

Related: Short-circuit study, Lockout/tagout
Lockout/tagout

A documented procedure that isolates energy sources, applies locks and tags, and verifies de-energization before work; prevents unexpected energization or release of stored energy.

Related: Arc flash study, Verification of de-energization
Verification of de-energization

Confirms a circuit is at zero energy by testing with a known-good voltage detector, checking all conductors and phases, and re-testing the detector after use.

Related: Lockout/tagout, Personal protective equipment
Personal protective equipment

Clothing and equipment such as arc-rated garments, face shields, gloves, and hearing protection selected from an arc flash and shock risk assessment to reduce injury severity.

Related: Arc flash study, Lockout/tagout
Transformer turns ratio test

Applies a known voltage to one winding and measures the induced voltage on another to verify turns ratio and polarity; deviations can indicate shorted turns or tap problems.

Related: Sweep frequency response analysis, Insulation resistance test
Sweep frequency response analysis

Compares transformer winding impedance over a range of frequencies to a baseline; shifts in the signature can indicate winding deformation, core movement, or bushing issues.

Related: Transformer turns ratio test, Dissolved gas analysis
Dissolved gas analysis

Samples insulating oil and measures dissolved gases; gas concentrations and ratios help diagnose overheating, arcing, partial discharge, or paper degradation in oil-filled transformers.

Related: Sweep frequency response analysis, Partial discharge test
Partial discharge test

Detects small electrical discharges within insulation by measuring high-frequency current pulses, acoustic signals, or electromagnetic emissions; PD can precede insulation failure.

Related: Dielectric withstand test, Dissolved gas analysis
Power factor/tan delta test

Measures dielectric losses in insulation as the ratio of resistive to capacitive current; increases can indicate moisture, contamination, or aging in bushings and windings.

Related: Insulation resistance test, Partial discharge test
Thermographic survey

Uses an infrared camera to find abnormal temperature rises in energized equipment; hot connections, overloads, and phase imbalances appear as thermal anomalies compared with similar components.

Related: Contact resistance test, Power quality analysis
Power quality analysis

Measures voltage sags, swells, harmonics, transients, and unbalance over time to diagnose equipment misoperation and verify compliance with standards such as IEEE 519.

Related: Thermographic survey, Harmonic distortion
Harmonic distortion

Deviation of a voltage or current waveform from a pure sine wave, quantified by total harmonic distortion (THD); high THD can overheat transformers, motors, and neutral conductors.

Related: Power quality analysis, Power factor/tan delta test
Ground grid testing

Measures resistance to remote earth of a grounding system, often by fall-of-potential or clamp-on methods; low resistance limits step and touch voltages during faults.

Related: Fall-of-potential test, Soil resistivity test
Fall-of-potential test

A three-point method that injects current into a ground electrode and measures voltage at varied probe spacings to determine earth resistance, avoiding the influence of nearby electrodes.

Related: Ground grid testing, Soil resistivity test
Soil resistivity test

Uses the Wenner four-pin method or similar to measure earth resistivity at depth; results inform ground grid design and electrode spacing.

Related: Ground grid testing, Fall-of-potential test
Battery capacity test

Discharges a stationary battery at a constant load to a defined end voltage and compares delivered capacity with rated ampere-hours; identifies aging cells and verifies backup time.

Related: Measurement uncertainty, Calibration
Calibration

Compares an instrument's indication with a reference standard of known uncertainty and documents the deviation; adjusts or assigns correction factors when required.

Related: Measurement uncertainty, Traceability
Measurement uncertainty

A quantified range around a measured value that accounts for instrument accuracy, resolution, environmental effects, and procedure; it determines whether results meet tolerances.

Related: Calibration, Traceability
Traceability

An unbroken chain of calibrations linking an instrument's measurements to national or international standards, each step documented with stated uncertainty.

Related: Calibration, Measurement uncertainty
As-found/as-left data

Test results recorded before and after adjustment or repair; as-found shows equipment condition at arrival, as-left shows condition after work and supports acceptance decisions.

Related: Baseline, Acceptance test
Acceptance test

A defined set of measurements and functional checks performed before energization or handover to confirm equipment meets specifications, standards, and contract requirements.

Related: Commissioning, As-found/as-left data
Commissioning

The process of verifying and documenting that installed systems operate safely and meet design intent, including component tests, functional tests, and integrated system tests.

Related: Acceptance test, Functional test
Functional test

Operates equipment through its intended control sequences and interlocks to confirm correct response, often including trip circuits, alarms, and remote indications.

Related: Commissioning, Protective relay
Baseline

A reference set of measurements or performance data taken when equipment is known to be in good condition; later results are compared to it to detect trends.

Related: As-found/as-left data, Trend analysis
Trend analysis

Plots test results over time to distinguish normal aging from sudden deterioration; requires consistent test methods, conditions, and calibrated instruments.

Related: Baseline, Dissolved gas analysis
NETA ATS

The InterNational Electrical Testing Association's Acceptance Testing Specifications, which define recommended tests and tolerances for electrical power equipment and systems.

Related: Acceptance test, Calibration