RFP definition
A solicitation that states requirements and invites vendors to propose a solution, technical approach, and price. Used when the buyer cannot fully specify the solution in advance.
RFI purpose
A market research tool that gathers vendor capabilities and pricing information without creating an award obligation. Responses cannot be used to disqualify a vendor from a later solicitation.
RFQ vs RFP
An RFQ is price-focused and used for well-defined goods; an RFP evaluates technical approach and past performance as well as price. Choosing wrongly distorts competition.
Evaluation weights rule
Published weights must sum to 100 percent and appear in the RFP itself. Changing criteria or weights after release creates protest exposure and undermines the award defensibility.
Addendum function
An addendum is the only formal channel for changing RFP requirements. Verbal answers and informal emails do not modify the solicitation and must not be relied upon.
Testable requirement
A requirement naming the actor, action, object, and a measurable threshold, such as returning search results within two seconds for 95 percent of queries.
Shall versus should
Shall marks a mandatory requirement usable as a pass/fail gate; should and may mark desirable features that are scored but cannot disqualify an offeror.
Non-functional requirements
Requirements covering performance, security, availability, usability, and compliance rather than specific functions. They often determine whether a technically compliant solution is usable in practice.
Requirements traceability
Assigning each requirement a unique identifier so proposals, demonstrations, and acceptance tests can be traced back to it, limiting scope creep and easing evaluation.
Statement of Work contents
Deliverables, acceptance criteria, period and place of performance, and customer-furnished items. An SOW without acceptance criteria invites disputes at delivery.
Independent Cost Estimate
A buyer-side should-cost estimate built before release that anchors price reasonableness and realism judgments during evaluation, independent of vendor proposals.
Proposal volume structure
Typical RFP volumes separate administrative representations, technical approach, past performance, and price so technical evaluators can score without seeing price.
Proposal instructions content
Page limits, formatting rules, submission format, deadline with time zone, and the stated consequence of noncompliance, which is usually rejection or point deduction.
Late proposal rule
Proposals received after the closing time are rejected unless the solicitation states a specific exception, such as a documented transmission error.
Pre-proposal conference
An optional meeting or site visit for offerors. If held, its minutes and answers become part of the solicitation record and bind all offerors equally.
Best value tradeoff
A source selection method allowing award to a higher-priced, technically superior proposal when the added value justifies the price premium over other offers.
LPTA award basis
Lowest price technically acceptable: proposals are gated on mandatory requirements, then award goes to the lowest-priced technically acceptable offer with no tradeoff discretion.
Consensus scoring
Evaluators score independently first, then reconcile differences in a consensus session. Individual worksheets are retained as part of the official evaluation record.
Price realism
An assessment of whether a proposed price is achievable for the proposed technical approach. Unrealistically low prices signal performance risk and possible underbidding.
Clarifications versus discussions
Clarifications resolve minor or clerical issues without changing price or technical content; discussions allow revisions and require equal treatment of all offerors in the competitive range.
Firm-fixed-price contract
A contract type where the price is not adjusted for the seller's cost changes. Suitable when requirements are well defined and performance risk is low.
Cost-reimbursement contract
A contract type paying allowable incurred costs plus a fee, used when requirements are uncertain. Requires a cost accounting system and active cost surveillance.
Time and materials ceiling
T and M contracts pay fixed hourly labor rates plus materials at cost. A stated ceiling and surveillance are required because cost risk sits with the buyer.
Contract definitization
Converting a letter contract or undefinitized action into a definitive contract within a stated period, commonly 180 days, before the arrangement becomes a compliance risk.
Negotiation reservation point
The least favorable outcome a negotiator will accept before walking away. Setting target and reservation points in advance prevents concessions made under pressure.
Bilateral modification
A contract change signed by both parties, used when scope, price, or terms change. A unilateral change order is limited to the Changes clause and triggers an equitable adjustment.
Acceptance criteria role
Objective, testable conditions that determine whether a deliverable is accepted. Acceptance triggers payment and starts the warranty or maintenance period.
Service level agreement
A performance commitment with defined metrics, measurement windows, remedies, and escalation paths. Without remedies, service levels function as aspirational statements rather than enforceable terms.
Past performance record
Evaluations such as CPARS recorded annually and at closeout. They feed future source selections, so accuracy and timely vendor comments matter.
Contract closeout steps
Final acceptance, property disposition, final invoice and payment, and release of claims. Records must be retained for the period required by regulation or policy.
Traceability matrix
A table linking each requirement to its evaluation criterion and acceptance test. It demonstrates coverage and exposes requirements that are unscored or untested.
Risk register fields
Each risk records likelihood, impact, mitigation owner, and trigger. The register is reviewed at milestones rather than written once for the appendix.
Contract type justification
The paper must justify the chosen contract type against requirement certainty, contract duration, and risk allocation, not simply assert a preference.