RFP Module 6 study materials
RFP Module 6 study resources

RFP Module 6 flashcards

RFP Module 6 · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Capstone deliverable set
The RFP Capstone typically requires three artefacts: a written RFP document, an evaluation and scoring instrument, and an oral defence. Each is scored against separate weighted criteria.
Six mandatory RFP elements
Need, scope, mandatory requirements, weighted evaluation criteria, submission instructions, and contract terms. A defensible RFP contains all six before release to bidders.
Weighted score formula
Total score equals the sum of each criterion weight multiplied by the evaluator score for that criterion. Weights must sum to one hundred percent before evaluation starts.
Mandatory versus scored requirement
Mandatory requirements are pass or fail and are checked first. A bid failing any mandatory requirement is excluded and never enters the weighted scoring stage.
Addendum rule
Any change to an RFP after release is issued as a numbered, dated addendum sent to all bidders at the same time. Bidders acknowledge addenda in their submission.
Consolidated clarification answers
All bidder questions and the buyer's answers are published together to every bidder. Unequal disclosure of clarification information is a standard ground for protest.
Lowest compliant price model
An evaluation model that awards to the lowest-priced bid that passes all mandatory requirements. It suits commodity purchases where quality differences are immaterial.
Best value evaluation model
A weighted model combining quality and price scores. The RFP must declare the quality and price weights before bids are received so bidders can price their response.
Quality-price weight inverse
Quality weight plus price weight equals one hundred percent. Raising the quality weight lowers the price weight by the same amount, so a stated split fixes both numbers.
Consensus scoring process
Evaluators score independently first, then reconcile differences in a moderation meeting. The reconciled score and the reason for divergence are recorded in the evaluation report.
Conflict of interest declaration
Every evaluator signs a conflict declaration before seeing any bid. An undeclared conflict invalidates that evaluator's scores and may require re-evaluation.
Bid security versus performance security
Bid security protects the buyer if a bidder withdraws before award. Performance security protects against supplier default after award. They are separate instruments with different triggers.
Risk allocation principle
Risk should sit with the party best able to control it. Liquidated damages, indemnities, and retention are the contractual mechanisms that transfer risk to the supplier.
Award recommendation contents
The recommendation names the winning bidder and score, lists rejected bids with the specific failed requirement identifiers, and discloses any reservations attached to the award.
Debriefing disclosure limits
Unsuccessful bidders learn their own scores and the winner's total score. They do not receive other bidders' confidential commercial details or competitor pricing breakdowns.
Segregation of duties in RFP
The requester defines need, procurement runs the process, the panel scores, and the approver signs. No individual should hold two of these roles in one procurement.
Single point of contact rule
All bidder communication during a live RFP flows through the nominated contact. Direct contact between a bidder and an evaluator is a disqualification trigger.
Governance gate reviews
Formal checkpoints at requirement sign-off, RFP release, evaluation close, and award. Each gate has named entry and exit criteria and a recorded decision.
Unique requirement identifiers
Every requirement carries a unique ID so bidders respond line by line and evaluators trace compliance to a specific clause. Identifiers also anchor rejection reasons.
Measurable statement of work
Requirements must be testable. A response time of four business hours is measurable; a phrase such as respond quickly cannot be scored or enforced.
Late bid default rule
A bid received after the published deadline is rejected unless the RFP explicitly permits a documented exception. The default position is rejection without evaluation.
Fixed price versus time and materials
Fixed price suits stable, well-defined scope. Time and materials suits uncertain volume. The RFP must state which contract type applies before bidding.
Deviations schedule
A bidder's list of departures from the attached terms and conditions. The evaluation panel prices the risk of each deviation rather than negotiating after award.
Approval threshold tiering
Approval authority is tiered by contract value. The candidate must identify the correct approval tier for the value in question rather than quoting a fixed currency figure.
Evaluation report contemporaneity
Scores are recorded during the scoring meeting, not reconstructed after the decision. Verbal scoring that is not written down is treated as not performed.
Standstill period
A pause between award notification and contract signature that allows unsuccessful bidders to challenge. The capstone timeline must include it before go-live dates.
Scope freeze before weighting
Requirements are finalised before evaluation weights are set. Adding scope afterwards breaks the link between the stated need and the scoring model.
Mandatory versus desirable split
True mandatory items are limited to pass or fail essentials. Everything else becomes a scored desirable requirement, which widens the supplier pool and preserves differentiation.
Undisclosed sub-criteria risk
Introducing scoring factors not published in the RFP lets evaluators apply hidden criteria. The full scoring breakdown must be released with the RFP.
Exit and handover clause
A contract clause requiring the outgoing supplier to transfer data, knowledge, and services to a successor. Without it, the incumbent's departure is unmanaged.
Post-award variation control
Scope changes after award need a formal variation with re-priced cost and schedule impact. Verbal instructions and informal changes are audit findings.
Defence risk register
In the capstone defence, each top risk is stated with likelihood, impact, named owner, and mitigation. A risk without an owner is treated as unmanaged.