Failed Insulation-Resistance Test at Commissioning

NABCEP SW Associate · Put your knowledge to work in context.

All case studies

Failed Insulation-Resistance Test at Commissioning

During commissioning of an 8 kW rooftop PV system, the installer isolates both DC strings and performs an insulation-resistance test from each string’s positive and negative conductors to ground. String 1 reads 80 MΩ; string 2 reads 0.6 MΩ. The inverter is disconnected, but the DC arc-fault and surge-protection devices are still connected to the array. The manufacturer requires a minimum insulation resistance of 1 MΩ before energizing. The roof was wet from overnight rain, and one home-run cable passes through a metal raceway with a sharp bend. The crew wants to energize the system to see if the inverter clears the fault because the sun is out and the homeowner is waiting. The site has a 600 V DC maximum system voltage and uses listed PV wire.

1. Interpret the test result. Is it safe to energize? What confounders must be ruled out before condemning the string?

Read the worked answer

String 2’s 0.6 MΩ is below the manufacturer’s 1 MΩ minimum, while string 1 at 80 MΩ is normal. The system should not be energized. Energizing a low-insulation array can produce a ground fault, arc, or equipment damage, and the inverter is not a substitute for finding the defect.

Before condemning the string, rule out test artifacts: wet surfaces and connectors from overnight rain, moisture inside junction boxes, the still-connected surge-protection or arc-fault devices providing a leakage path, an incorrect test voltage, and a meter or lead problem. Disconnect the SPD/AFD from the circuit, dry accessible connections if appropriate, and retest. Also inspect the sharp raceway bend for cable insulation damage.

2. Describe a logical fault-location sequence for string 2, including safety steps.

Read the worked answer

Lock out the DC source and verify zero voltage at the string with a meter rated for 600 V DC or higher. Disconnect the string from the combiner and isolate the SPD/AFD. Test the whole string to ground, then split the string at a mid-string connector and test each half separately. The half with low resistance contains the fault. Continue splitting until a module, connector, or cable section is isolated.

Inspect the raceway bend for pinched or abraded insulation, check junction boxes for water intrusion or loose strands, and look for damaged module leads. Use a megohmmeter at the manufacturer’s specified test voltage, typically 1000 V for this class of PV cable, and do not exceed the rating of modules or test equipment. Replace damaged cable or modules rather than taping over insulation damage.

3. What acceptance criteria and documentation are needed before energizing?

Read the worked answer

After repair, dry and retest each string. Both strings should read at least 1 MΩ, preferably with a comfortable margin above the manufacturer’s minimum. Verify string polarity and Voc, check that connectors are fully engaged and torqued, confirm equipment grounding, and inspect that the raceway bend no longer stresses the cable. Record the insulation-resistance values, test voltage, ambient and weather conditions, and the repaired component. Update the commissioning sheet and as-built drawing. Only then should the DC switch be closed and the inverter started, followed by an operational check of array voltage, current, and any ground-fault alarm.