NATE Hydronics Oil · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Hydronic Heating System Fundamentals & Oil Burner and Combustion Components

  • Define heat-loss fundamentals (conductive, convective, radiant) and calculate a room-by-room heat loss using U-values and design temperature difference for a sample two-story house

  • Trace a complete hydronic loop from boiler supply through zone valves, emitters, and return, labeling supply/return temperatures at each point

  • Identify the three legs of the combustion triangle and explain how excess air, draft, and stack temperature interact in an oil-fired system

  • Compare series-loop, primary-secondary, and zone-valve distribution layouts and state one application where each is preferred

Your checkpoint

A one-page hand-drawn system schematic with labeled components, plus a completed heat-loss worksheet for a 1,800 sq ft sample house showing total design load in Btuh

Week 2

Oil Burner and Combustion Components

  • Disassemble (in description) a retention-head oil burner into its major components: burner motor, fuel pump, nozzle, electrodes, transformer, cad cell, and air tube, and state the function of each

  • Calculate nozzle flow rate and pump pressure relationships, and select the correct nozzle size and spray pattern for a given firing rate and combustion chamber shape

  • Explain the oil delivery path from tank through filter, pump, and nozzle, including one-pipe vs two-pipe systems and when a bypass plug is required

  • Describe proper electrode settings, cad cell operation, and the sequence of a typical primary control trial for ignition

Your checkpoint

A component-identification table listing at least 12 burner parts with function, common failure mode, and one test or measurement used to verify each

Week 3

Oil Burner and Combustion Components & Boilers, Controls, and Electrical

  • Perform combustion analysis math: convert CO2 or O2 readings to excess air, compute steady-state efficiency from stack temperature and net temperature, and interpret smoke number and draft readings

  • Adjust a burner for target smoke (trace to #1) and explain the trade-off between excess air, efficiency, and stack temperature

  • Identify boiler controls: aquastat (high/low limit), circulator relay, low-water cutoff, expansion tank, relief valve, and primary control, and state the setpoint or setting each typically uses

  • Trace a 120V control circuit from transformer through thermostat, relay, and burner primary control and explain what opens or closes at each step

Your checkpoint

A combustion-analysis worksheet with calculated excess air, steady-state efficiency, and a written burner-adjustment recommendation for three sample test scenarios

Week 4

Boilers, Controls, and Electrical

  • Read and interpret a boiler wiring ladder diagram and redraw it as a labeled schematic showing line, neutral, and safety-control paths

  • Explain the function and failure symptoms of the low-water cutoff and relief valve, and describe the annual test procedure for each

  • Differentiate fixed high-limit, adjustable high-limit, and low-limit aquastat settings and describe how each affects domestic hot water priority and zone operation

  • Describe expansion tank sizing and the difference between a conventional tank and a diaphragm tank, including air-charge verification

Your checkpoint

A redrawn ladder diagram with a written fault-analysis table: for five simulated failures (open cad cell, tripped LWCO, failed transformer, stuck zone valve, bad aquastat), state the symptom and the meter test that confirms it

Week 5

Piping, Pumps, and Distribution

  • Size a circulator from a pump curve given required flow in GPM and system head in feet, and explain how pipe size, fittings, and emitters contribute to head

  • Compare series loop, one-pipe, two-pipe direct return, and two-pipe reverse return piping and explain which balances best and why

  • Explain primary-secondary pumping, hydraulic separation, and when a mixing valve or injection loop is needed for low-temperature emitters such as radiant floor

  • Describe air elimination, expansion tank placement, and the function of air scoops and automatic vents at the system's high points

Your checkpoint

A piping layout for a two-zone system (baseboard plus radiant floor) showing pump placement, primary-secondary piping, air elimination, expansion tank, and a pump-curve selection with the operating point marked

Week 6

Piping, Pumps, and Distribution & Installation, Service, and Troubleshooting

  • Plan a commissioning sequence for a new oil-fired hydronic installation: pressure test, fill and purge, air removal, burner startup, combustion test, and zone balancing

  • Describe purging air from a zone using a purge valve and explain why air-bound systems cause noisy operation and poor heat delivery

  • Explain how to balance zones using flow valves or balancing valves and how to verify temperature drop across a loop

  • Identify code- and safety-related installation requirements for relief valve discharge piping, combustion air, and oil tank and supply-line protection

Your checkpoint

A written commissioning checklist of at least 15 steps in correct order, with the expected reading or observation that confirms each step is complete

Week 7

Installation, Service, and Troubleshooting

  • Build a systematic diagnostic sequence for no-heat calls that checks thermostat, control circuit, burner primary control, cad cell, fuel supply, and ignition in order, and state the meter reading expected at each step

  • Diagnose common burner faults (delayed ignition, puffback, rumbling, short cycling, sooting) and name the likely cause and corrective action for each

  • Explain how to test a cad cell with an ohmmeter and interpret resistance in light vs darkness

  • Describe service procedures for nozzle replacement, electrode adjustment, filter change, and heat-exchanger cleaning, including safety lockout steps

Your checkpoint

A troubleshooting decision tree for no-heat and for delayed-ignition complaints, with at least eight decision points and the test or measurement at each branch

Week 8

Hydronic Heating System Fundamentals & Oil Burner and Combustion Components & Boilers, Controls, and Electrical & Piping, Pumps, and Distribution & Installation, Service, and Troubleshooting

  • Review all five domains using a self-made summary sheet of formulas, setpoints, and safety limits

  • Retake practice questions in each domain and log every missed item with the underlying concept it tested

  • Re-derive combustion efficiency, heat loss, and pump-curve calculations from memory without notes

  • Simulate a full service call from complaint to verified repair, narrating each diagnostic step and the measurement that confirms the fix

Your checkpoint

A completed formula and setpoint reference sheet plus a scored practice-exam log showing at least 80% correct in every domain, with a written remediation note for each remaining weak area

Milestones

Week 2: Can name every major oil burner component, its function, and one test for it without notes, and correctly select a nozzle for a stated firing rate

Week 4: Can calculate excess air and steady-state efficiency from raw combustion readings and trace a boiler control circuit from thermostat to burner without referring to notes

Week 6: Can select a circulator from a pump curve and lay out a primary-secondary two-zone system with correct air elimination and expansion tank placement

Week 8: Scores at least 80% on practice questions in all five domains and can complete a full no-heat diagnostic sequence from memory