NBBI Authorized Inspector Supervisor (B) flashcards
NBBI Authorized Inspector Supervisor (B) · Build recall with a focused review session.
31 cards. Read the term and the definition here. The deck at the top of this page is optional.
- National Board commission
- A personal credential issued by the National Board of Boiler and Pressure Vessel Inspectors to an individual inspector, qualifying that person to perform code inspections when acting for an authorized inspection agency or jurisdiction.
- Authorized Inspector definition
- Under NBIC Part 1, an inspector who holds a valid National Board commission and performs inspections for a jurisdiction or an authorized inspection agency, with authority derived from that jurisdiction.
- Inspector Supervisor role
- The commissioned individual who directs, reviews, and takes responsibility for the inspection work of Authorized Inspectors in an agency, including report completeness and consistency of code application.
- Authorized Inspection Agency
- An organization authorized by a jurisdiction, or recognized by the National Board where no jurisdictional program exists, to employ commissioned inspectors and perform NBIC inspections.
- R stamp holder
- The repair organization, not the individual inspector, that holds the National Board R stamp and is therefore permitted to perform code repairs and alterations documented on R forms.
- VR stamp scope
- The National Board stamp held by an organization qualified to repair and test pressure relief valves, with work documented on R-2 forms and test records retained for review.
- NBIC Part 3 scope
- The part of the NBIC governing repairs and alterations to boilers and pressure vessels, including who may perform them and what documentation and inspection are required.
- Jurisdiction controls conflict
- Where a jurisdictional rule and the NBIC differ, the stricter applicable requirement governs the inspection; the NBIC is adopted by reference, so local law supplies the legal force.
- In-service inspection interval
- The period between required in-service inspections set by the jurisdiction, during which the item must remain documented and available for inspection under the adopted NBIC edition.
- Complete edition replacement
- Each new NBIC edition replaces the prior edition in full rather than amending it, so the applicable edition must be identified for every item and every task.
- Edition in effect rule
- Work is generally judged against the code edition in force when that work was performed, not automatically against the newest edition published later.
- Jurisdictional adoption lag
- Because jurisdictions adopt NBIC editions on their own schedule, a published change does not apply until that jurisdiction formally adopts it, which the supervisor must confirm.
- Current form requirement
- When a new edition revises a form, only the current version is acceptable for new work; superseded forms still found at a plant must not be used.
- ASME alignment
- NBIC in-service acceptance criteria track the ASME construction code edition referenced by the jurisdiction, so repairs are evaluated against that referenced edition.
- NDE personnel qualification
- The NBIC expects nondestructive examination personnel to be qualified under a recognized program such as SNT-TC-1A; the supervisor verifies certification records rather than qualifying personnel.
- R-1 versus R-2
- R-1 documents repairs and alterations to boilers and pressure vessels; R-2 documents pressure relief device repair work. Both require Authorized Inspector signature.
- Administrative tightening
- Recent editions have strengthened documentation of inspector qualifications and the identity of the authorized inspection agency on reports and forms, increasing supervisor review burden.
- Verify against code text
- Summaries and study aids cannot substitute for the published 2025 NBIC; clause numbers and effective dates must be confirmed in the code itself before field application.
- NBIC Interpretation defined
- A written National Board answer to a specific written inquiry about the intent of existing code text; it clarifies rather than creates requirements and is cited by its identifier.
- Interpretation numbering
- Interpretations carry an edition year plus a sequential case number, which is the identifier used when citing the answer in reports or correspondence.
- Scope of an interpretation
- An interpretation applies to the code edition named in the inquiry unless the answer states broader applicability; extending it to earlier work needs jurisdictional direction.
- Interpretation versus law
- Interpretations guide consistent application but gain legal force only through jurisdictional adoption or enforcement; they are not self-executing law.
- Formal inquiry path
- When code text and existing interpretations do not resolve a question, the correct route is a written inquiry to the National Board, not an informal supervisor ruling.
- Interpretation log
- A maintained record of interpretations relevant to an agency's work, kept so field inspectors apply one consistent reading rather than divergent personal interpretations.
- No waiver by interpretation
- An interpretation cannot waive a jurisdictional requirement; where a jurisdiction has issued its own ruling, that ruling controls within that jurisdiction.
- Confirm published wording
- Before relying on an interpretation in a dispute, the supervisor confirms its exact wording and current status in the published National Board compilation.
- Manufacturer's Data Report
- The construction record form, such as U-1 or P-2, signed by the Authorized Inspector to attest that the item was built to the applicable code.
- Data report registration
- Filing the data report with the jurisdiction and, where required, the National Board, so the item enters the in-service system with a traceable inspection history.
- NB number
- The National Board registration number assigned to a boiler or pressure vessel, linking that item permanently to its data report and its in-service inspection record.
- Report consistency review
- Supervisor check that identifier, design data, code edition, stamp, and signatures agree across the data report and supporting records before filing.
- Missing data report handling
- Absence of the original data report does not remove the item's code status; the jurisdiction and National Board direct reconstruction of history, which the supervisor documents.