This domain tests whether you can design reliable operations and deliver projects against scope, time, cost and quality. The exam expects control mechanisms, not optimistic plans.

Core rules and concepts

  • Operations compete on quality, speed, dependability, flexibility and cost. Trade-offs must be explicit.
  • Process improvement uses PDCA for iterative control, Lean to remove waste, and Six Sigma to reduce variation.
  • Projects are temporary and produce a unique output; programmes coordinate related projects; business-as-usual is ongoing.
  • The triple constraint links scope, schedule and cost, with quality as the outcome. Change one and the others move.
  • A RACI clarifies who is responsible, accountable, consulted and informed. One person should be accountable per activity.
  • The critical path is the longest dependent sequence and determines minimum duration. Float is the slack on non-critical tasks.
  • Risk registers record probability, impact, owner and response: avoid, reduce, transfer or accept. An issue is a risk that has already happened.
  • PRINCE2 suits governed stage-gate delivery; Agile suits uncertain requirements and iterative learning.

Worked example A three-day delay hits a critical-path task. A weak response crashes every task. A stronger response checks float: a parallel task has five days' float, so it can absorb no delay but can be rescheduled to release a specialist. The manager models expediting cost against milestone impact, updates the risk register and informs the sponsor. Reasoning: protect the critical path and the milestone, not every activity.

Traps that cost marks

  • Confusing projects, programmes and business as usual.
  • Planning without baselines or change control.
  • Gold-plating scope without approval.
  • Logging realised problems as risks.
  • Using Agile as an excuse for no governance.