NC Phase F study materials
NC Phase F study resources

NC Phase F practice questions

One question at a time. Build your NC Phase F understanding.

First 50 of 200 questions. Each one lists the choices, the correct answer, and an explanation. The checker at the top of this page saves progress in this browser when it is available.

Continue in the practice tool above to load more questions, 50 at a time.

Question 1Fundamentals and Terminology

In the context of the NC Phase F examination, what does the term 'terminology' most directly refer to?

  1. The legal statutes governing practice
  2. The mathematical formulas used to calculate outcomes
  3. The historical development of the profession
  4. The standardized vocabulary and definitions used within the field Correct answer.

Explanation

Terminology concerns the standardized vocabulary and agreed definitions that practitioners use to communicate precisely. It is distinct from formulas, history, or statutes, which are separate bodies of knowledge.

Question 2Fundamentals and Terminology

A candidate encounters the abbreviation 'NC' in the exam title. Which interpretation is most consistent with standard exam nomenclature?

  1. A software version number
  2. A unit of measurement
  3. A chemical compound symbol
  4. A certification or examination designation Correct answer.

Explanation

In exam titles, letter combinations like 'NC' typically denote a certification or examination designation rather than a physical unit. Recognizing this helps candidates correctly frame the scope of the exam.

Question 3Fundamentals and Terminology

Which term best describes a word or phrase that has a precise, agreed meaning within a specialized field?

  1. Slang
  2. Technical term Correct answer.
  3. Colloquialism
  4. Archaism

Explanation

A technical term carries a precise, field-specific meaning understood consistently by practitioners. Colloquialisms, slang, and archaisms lack that standardized precision.

Question 4Fundamentals and Terminology

When a definition in the field's terminology conflicts with everyday usage of the same word, how should a candidate interpret the term on the exam?

  1. According to the most common everyday meaning
  2. According to the field's standardized definition Correct answer.
  3. According to the oldest recorded usage
  4. According to the candidate's personal preference

Explanation

Exams test the field's standardized definitions, which may differ from everyday usage. Applying everyday meaning risks selecting a plausible but incorrect option.

Question 5Fundamentals and Terminology

Which of the following best characterizes an 'acronym' as used in professional terminology?

  1. A word formed from the initial letters of a phrase Correct answer.
  2. A word borrowed unchanged from another language
  3. A word that imitates a sound
  4. A word with the same meaning as another

Explanation

An acronym is formed from the initial letters of a multi-word phrase and read as a word. This distinguishes it from loanwords, onomatopoeia, and synonyms.

Question 6Fundamentals and Terminology

A candidate reads that a term is 'synonymous' with another. What relationship does this describe?

  1. The two terms sound alike but differ in meaning
  2. The two terms have opposite meanings
  3. The two terms share essentially the same meaning Correct answer.
  4. The two terms belong to different fields

Explanation

Synonymy describes terms with essentially the same meaning, allowing them to substitute for one another in context. Antonymy, homophony, and cross-field divergence describe different relationships.

Question 7Fundamentals and Terminology

Which statement best explains why standardized terminology matters in professional practice?

  1. It replaces the need for professional judgment
  2. It reduces ambiguity in communication among practitioners Correct answer.
  3. It eliminates the need for written documentation
  4. It guarantees uniform outcomes in every case

Explanation

Standardized terminology primarily reduces ambiguity so that practitioners interpret terms consistently. It does not remove documentation needs, guarantee outcomes, or substitute for judgment.

Question 8Fundamentals and Terminology

A candidate must distinguish a 'definition' from an 'example' when studying terminology. Which statement correctly captures the difference?

  1. A definition states what a term means; an example illustrates it Correct answer.
  2. A definition applies only to abbreviations
  3. Both terms mean exactly the same thing
  4. A definition illustrates a term; an example states its meaning

Explanation

A definition specifies the meaning of a term, while an example demonstrates that meaning in use. Confusing the two can cause candidates to mistake an illustration for a formal meaning.

Question 9Fundamentals and Terminology

In terminology study, what is the purpose of a 'glossary'?

  1. To record the history of an organization
  2. To summarize statistical findings
  3. To outline examination procedures
  4. To list terms with their definitions for reference Correct answer.

Explanation

A glossary is a reference list pairing terms with their definitions. It supports consistent interpretation of specialized vocabulary rather than documenting history, statistics, or procedures.

Question 10Fundamentals and Terminology

Which term describes the process of defining a word by the category it belongs to plus the features that distinguish it?

  1. Circular definition
  2. Persuasive definition
  3. Genus and differentia definition Correct answer.
  4. Operational definition

Explanation

A genus and differentia definition places a term in a broader category and then states distinguishing features. Circular, operational, and persuasive definitions use different structures.

Question 11Fundamentals and Terminology

A term is described as 'ambiguous' in a technical document. What does this mean for the reader?

  1. The term can be interpreted in more than one way Correct answer.
  2. The term is no longer used
  3. The term is misspelled
  4. The term is always defined in a glossary

Explanation

Ambiguity means a term admits more than one interpretation in context, which can cause miscommunication. Spelling, currency, and glossary inclusion are separate issues.

Question 12Fundamentals and Terminology

Which of the following is the best example of a 'euphemism' as a terminological device?

  1. A technical abbreviation used in reports
  2. A word borrowed from another language
  3. A term with two opposite meanings
  4. A mild expression substituted for a harsh one Correct answer.

Explanation

A euphemism replaces a harsh or sensitive expression with a milder one. Abbreviations, loanwords, and contronyms describe different phenomena.

Question 13Fundamentals and Terminology

In terminology, what distinguishes a 'contronym' from an ordinary word?

  1. It has no meaning at all
  2. It is always an abbreviation
  3. It carries two opposite meanings depending on context Correct answer.
  4. It is used only in legal writing

Explanation

A contronym is a single word with two opposite senses, so context determines meaning. This is unlike words lacking meaning or being restricted to a register.

Question 14Fundamentals and Terminology

A candidate sees the notation 'e.g.' in a terminology passage. How should it be read?

  1. As marking an abbreviation
  2. As introducing an example Correct answer.
  3. As introducing a contrast
  4. As marking a definition

Explanation

'e.g.' stands for exempli gratia and introduces an example, whereas 'i.e.' introduces a restatement. Recognizing this prevents misreading illustrative material as definitional.

Question 15Fundamentals and Terminology

Which statement best describes the relationship between a 'term' and a 'concept' in terminology science?

  1. A term is a label that designates a concept Correct answer.
  2. Terms and concepts never relate to each other
  3. A term is the same thing as a concept
  4. A concept is a label that designates a term

Explanation

In terminology science, a concept is the underlying idea, and a term is the linguistic label used to designate it. Treating the two as identical blurs an important distinction.

Question 16Fundamentals and Terminology

A document uses 'i.e.' before a phrase. What function does this abbreviation serve?

  1. It introduces a list of examples
  2. It signals the end of a quotation
  3. It introduces a restatement or clarification Correct answer.
  4. It marks an uncertain claim

Explanation

'i.e.' stands for id est and introduces a restatement or clarification of what precedes it. It is often confused with 'e.g.', which introduces examples.

Question 17Fundamentals and Terminology

Which of the following best defines a 'neologism'?

  1. A word borrowed from Latin
  2. A word with multiple spellings
  3. A newly coined word or expression Correct answer.
  4. A word that has fallen out of use

Explanation

A neologism is a newly coined word or expression entering usage. Obsolescence, spelling variation, and borrowing describe different lexical phenomena.

Question 18Fundamentals and Terminology

A terminology standard specifies preferred terms for a concept. What is the main practical benefit of such standardization?

  1. Guaranteed translation accuracy in every language
  2. Elimination of all synonyms from a language
  3. Reduction in the number of concepts in a field
  4. Consistent interpretation across documents and users Correct answer.

Explanation

Preferred-term standardization promotes consistent interpretation across documents and users. It does not eliminate synonyms, reduce concepts, or guarantee translation accuracy.

Question 19Fundamentals and Terminology

Which pairing correctly matches a term with its meaning?

  1. Antonym - a word identical in meaning to another
  2. Homonym - a word that shares form with another but differs in meaning Correct answer.
  3. Acronym - a word borrowed from another language
  4. Synonym - a word opposite in meaning to another

Explanation

A homonym shares spelling or sound with another word while differing in meaning. The other pairings swap or misassign the definitions of synonym, antonym, and acronym.

Question 20Fundamentals and Terminology

A candidate must decide whether a term is being used in its 'general' or 'restricted' sense. Which approach is most defensible?

  1. Ignore context and rely on the dictionary's first entry
  2. Assume the general sense always applies
  3. Assume the restricted sense always applies
  4. Check whether the field assigns the term a narrower technical meaning Correct answer.

Explanation

Technical fields often restrict a term to a narrower meaning than everyday use. Checking whether the field assigns such a restricted sense is the defensible approach; blanket assumptions are not.

Question 21Fundamentals and Terminology

Which situation best illustrates a 'false friend' in terminology?

  1. A term that has been officially retired
  2. A term that looks familiar but carries a different technical meaning Correct answer.
  3. A term used only in spoken language
  4. A term with no accepted definition

Explanation

A false friend appears familiar but denotes something different in the technical context, creating a trap for the unwary. Retired terms, undefined terms, and spoken-only terms are distinct issues.

Question 22Fundamentals and Terminology

A definition reads: 'A widget is a device used for widgeting.' Which flaw does this definition exhibit?

  1. Ambiguity
  2. Overbreadth
  3. Obscurity
  4. Circularity Correct answer.

Explanation

The definition repeats the term being defined within its own explanation, making it circular. Overbreadth, ambiguity, and obscurity are separate defects that this example does not primarily display.

Question 23Fundamentals and Terminology

When a technical term has both a broad and a narrow accepted definition, what is the most rigorous way to resolve which applies in a passage?

  1. Choose the broad definition because it is more inclusive
  2. Use contextual clues and the document's stated scope Correct answer.
  3. Choose whichever definition yields the shorter reading
  4. Choose the narrow definition because it is more precise

Explanation

Rigorous interpretation relies on contextual clues and the document's declared scope to select the intended sense. Defaulting to broad, narrow, or shorter readings substitutes a rule of thumb for evidence.

Question 24Fundamentals and Terminology

A glossary entry gives a term, a definition, and a deprecated synonym. What does 'deprecated' indicate about the synonym?

  1. It is illegal to use in any context
  2. It is the most current form
  3. It is a translation of the preferred term
  4. It is discouraged in favor of the preferred term Correct answer.

Explanation

A deprecated synonym is discouraged in favor of the preferred term but is not illegal or necessarily a translation. It signals declining acceptance rather than current preference.

Question 25Project Initiation and Planning

In project initiation, what is the primary purpose of developing a project charter?

  1. To document detailed technical specifications for each deliverable
  2. To establish the schedule baseline and cost baseline for control
  3. To list every activity required to complete the product scope
  4. To formally authorize the project and empower the project manager to apply organizational resources Correct answer.

Explanation

The project charter is the document that formally authorizes the existence of a project and gives the project manager authority to commit organizational resources to activities. It is created during initiation, before detailed planning baselines exist. Technical specifications, schedules, and activity lists are developed later in planning.

Question 26Project Initiation and Planning

A sponsor asks a newly assigned project manager to begin work, but no charter exists. What is the most appropriate action for the project manager?

  1. Request that a charter be developed and approved before committing resources Correct answer.
  2. Ask the team to start execution while the charter is drafted in parallel
  3. Treat the sponsor's verbal request as sufficient authorization and proceed
  4. Begin planning immediately to save time and document the charter later

Explanation

Without an approved charter, the project manager lacks formal authority to commit organizational resources and the project has no recognized authorization. The correct action is to ensure the charter is created and approved before significant planning or execution begins. Verbal direction may indicate intent but does not substitute for the authorizing document.

Question 27Project Initiation and Planning

Which element is typically found in a project charter rather than in a detailed project management plan?

  1. The resource-loaded schedule with critical path
  2. The risk register with response owners
  3. The quality control inspection checklist
  4. The high-level project description and measurable objectives Correct answer.

Explanation

A charter captures high-level information such as purpose, measurable objectives, high-level requirements, and summary milestones. Detailed schedules, risk registers, and inspection checklists are planning outputs created after authorization. This distinction keeps the charter concise and authorizing in nature.

Question 28Project Initiation and Planning

A project manager is identifying stakeholders early in the project. Which group should be considered first when building the stakeholder register?

  1. Only the executives who approve funding
  2. All individuals and groups who can affect or be affected by the project Correct answer.
  3. Only the people who will perform the project work
  4. Only external customers who will receive the final product

Explanation

Stakeholder identification considers everyone who can impact or be impacted by the project, including internal team members, sponsors, customers, suppliers, and regulators. Narrowing the list too early causes missed requirements and late resistance. The register is then analyzed and prioritized for engagement planning.

Question 29Project Initiation and Planning

During initiation, a project manager learns that a regulatory body must approve the product before release. How should this stakeholder be classified and handled?

  1. Delegate all communication with the regulator to the procurement team
  2. Record the regulator as a key stakeholder with high influence and plan early engagement Correct answer.
  3. Add the regulator to the team directory without further analysis
  4. Ignore the regulator until the release phase to avoid scope creep

Explanation

A regulator that can block release has high influence over project success and must be recorded and analyzed in the stakeholder register. Early engagement planning helps surface compliance requirements before design is locked. Deferring or delegating without analysis risks late rework.

Question 30Project Initiation and Planning

What distinguishes a project from ongoing operations in the context of project initiation?

  1. A project has no defined start or finish date
  2. A project always requires more funding than operations
  3. A project is performed only by external contractors
  4. A project is temporary and produces a unique result, while operations are ongoing and repetitive Correct answer.

Explanation

A project is a temporary endeavor undertaken to create a unique product, service, or result, whereas operations are ongoing repetitive activities that sustain the business. Temporariness and uniqueness are the defining characteristics used to decide whether work should be managed as a project. Funding source and staffing model do not define a project.

Question 31Project Initiation and Planning

A business case is being prepared for a proposed project. What is its main role in project initiation?

  1. To provide the detailed work breakdown structure for the project
  2. To justify the investment by documenting expected benefits, costs, and rationale Correct answer.
  3. To record the lessons learned from previous similar projects
  4. To assign specific tasks to individual team members

Explanation

The business case establishes whether the expected benefits of the project justify the investment and provides the rationale for authorization. It supports the decision to initiate and is referenced later to confirm benefits are still viable. Work breakdown structures and task assignments are planning outputs.

Question 32Project Initiation and Planning

An organization must select among three candidate projects with limited funding. Which approach best supports the selection decision during initiation?

  1. Apply benefit measurement methods such as cost-benefit analysis and scoring models Correct answer.
  2. Choose the project requested by the most senior manager
  3. Fund all three partially to avoid making a decision
  4. Select the project with the shortest estimated duration regardless of value

Explanation

Project selection should use objective benefit measurement or constrained optimization methods, such as cost-benefit analysis, scoring models, or economic models. These methods compare expected value against cost and risk. Seniority, duration alone, or spreading funds thinly do not provide a defensible basis for selection.

Question 33Project Initiation and Planning

A project manager is developing the project management plan. What best describes the relationship between the project charter and the project management plan?

  1. The plan authorizes the project, and the charter describes how the work will be executed
  2. The plan is created first and the charter is derived from it
  3. The two documents are interchangeable and one can replace the other
  4. The charter authorizes the project, and the plan describes how the project will be executed and controlled Correct answer.

Explanation

The charter authorizes the project and provides high-level direction, while the project management plan integrates the baselines and subsidiary plans describing how the work will be performed, monitored, and controlled. The charter precedes the plan and serves as an input to it. They are distinct documents with different purposes.

Question 34Project Initiation and Planning

Which of the following best describes a progressive elaboration approach during planning?

  1. Freezing requirements at initiation and rejecting all later changes
  2. Finalizing all scope, schedule, and cost details before any work begins
  3. Developing details incrementally as more information and understanding become available Correct answer.
  4. Avoiding documentation until the product is complete

Explanation

Progressive elaboration means details are developed and refined incrementally as the project advances and more is learned. It acknowledges that complete certainty is rarely available at initiation. It does not mean avoiding documentation or refusing legitimate change control.

Question 35Project Initiation and Planning

A project manager is defining project scope. Which statement correctly distinguishes product scope from project scope?

  1. Product scope applies only to IT projects, while project scope applies to all projects
  2. Product scope describes the features of the deliverable, while project scope describes the work to deliver it Correct answer.
  3. Both terms refer only to the schedule of deliverables
  4. Product scope describes the work, while project scope describes the features of the deliverable

Explanation

Product scope defines the features and functions that characterize the product, service, or result, while project scope defines the work that must be performed to deliver it. Completion of product scope is measured against requirements, and completion of project scope is measured against the project management plan. The two are related but distinct.

Question 36Project Initiation and Planning

During scope planning, the team collects requirements from users. Which output directly results from this process and guides later scope definition?

  1. The team performance assessment
  2. The risk response plan
  3. The procurement statement of work
  4. The requirements documentation and requirements traceability matrix Correct answer.

Explanation

Collecting requirements produces requirements documentation and a requirements traceability matrix that links requirements to their sources and to deliverables. These outputs feed scope definition and later verification. Risk responses, procurement documents, and performance assessments come from other processes.

Question 37Project Initiation and Planning

What is the primary purpose of creating a work breakdown structure during planning?

  1. To determine the total budget by summing vendor invoices
  2. To establish the order in which activities must be performed
  3. To assign a single accountable owner to every risk
  4. To decompose the total scope of work into manageable, deliverable-oriented components Correct answer.

Explanation

The work breakdown structure decomposes the total scope of the project into progressively smaller deliverable-oriented components, with the lowest level being work packages. It provides a basis for estimating, scheduling, and control. It is not a risk assignment tool or a sequencing diagram.

Question 38Project Initiation and Planning

A project team has created a WBS but some work packages contain only one deliverable while others contain dozens. Some required scope is missing, and the larger packages cannot be reliably estimated or controlled. What planning principle does this violate?

  1. The rule that all work packages must be assigned to external vendors
  2. The rule that every work package must have exactly one activity
  3. The 100 percent rule and the rule of thumb that work packages be sized for manageability Correct answer.
  4. The rule that WBS levels must never exceed three

Explanation

A valid WBS captures 100 percent of the project scope and decomposes work into packages sized appropriately for estimating and control, often using a rule of thumb such as the 8/80 guideline. Omitted scope violates the 100 percent rule, while unmanageable work packages need further decomposition. There is no fixed limit of three levels or requirement for a single activity per package.

Question 39Project Initiation and Planning

Which document formally authorizes the project manager to apply organizational resources to project activities?

  1. The project charter Correct answer.
  2. The scope baseline
  3. The stakeholder engagement plan
  4. The project management plan

Explanation

The project charter is the document issued by the sponsor or initiating authority that formally authorizes the project and identifies the project manager with authority to apply resources. The plan, engagement plan, and baselines are developed after authorization and do not grant that authority.

Question 40Project Initiation and Planning

A project manager is estimating activity durations and wants to account for uncertainty. Which technique applies a weighted average of optimistic, most likely, and pessimistic estimates?

  1. Analogous estimating
  2. Parametric estimating
  3. Bottom-up estimating
  4. Three-point estimating Correct answer.

Explanation

Three-point estimating uses optimistic, most likely, and pessimistic estimates to compute an expected duration or cost, often with the PERT weighted formula. It explicitly incorporates uncertainty and risk. Analogous, parametric, and bottom-up methods describe how estimates are derived rather than how uncertainty is weighted.

Question 41Project Initiation and Planning

In schedule planning, what is the purpose of identifying the critical path?

  1. To list activities that can be delayed without affecting the project finish
  2. To assign resources to the least expensive activities first
  3. To determine the sequence of activities that determines the shortest possible project duration Correct answer.
  4. To identify activities with the largest budgets

Explanation

The critical path is the longest path through the network and therefore determines the shortest possible project duration. Activities on the critical path have zero or negative total float, so any delay there delays the project. Activities with float can be delayed without affecting the finish date.

Question 42Project Initiation and Planning

A project manager needs to estimate costs early when very little detail is known. Which estimating approach is most appropriate at this stage?

  1. Bottom-up estimating from detailed work packages
  2. Vendor bid analysis using final proposals
  3. Definitive estimating based on complete specifications
  4. Analogous estimating using historical data from similar projects Correct answer.

Explanation

Analogous estimating uses historical data from comparable projects and is useful when detail is limited, though it is less accurate. Bottom-up and definitive estimates require detailed information that is not yet available. Vendor bid analysis depends on proposals that come later in procurement.

Question 43Project Initiation and Planning

What is the main purpose of a responsibility assignment matrix such as a RACI chart in project planning?

  1. To sequence project activities on a network diagram
  2. To record the acceptance criteria for each deliverable
  3. To clarify who is responsible, accountable, consulted, and informed for project work Correct answer.
  4. To document the project budget by cost account

Explanation

A RACI chart maps work packages or activities to roles and clarifies responsibility, accountability, consultation, and information needs. It reduces confusion about ownership and communication. It does not document budget, sequence activities, or define acceptance criteria.

Question 44Project Initiation and Planning

A project manager is planning communications and wants to ensure the right information reaches the right stakeholders in a timely manner. Which input is most directly relevant to this planning?

  1. The stakeholder register and engagement plan Correct answer.
  2. The quality control measurements
  3. The final product acceptance report
  4. The procurement audit results

Explanation

Communications planning relies on stakeholder information such as needs, influence, and engagement approach to determine what to communicate, to whom, when, and how. Procurement audits, quality measurements, and acceptance reports are execution or control outputs that come later.

Question 45Project Initiation and Planning

During risk planning, a team identifies a risk and decides to purchase insurance to transfer the financial impact. Which risk response strategy is being applied?

  1. Mitigate
  2. Avoid
  3. Accept
  4. Transfer Correct answer.

Explanation

Transferring a risk shifts the financial impact and ownership of the response to a third party, such as through insurance or warranties. Avoidance eliminates the threat, mitigation reduces probability or impact, and acceptance acknowledges the risk without active response. Insurance is a classic transfer example.

Question 46Project Initiation and Planning

A project manager is building the risk register. Which combination of attributes is most useful for prioritizing identified risks?

  1. The names of team members who reported the risks
  2. Probability of occurrence and potential impact on objectives Correct answer.
  3. The color coding used in the project schedule
  4. The number of meetings held to discuss each risk

Explanation

Risk prioritization is based on assessed probability of occurrence and potential impact on project objectives, often combined in a probability and impact matrix. This allows the team to focus response planning on the most significant risks. Reporter identity, schedule color coding, and meeting counts do not measure risk significance.

Question 47Project Initiation and Planning

What is the key difference between a project's quality planning and its quality control?

  1. Quality planning is optional, while quality control is mandatory
  2. Quality planning sets standards and how to meet them, while quality control monitors results to verify compliance Correct answer.
  3. Quality planning applies only to products, while quality control applies only to processes
  4. Quality planning happens during closing, while quality control happens during initiation

Explanation

Quality planning identifies relevant quality standards and determines how the project will satisfy them, producing the quality management plan. Quality control monitors and records results of quality activities to assess performance and recommend corrective actions. Planning precedes control and both apply to products and processes.

Question 48Project Initiation and Planning

A project manager is developing the resource management plan. Which consideration most directly affects how team members will be acquired and managed?

  1. The organizational structure and the availability of staff with required competencies Correct answer.
  2. The location of the project's final acceptance ceremony
  3. The number of stakeholders who prefer email
  4. The color scheme of the project dashboard

Explanation

Resource planning depends on the organizational structure, reporting relationships, and the availability and competencies of staff needed to perform the work. These factors determine acquisition, training, and team development needs. Presentation choices, communication preferences, and ceremony location are not primary drivers.

Question 49Project Initiation and Planning

A project manager discovers that two stakeholders have conflicting requirements for the same deliverable. What is the best planning action?

  1. Facilitate a resolution that documents agreed requirements and records the decision in the requirements documentation Correct answer.
  2. Defer the conflict to the closing phase
  3. Remove the deliverable from scope to avoid the conflict
  4. Accept the requirement from the higher-ranking stakeholder without discussion

Explanation

Conflicting requirements should be resolved through facilitated discussion, with the agreed outcome documented and traced in the requirements documentation and traceability matrix. This preserves stakeholder alignment and provides a basis for later verification. Deferring or unilaterally favoring one party creates unresolved risk.

Question 50Project Initiation and Planning

A project manager is assembling the stakeholder register during initiation. Which attribute is most useful for deciding how much planning effort each stakeholder should receive?

  1. The department in which the stakeholder is employed
  2. The stakeholder's level of interest in and potential influence over the project outcomes Correct answer.
  3. The order in which stakeholders were identified
  4. Whether the stakeholder has previously received project status reports

Explanation

Stakeholder analysis classifies people by interest and influence so the project manager can prioritize engagement and communication effort. Employment department, discovery order, and past report history do not by themselves indicate how much power or concern a stakeholder has.