NC Phase F: Project Initiation and Planning

NC Phase F · Work through your exam, one topic at a time.

All guide sections

Project Initiation and Planning

This domain tests how a project is authorized and how the performance measurement baseline is built: charter, scope, work breakdown, schedule, cost, and the integrated plan.

Initiation

  • The business case justifies the investment; the charter authorizes the project and names the sponsor and project manager, plus high-level scope, budget, milestones, and success criteria. Without a charter you have no authority to commit resources.
  • Identify stakeholders at initiation, not after design starts.

Planning

  • Scope statement captures inclusions, explicit exclusions, and acceptance criteria.
  • Work breakdown structure: deliverable-oriented, obeying the 100 percent rule (all the work, and nothing but the work), decomposed into work packages sized for reliable estimating, each with an owner.
  • Schedule: sequence activities, define dependencies (finish-to-start is the default), apply leads and lags sparingly, then run the critical path.
  • Cost: estimate per work package, add contingency for identified risks, aggregate to the cost baseline.
  • Baseline approval is the gate into execution.

Worked example

Three paths: A-B-D = 5+7+4 = 16 days; A-C-E = 5+3+6 = 14 days; A-C-D = 5+3+4 = 12 days. The critical path is A-B-D at 16 days. Total float on C and E is 16 minus 14, so 2 days each. Reasoning: float is late finish minus early finish along the longest path; shortening the project means shortening the critical path, not squeezing non-critical work.

Traps

  • A work breakdown that mirrors the org chart instead of deliverables.
  • Baselining before scope is signed off.
  • Estimating with no contingency and discovering the gap later.
  • Treating the plan as a finished document rather than an iterative activity.