- Ground bearing pressure
- The load per unit area the crane's outriggers or tracks impose on the soil, equal to total weight divided by total support area; it determines whether mats or cribbing are needed.
- Outrigger float area
- The contact area of an outrigger pad, computed as pi times the radius squared for a circular pad; larger pads reduce ground bearing pressure for the same load.
- Level tolerance
- The maximum slope on which a crane may be set up, typically 1% or less per the manufacturer; the level indicator must be centered before any lift.
- Pre-shift inspection
- The walk-around check of wire rope, hooks, slings, outriggers, and the load moment indicator performed before each shift and documented per the employer's procedure.
- Power line clearance
- The minimum distance crane parts and load must stay from energized lines, 10 ft up to 50 kV plus 0.4 in per kV above 50 kV unless de-energized and grounded.
- Cribbing
- Sound, full-contact blocking placed under outrigger pads to level the crane and spread load; it must be sized to the pad and free of voids or soft spots.
- Rated capacity
- The maximum load a crane may lift in a specific configuration, equal to the smallest of the load chart value, the LMI limit, the rigging capacity, and the structural limit.
- Radius measurement
- The horizontal distance from the crane's center of rotation to the center of gravity of the load, measured at the load, not at the boom tip.
- Net capacity
- The load chart capacity minus the weight of the hook block, slings, spreader bars, and other below-the-hook devices attached to the boom.
- Load chart selection
- Choosing the chart page that matches the outrigger configuration, boom mode, counterweight, and jib or extension in use; using the wrong page invalidates the capacity.
- Interpolation limits
- Estimating capacity between charted radius or boom length values is permitted only within the charted range and only when the chart allows it; extrapolation beyond the chart is prohibited.
- Boom deflection effect
- Boom bending under load increases the actual radius beyond the geometric value, so the chart radius must reflect the loaded condition, not the unloaded boom position.
- Pick-and-carry chart
- A separate reduced-capacity chart used when traveling with a suspended load; it accounts for travel speed, ground conditions, and boom position and never equals the static lift chart.
- Two-crane lift share
- Each crane's portion of a shared load depends on the load's center of gravity; the crane nearer the center of gravity carries more and must be rated for its share.
- Sling angle factor
- The multiplier applied to sling capacity based on the angle from horizontal; at 30 degrees the factor is 0.5, so each leg carries twice its share of the load.
- Bridle tension formula
- Tension per leg in a two-leg bridle equals half the load divided by the sine of the angle from horizontal; a shallower angle dramatically increases tension.
- Center of gravity pick
- Rigging so the hook is directly above the load's center of gravity; an off-center pick shifts weight to one leg and can cause rotation or sling failure.
- Shackle loading axis
- Shackles and hooks must be loaded along the pin or bowl axis; side loading reduces capacity and can bend or open the hardware.
- Shock loading
- A dynamic force from sudden starts, stops, or a slack sling taking up load, which can multiply the static load several times and exceed rigging capacity.
- Tag line use
- A rope used to control load rotation and swing from a safe distance; it keeps hands off the suspended load and personnel out of the fall zone.
- Sling removal criteria
- Conditions that require removing a sling from service, including missing tags, knots, cuts, broken wires, or wear beyond the manufacturer's published limits.
- Standard hand signals
- The agreed set of arm and hand motions for boom, swing, hoist, and stop commands; the operator obeys a stop signal from any person on site.
- Designated signalperson
- The single qualified person who directs the lift; the operator takes signals only from that person except for a stop signal, which is honored from anyone.
- Radio communication check
- Confirming a dedicated channel and clear voice commands with the signalperson before the lift, using standard terms such as boom up and load down.
- Pre-lift checks
- Verifying load weight, rigging, radius, chart, LMI reading, and that all personnel are clear; then sounding the horn and lifting slowly to test stability.
- Swing control
- Leading the load with the swing and avoiding sudden stops so the load does not swing out of control; tag lines help steady it when practical.
- Suspended load rule
- Never leave the operator station with a load suspended; lower the load and shut down per the manufacturer's procedure before leaving the controls.
- Travel with load
- Moving the crane with a suspended load only per the manufacturer's pick-and-carry chart, with the boom in the recommended position and the load kept low.
- OSHA crane standard
- 29 CFR 1926 Subpart CC governs cranes and derricks in construction; 29 CFR 1910.180 covers general industry cranes, and the work being performed determines which applies.
- LMI and RCL
- The load moment indicator or rated capacity limiter warns and stops the crane before capacity is exceeded; operating with a failed or bypassed unit is prohibited.
- Annual inspection
- A competent person inspects the crane at least annually and functionally tests the LMI, RCL, and limit switches; the inspection record is retained.
- Personnel lifting rules
- Lifting people only with an approved platform, a pre-lift meeting, and manufacturer approval; never lift personnel directly on the crane hook.
- Critical lift plan
- A written plan required for lifts over 75% of capacity, multiple-crane lifts, or personnel lifting, covering rigging, radius, capacity, and contingency steps.