NCCCO Concrete Pump (CPO) flashcards
NCCCO Concrete Pump (CPO) · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Allowable bearing capacity
- The maximum soil pressure a ground surface can support without excessive settlement, used to size outrigger pads so calculated bearing pressure stays below it with a safety margin.
- Outrigger float sizing
- Pad area is chosen so total outrigger load divided by effective contact area stays under the soil's allowable bearing capacity; soft fill needs larger mats or cribbing.
- One-call utility locate
- The free service (811 in the US) that marks underground utilities before excavation or setup; outriggers and stabilizers must stay outside the marked tolerance zone.
- Boom load chart
- The manufacturer's table giving allowable boom tip load and reach for each boom length, radius, and outrigger configuration; it is not a lifting rating.
- Exclusion zone at the pump
- The area around the pump, hopper, and discharge point restricted to the operator, signal person, and necessary crew during pumping to prevent injury from blowouts or moving parts.
- Maximum wind speed for boom
- The manufacturer's limit above which the boom must be lowered or stowed; gusts near the limit require stopping the pour and securing the boom.
- Rated output versus actual
- Published pump output in cubic meters per hour is measured under ideal conditions; actual output drops with line length, lift, elbow count, and low slump.
- Maximum concrete pressure
- The highest pressure in bar the pump can develop at the outlet; it must exceed calculated line resistance from distance, elevation, elbows, and slump.
- Safety clamp or whip check
- A restraining device fitted at each pipe coupling and hose connection that limits travel if a coupling separates under pressure, protecting nearby workers.
- Hopper grate
- A heavy grid over the hopper that blocks oversize material and prevents workers from reaching the agitator or auger; it must be intact whenever the pump runs.
- Accumulator hazard
- A hydraulic accumulator stores pressurized fluid after shutdown; pressure must be bled per the manual before any fitting is opened or maintenance begins.
- S-valve and wear ring
- The valve that switches concrete flow between the two cylinders; a worn wear ring causes lost output, higher pressure, and concrete leaking past the valve.
- Boom pin inspection
- Checking boom and outrigger pins for wear, looseness, and missing retainers during pre-use inspection; failed pins can drop a boom section.
- Line priming
- Coating the inside of the pipeline with grout, slurry, or a sponge pig before concrete is pumped, preventing segregation and blockage at the first restriction.
- Free-fall limit for concrete
- Concrete should not drop more than roughly one to one and a half meters into a form; greater falls segregate coarse aggregate from mortar and weaken the placement.
- Layer thickness for placement
- Placing concrete in horizontal layers of about 300 to 500 millimeters and consolidating each layer with a vibrator prevents voids and cold joints.
- Adding water at the pump
- Adding water to increase slump on site raises the water/cement ratio and lowers strength; it requires approval from the producer and engineer.
- Blockage response
- Stop pumping, reverse briefly at low pressure, then relieve pressure before opening any coupling; personnel must stay out of line with the pipe end.
- Vertical pipe anchoring
- Vertical runs need secure anchoring and a trap or blow-back arrangement so concrete does not free-fall back down the line when pumping stops.
- Signal person authority
- One agreed signal method is used, and the operator stops immediately on any unclear signal or on a stop signal from any worker on the site.
- Air-blowing the line
- Cleaning the pipeline with a sponge ball driven by compressed air; the line must be anchored and restrained, and no one may stand at the discharge end.
- Hopper entrapment hazard
- Reaching into the hopper can pull a worker into the agitator; only the grate and a proper tool are used, and the pump is locked out for hopper work.
- Stored energy in a blocked line
- A blocked or pressurized pipeline holds energy like a compressed spring; pressure must be relieved before any coupling is opened and personnel kept clear.
- Power line contact response
- If the boom contacts an energized line, the operator stays in the cab and warns others away until the utility confirms de-energization, unless fire forces evacuation.
- Wet concrete chemical burns
- Wet concrete is highly alkaline and can cause serious skin burns; gloves, boots, and prompt washing are required, and eye protection prevents splash injury.
- Washout containment
- Washout water is often a regulated discharge; it is contained in a lined pit or tank and never released to a storm drain or waterway.
- Lockout/tagout on pumps
- Isolating hydraulic and electrical energy, bleeding accumulators, and verifying zero energy before maintenance; required for hopper, valve, and hydraulic work.
- Daily lubrication points
- Slew ring, boom pins, outrigger pins, and hopper shaft are greased at the manual's interval; missed grease is a leading cause of pin and bearing failure.
- Hydraulic overheating causes
- High oil temperature often traces to a clogged cooler, low oil level, or a stuck relief valve; oil level, filter restriction, and temperature are checked daily.
- Blockage causes list
- Low slump, oversized aggregate, poor priming, too many elbows, a collapsed hose, or long pumping pauses that let concrete stiffen in the line.
- Clearing a line blockage
- Stop, reverse at low pressure, and if that fails, relieve pressure and open the line from the pump end one restrained joint at a time.
- Boom failure emergency procedure
- If the boom cannot retract or hydraulics fail, stop, secure the area, and follow the manufacturer's emergency lowering procedure rather than improvising with the boom aloft.