Rated Capacity

The maximum load a crane may lift under a specific configuration, including boom length, radius, and counterweight, as published by the manufacturer in the load chart.

Related: Load Chart, Working Radius, Gross Load
Load Chart

The manufacturer-supplied table or diagram that lists allowable capacities for each combination of boom length, radius, and other configuration variables. Inspectors verify it is present, legible, and matches the crane.

Related: Rated Capacity, Working Radius, Deductions
Working Radius

The horizontal distance from the crane's center of rotation to the center of gravity of the suspended load. Capacity decreases as radius increases, so accurate measurement is essential.

Related: Rated Capacity, Load Chart, Boom Angle
Boom Angle

The angle of the boom measured from horizontal. It determines working radius and capacity, and is read from the boom angle indicator during inspection and operation.

Related: Working Radius, Boom Angle Indicator, Load Chart
Gross Load

The total weight being handled, comprising the load, rigging, hook block, and any other suspended attachments. Rated capacities are compared against gross load, not just the payload.

Related: Deductions, Rated Capacity, Rigging
Deductions

Weights subtracted from the published capacity for items not included in the load chart figures, such as hook block, slings, jib, or auxiliary lifting devices. Inspectors confirm operators account for them.

Related: Gross Load, Load Chart, Rigging
Anti-Two-Block Device

A safety device that prevents the hook block from contacting the boom tip by stopping hoisting or boom lowering when the two come too close. Its function must be verified during inspection.

Related: Limit Switch, Load Moment Indicator, Operator Aids
Load Moment Indicator

An operator aid that senses load and boom geometry and warns or stops operation when capacity is approached or exceeded. Inspectors check calibration, display, and alarm function.

Related: Rated Capacity, Anti-Two-Block Device, Operator Aids
Operator Aids

Devices that assist the operator in monitoring crane status, including load moment indicators, boom angle indicators, radius indicators, and level indicators. They supplement but do not replace the load chart.

Related: Load Moment Indicator, Boom Angle Indicator, Anti-Two-Block Device
Boom Angle Indicator

An instrument mounted on the boom that displays its angle above horizontal. Inspectors verify it is present, readable, and reasonably accurate against a measured reference.

Related: Boom Angle, Operator Aids
Limit Switch

A device that stops or restricts a crane motion at a preset point, such as hoist upper limit or boom lower limit. Function is tested during periodic inspection.

Related: Anti-Two-Block Device, Operational Test
Wire Rope Lay

The pattern in which strands are wound around the core, such as regular lay or lang lay. Lay affects inspection criteria and the meaning of broken wire counts.

Related: Broken Wire Count, Wire Rope Inspection, Rope Lay Length
Rope Lay Length

The distance along a rope in which one strand makes a complete helical turn around the core. Broken wire removal criteria are often stated per lay length.

Related: Wire Rope Lay, Broken Wire Count, Wire Rope Inspection
Broken Wire Count

The number of broken wires found in a specified length of rope, used against removal criteria. Counts are typically evaluated per lay length and across the rope diameter.

Related: Rope Lay Length, Wire Rope Inspection, Rope Removal Criteria
Rope Removal Criteria

Published conditions that require a wire rope to be replaced, such as broken wire counts, diameter reduction, corrosion, kinking, or heat damage. Inspectors apply them during rope inspection.

Related: Broken Wire Count, Wire Rope Inspection, Sheave Wear
Wire Rope Inspection

A systematic examination of running and standing ropes for broken wires, wear, corrosion, distortion, and end connections. Results are recorded and compared to removal criteria.

Related: Rope Removal Criteria, Broken Wire Count, Wire Rope Lay
Sheave Wear

Loss of groove profile or diameter on a sheave that can damage rope and affect reeving geometry. Inspectors check groove condition and compare sheave diameter to rope diameter.

Related: Wire Rope Inspection, Rope Removal Criteria, Reeving
Reeving

The path and number of rope parts running between boom tip sheaves and the hook block. Incorrect reeving changes load distribution and is verified against the manufacturer's instructions.

Related: Sheave Wear, Hook Block, Deductions
Hook Block

The assembly of hook, sheaves, and weight that carries the load and provides parts of line. Inspectors check hook throat opening, wear, latch function, and sheave condition.

Related: Hook Latch, Throat Opening, Reeving
Hook Latch

A spring-loaded device that closes the hook throat to prevent slings from slipping off. Inspectors verify it is present, undamaged, and closes freely.

Related: Hook Block, Throat Opening
Throat Opening

The inside distance across the hook at its narrowest point. Excessive opening from deformation or wear is a removal criterion for the hook.

Related: Hook Block, Hook Latch
Rigging

The slings, shackles, hardware, and attachments used to connect the load to the hook. Inspectors check identification, condition, and configuration against the lift plan.

Related: Gross Load, Sling Angle, Shackle
Sling Angle

The angle between a sling leg and the horizontal, which determines the tension in each leg. Lower angles increase leg tension and reduce usable capacity.

Related: Rigging, Sling Capacity
Sling Capacity

The maximum load a sling may carry in a given configuration, adjusted for angle, number of legs, and hitch type. Inspectors verify markings and configuration match the lift.

Related: Sling Angle, Rigging, Shackle
Shackle

A U-shaped connector with a pin used to join slings and hardware. Inspectors check for markings, pin security, wear, cracks, and deformation.

Related: Rigging, Sling Capacity
Outrigger

An extendable beam and float that widens the crane's support base and transfers load to the ground. Inspectors check extension, pinning, float condition, and pad bearing.

Related: Ground Bearing Pressure, Level Indicator, Crane Level
Ground Bearing Pressure

The pressure exerted through outrigger floats or crawler tracks onto the supporting surface. Inspectors verify mats, cribbing, and soil conditions are adequate for the planned lift.

Related: Outrigger, Crane Level, Lift Plan
Crane Level

The condition of the crane being set horizontal within the manufacturer's tolerance. Level status affects capacity and is verified with the level indicator before lifting.

Related: Level Indicator, Outrigger, Ground Bearing Pressure
Level Indicator

A bubble or electronic device on the crane that shows whether the machine is level. Inspectors confirm it is present, intact, and readable.

Related: Crane Level, Operator Aids
Pre-Operational Inspection

The check performed before each shift or use, covering fluids, safety devices, controls, ropes, and visible structural condition. Results are documented and deficiencies addressed before operation.

Related: Periodic Inspection, Deficiency, Inspection Record
Periodic Inspection

A more thorough inspection performed at defined intervals based on crane type, use, and manufacturer or regulatory requirements. It covers items not practical to check daily.

Related: Pre-Operational Inspection, Frequent Inspection, Inspection Record
Frequent Inspection

An inspection interval category for equipment in regular service, falling between daily checks and periodic inspections. Items and frequency depend on severity of use and applicable standards.

Related: Periodic Inspection, Pre-Operational Inspection
Deficiency

A condition found during inspection that does not meet requirements and must be corrected or evaluated before continued use. Serious deficiencies require removal from service.

Related: Pre-Operational Inspection, Inspection Record, Removal from Service
Removal from Service

The act of taking a crane or component out of operation because a deficiency makes continued use unsafe. The item is tagged, secured, and reported until repaired and re-inspected.

Related: Deficiency, Inspection Record
Inspection Record

Documentation of inspection date, inspector, items checked, findings, and corrective actions. Records support compliance verification and maintenance history tracking.

Related: Deficiency, Periodic Inspection, Load Test
Load Test

A controlled test applying a specified load to verify crane or lifting equipment strength and function. It is performed under defined procedures and documented with results.

Related: Proof Load, Inspection Record, Operational Test
Proof Load

A test load, usually a percentage above rated capacity, applied to verify structural and mechanical integrity. It is not the same as a working load and is used only under controlled test conditions.

Related: Load Test, Rated Capacity
Operational Test

A function check of crane motions, brakes, and safety devices without necessarily applying a test load. It confirms controls and limits operate as intended.

Related: Load Test, Limit Switch, Anti-Two-Block Device
Lift Plan

A documented description of a lift including load weight, rigging, crane position, capacity analysis, and responsibilities. Inspectors confirm the plan matches actual site conditions.

Related: Rigging, Ground Bearing Pressure, Critical Lift
Critical Lift

A lift that warrants additional planning and oversight, such as near capacity, over occupied areas, or involving multiple cranes. It typically requires a written plan and specific approvals.

Related: Lift Plan, Rated Capacity