Slump test
ASTM C143 test that measures the vertical drop of a molded concrete cone after the mold is lifted; indicates workability and consistency of the mix.
Air content test
ASTM C231 pressure method or ASTM C173 volumetric method; measures entrained air percentage, typically 5 to 7 percent for moderate freeze-thaw exposure.
Bleed water
Water that rises to the concrete surface as heavier solids settle; must evaporate or be removed before floating, or the surface becomes weak and prone to dusting.
Screeding
Striking off excess concrete to the required grade or elevation using a straightedge, screed board, or laser screed; first step after placement and consolidation.
Bull float
Long-handled float with a wide blade used to open the concrete surface, embed aggregate, and knock down ridges left by screeding.
Darby
Hand tool with a long straight blade used after bull floating to true the surface, cut high spots, and fill low spots before troweling.
Power trowel
Rotating-blade machine that compacts and smooths the surface; used after concrete is firm enough to support it without leaving deep marks.
Broom finish
Texture produced by dragging a broom across a floated surface; coarser bristles and deeper drag increase roughness and improve wet slip resistance.
Exposed aggregate finish
Finish achieved by retarding the surface set or washing away the top mortar before full set, exposing the coarse aggregate for texture and appearance.
Stamped concrete
Patterned finish made by pressing imprint tools or mats into colored, partially set concrete to imitate stone, brick, or tile.
Control joint depth
Contraction joints are cut to at least one-quarter of slab thickness, with a 1 in minimum, so the crack forms at the joint rather than randomly.
Control joint spacing
For unreinforced slabs, joint spacing is commonly 24 to 36 times slab thickness, adjusted for shrinkage, subgrade friction, and mix design.
Isolation joint
A joint that separates a slab from columns, walls, or other fixed elements so movement does not crack the slab; often filled with a compressible material.
Construction joint
A planned stopping point in a pour where fresh concrete is placed against set concrete; requires a clean, roughened, and bonded surface.
Curing compound
Liquid membrane sprayed on a fresh surface to slow moisture loss; must be applied at the manufacturer's coverage rate and within the specified window.
Wet curing
Method using ponding, wet burlap, or continuous sprinkling to keep the concrete surface moist for the specified curing period.
Plastic sheeting curing
Polyethylene sheet placed over the concrete to retain moisture; edges must be sealed or weighted to prevent drying from wind.
Cold-weather protection
ACI 306 practice of keeping concrete above 40 to 50 degrees F during curing; uses insulation blankets, heaters, or enclosures to prevent freezing damage.
Hot-weather concreting
ACI 305 practice of cooling concrete, placing at cooler times, and using evaporation retarders when the evaporation rate exceeds 0.2 lb/sq ft/hr.
Plastic shrinkage cracking
Cracks that form in fresh concrete when surface evaporation exceeds bleed water; controlled by windbreaks, fogging, and evaporation retarders.
Dusting
Powdery surface caused by a weak top layer, often from floating bleed water into the surface or finishing too early; corrected by proper timing and curing.
Scaling
Local flaking of the finished surface, usually from freeze-thaw damage, low air content, or finishing while bleed water is present.
Delamination
Separation of a thin top layer from the concrete below, often from troweling too early or trapping air under a dense finish.
Consolidation
Removing entrapped air with internal vibrators or spud vibrators; vibrator should be inserted vertically at regular intervals and withdrawn slowly.
Vibrator spacing
Internal vibrators are typically spaced at about 1.5 times the radius of action, inserted through the lift, and withdrawn slowly to avoid voids.
Saw cutting window
Joints are sawed as soon as concrete is hard enough to resist raveling but before shrinkage cracking begins, often within 4 to 12 hours.
Evaporation rate
Rate of moisture loss from the surface, affected by air temperature, concrete temperature, humidity, and wind; above 0.2 lb/sq ft/hr requires protective measures.
Water-cement ratio
Ratio of water to cementitious material by weight; lower ratios increase strength and durability but reduce workability.
Slump and workability
Slump measures consistency, not strength; adding water increases slump but lowers strength, so plasticizers are used to improve flow without extra water.
Float finish
Textured finish left by a float or trowel without further smoothing; provides moderate slip resistance for walks and drives.
Trowel finish
Smooth, dense finish produced by power or hand troweling; used indoors and where a hard, easy-to-clean surface is required.
Curing duration
Curing period depends on mix and exposure; commonly 7 days for Type I cement and 3 days for high-early-strength, or until specified strength is reached.