NCCER Ironworker flashcards
NCCER Ironworker · Build recall with a focused review session.
31 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Anchor bolt projection tolerance
- Projection of anchor bolts above the base plate is typically allowed to vary ±1/4 in. from the specified dimension. Verify the structural drawings because project-specific tolerances override general practice.
- Standard bolt hole size
- A standard hole is punched or drilled 1/16 in. larger than the nominal bolt diameter. Oversize and slotted holes are permitted only where shown on the approved drawings.
- Turn-of-nut tightening
- A pretensioning method where the nut is rotated a specified fraction of a turn after snugging. The amount depends on bolt diameter, length, and whether the nut is the turned element.
- DTI washer
- A direct tension indicator is a hardened washer with protrusions that compress as the bolt is tensioned. A feeler gauge gap check confirms the required tension has been reached.
- Column plumbness tolerance
- Completed steel columns are typically limited to 1:500 of their height out of plumb, measured between working points. The contract documents may impose a tighter limit.
- Stop hand signal
- A raised clenched fist held overhead signals the crane operator to stop all movement immediately. This signal takes priority over any other signal being given.
- Hoist hand signal
- The signalman raises a thumb upward with the arm to signal the operator to raise the load. The thumb-down version of the same motion signals lower.
- Dog everything signal
- Both arms are extended with palms down and fingers opening and closing, signaling the operator to stop and hold all crane functions in position.
- Wire rope removal criteria
- Remove running wire rope from service when 12 or more randomly distributed broken wires appear in one lay, or 4 broken wires in one strand in one lay.
- Prequalified WPS
- A written welding procedure that meets AWS D1.1 requirements without further testing. It specifies joint detail, electrode, preheat, current, and pass sequence for the weld.
- A992 minimum preheat
- ASTM A992 structural steel under 3/4 in. thick requires a minimum preheat of 50°F per AWS D1.1. Thicker sections and higher-strength steels require higher preheat values.
- Erection stability rule
- Erect the frame in stable, self-supporting units. Never release hoisting equipment from a tier until at least two permanently connected lines of strength are in place.
- Guying versus bracing
- Temporary guying and bracing hold partially erected steel in alignment until permanent connections are complete. They are removed only after the structure is self-supporting.
- Snug-tight condition
- A bolt is snug-tight when the plies are in firm contact and the installer has applied the full effort of an ironworker with an ordinary spud wrench. It is not a tensioned condition.
- Minimum bolt spacing
- Center-to-center spacing of bolts is generally at least 2-2/3 times the bolt diameter, with a minimum edge distance of 1-1/2 times the bolt diameter from a sheared edge.
- Load angle and sling tension
- Sling tension equals load divided by the number of legs, then divided by the sine of the angle from horizontal. A 60° angle gives about 1.155 times the share per leg.
- Concrete cover minimum
- ACI 318 requires 1-1/2 in. cover for beams and columns, 3/4 in. for slabs and walls not exposed to weather, and 2 in. where concrete is cast against earth.
- Minimum clear bar spacing
- Clear spacing between parallel bars must be at least the bar diameter, 1 in., or 4/3 times the nominal maximum coarse aggregate size, whichever is greatest.
- 90-degree standard hook
- A 90° hook requires a bend diameter of 6 bar diameters for No. 3 through No. 8 bars and a straight extension of 12 bar diameters beyond the bend.
- 180-degree standard hook
- A 180° hook requires a bend diameter of 6 bar diameters for No. 3 through No. 8 bars and a straight extension of 4 bar diameters, but not less than 2-1/2 in.
- Class A tension splice
- A Class A lap splice requires 1.0 times the development length and is permitted where 50% or fewer of the bars are spliced within the required lap length.
- Class B tension splice
- A Class B lap splice requires 1.3 times the development length and applies where more than 50% of bars are spliced at one location, or where Class A conditions are not met.
- Mechanical splice strength
- Mechanical couplers and welded splices must develop at least 125% of the specified yield strength of the bar. They are used where lap lengths cannot be provided.
- Bar placement tolerance
- ACI 117 allows ±3/8 in. for bar location in members up to 8 in. deep and ±1/2 in. in members over 8 in. deep, measured from the specified position.
- Bar chair spacing
- Bar chairs and bolsters support the top mat of reinforcement. Typical spacing is 4 ft or less, tight enough to prevent sagging under the weight of workers and concrete.
- Double tie wire
- Bars larger than No. 5, or bars in heavily loaded members, are tied with double wire loops. Ties must prevent movement during concrete placement and vibration.
- Development length
- Development length is the embedment needed for a bar to reach its yield strength in tension. It depends on bar size, concrete strength, cover, spacing, and coating.
- Bar size designation
- A No. 8 bar is 1 in. in diameter and weighs 2.67 lb per foot. Bar numbers correspond to eighths of an inch of nominal diameter for No. 8 and smaller.
- Stirrup spacing
- Stirrups resist shear and confine concrete. Spacing is set by the structural design and is typically tighter near supports where shear forces are highest.
- Reinforcement corrosion protection
- Epoxy-coated bars are used in corrosive environments. Coated bars require longer development lengths and careful handling to prevent coating damage during placement.
- Form tie and bar conflict
- Reinforcement must not be moved to clear form ties without engineer approval. Relocating bars changes cover and effective depth, which affects structural capacity.