- Type M mortar
- Highest-strength mortar (2500 psi) with the highest portland cement content. Used for below-grade walls, retaining walls, and masonry in severe weathering or high-wind zones.
- Type N mortar
- Medium-strength mortar (750 psi) with balanced cement and lime. The general-purpose choice for above-grade exterior walls in moderate weathering and for interior load-bearing walls.
- Mortar sand ratio
- Sand is measured as 2.25 to 3 times the combined cementitious and lime volume. Too much sand weakens the mix; too little makes it stiff and hard to tool.
- Grout lift limits
- Fine grout is placed in lifts no higher than 5 ft; coarse grout in lifts no higher than 12 ft 8 in. Each lift is consolidated before the next is placed.
- Nominal brick dimensions
- A modular brick is 3 5/8 x 2 1/4 x 7 5/8 in. actual, becoming 8 x 2 2/3 x 8 in. nominal with a 3/8 in. mortar joint.
- Concrete block module
- A standard block is 8 x 8 x 16 in. nominal, giving 8 in. of wall height and 16 in. of length per unit. One square foot of wall face needs about 1.125 blocks.
- Running bond
- Every course is offset by half a unit from the course below, so vertical joints never align. This is the most common bond for single-wythe walls and gives good strength.
- Flemish bond
- Each course alternates a stretcher and a header. The pattern is decorative and historically common in brick facades, providing both appearance and cross-wall tying.
- Stack bond
- Units are stacked with vertical joints aligned from course to course. It has little inherent strength and requires horizontal joint reinforcement or a backup wall.
- Wall tie spacing
- Cavity wall ties are placed at 16 in. maximum vertically and 24 in. maximum horizontally. Ties must be embedded in both wythes and slope to drain moisture outward.
- Weep hole spacing
- Weeps are placed at 24 in. maximum on center and immediately above flashing at the base of a cavity wall, keeping the drainage path open.
- Flashing upstand height
- Through-wall flashing turns up the backup wall at least 8 in. and laps the flashing below. The upstand prevents water from bypassing the flashing into the wall.
- Mortar joint thickness
- Bed and head joints are typically 3/8 in. thick. Joints thicker than 1/2 in. reduce mortar strength and are not permitted in structural masonry.
- Masonry cement versus portland
- Masonry cement is a factory blend of portland cement and plasticizers, while portland-lime mortar is mixed on site. The two systems are not interchangeable in a specified mix.
- Efflorescence cause
- Water-soluble salts migrate to the masonry surface and crystallize as a white deposit. It signals moisture movement through the wall, not necessarily defective units.
- Corbel limits
- Each course of corbelling projects no more than one-third of the unit width, and total projection is limited to one-half the wall thickness for solid masonry.
- Plumb tolerance
- Masonry walls must be plumb within 1/4 in. in 10 ft and within 3/8 in. total per story. Engineered work may allow 1/2 in. in any 20 ft.
- Course level tolerance
- Individual courses must be level within 1/4 in. in 10 ft. Bed joint thickness on adjacent courses should not vary more than 1/4 in. over that distance.
- Concave joint tooling
- A round or V-shaped tool compacts the mortar face and sheds water. This joint profile gives the best weather resistance on exterior masonry walls.
- Mortar cube test
- Field samples of mortar are cast in 2 in. cubes or 3 in. cylinders, cured, and tested at 28 days. Results confirm the mix meets the specified compressive strength.
- Prism test purpose
- Prisms built from the project's units, mortar, and grout are tested to verify the compressive strength of the assembled masonry, not just the individual materials.
- Grout slump range
- Grout slump measured at the point of placement must be 8 to 11 in. Slump outside this range indicates a mix that will not flow into voids or will segregate.
- Grout cube testing
- Grout samples are cast in molds and tested at 28 days for compressive strength, commonly 2000 psi minimum. Cubes are cured like the wall before testing.
- Anchor bolt inspection
- Verify bolt diameter, embedment depth, and spacing before grouting. Bolts must be set in grout, not mortar, and positioned with templates to match the sill plate.
- Water penetration test
- A spray rack applies about 5 gal/hr per square foot to a 10 ft by 10 ft wall area for at least 4 hours, and the interior face is checked for leakage.
- Weep hole verification
- Final inspection confirms weep holes are open and unobstructed. Mortar droppings in the cavity or blocked weeps trap water and cause interior leakage.
- Flashing lap check
- Inspection confirms flashing laps are correct and the upstand is sealed to the backup. Reversed laps or unsealed ends let water run behind the flashing.
- Rebar placement check
- Verify bar size, spacing, lap lengths, and cover before grouting. Rebar must be tied in place and centered in the cell so grout fully surrounds it.
- Mortar joint thickness check
- Measure bed and head joints during inspection; they should be about 3/8 in. and not exceed 1/2 in. Oversized joints weaken the wall and are a common rejection item.
- Masonry cleaner test
- Before cleaning a whole wall, test the cleaner on an inconspicuous area to confirm it removes mortar smears without etching or discoloring the units.
- Cavity width tolerance
- The cavity between wythes is typically 2 in. wide with a tolerance of plus or minus 1/2 in. Ties and flashing must accommodate the actual cavity width.