trench

A narrow, relatively deep excavation below ground level made to receive a pipe, conduit, or similar structure; its width is normally kept as close to the pipe as practical.

Related: excavation, trench box, spoil pile
excavation

Any man-made cut, cavity, trench, or depression in the earth's surface formed by removing soil or rock, whether for a pipeline, structure, or utility crossing.

Related: trench, competent person, benching
competent person

A worker capable of identifying existing and predictable hazards in the surroundings or working conditions and authorized to take prompt corrective measures to eliminate them, including trench safety decisions.

Related: excavation, protective system, soil classification
protective system

A method used to prevent cave-ins of trench walls, such as sloping, benching, shoring, or a trench shield, selected according to soil type and depth.

Related: shoring, trench box, sloping
sloping

A protective method in which trench walls are cut back at an angle from the bottom up so the soil stands at a stable incline rather than a vertical face.

Related: benching, protective system, soil classification
benching

A protective method that cuts the trench wall into a series of horizontal steps or ledges; permitted only in stable soil types and not in loose or running ground.

Related: sloping, protective system, soil classification
shoring

A structure of posts, wales, struts, and sheeting that supports trench walls to prevent soil movement; it is installed as excavation progresses and removed from the bottom up.

Related: trench box, protective system, spoil pile
trench box

A prefabricated steel or aluminum shield with two side walls and spreaders that is lowered into a trench to protect workers; it does not shore the soil, it shields them from it.

Related: shoring, protective system, trench
spoil pile

Excavated material placed beside a trench; it must be kept back from the edge to reduce surcharge loading on the walls and to keep tools and traffic clear.

Related: trench, surcharge, excavation
surcharge

Extra load imposed near the top of a trench by spoil, equipment, materials, or vehicles; it increases pressure on the walls and can trigger a cave-in.

Related: spoil pile, protective system, trench
soil classification

The process of judging soil as stable rock, Type A, Type B, or Type C based on strength and stability, which determines the protective system and slope allowed.

Related: competent person, sloping, protective system
access and egress

A safe way for workers to enter and leave a trench, such as a ladder, stairway, or ramp, required when the trench reaches a specified depth and placed within a short travel distance.

Related: trench, competent person, protective system
pipe bedding

The prepared material placed in the trench bottom to support the pipe, such as compacted granular material, sand, or native soil, shaped to give uniform bearing along the barrel.

Related: haunching, over-excavation, trench
haunching

Material placed and compacted in the lower side areas of the pipe, between the bedding and the springline, to lock the pipe in place and distribute loads into the soil.

Related: pipe bedding, springline, backfill
springline

The horizontal line across the widest part of a pipe's outside diameter, halfway up the pipe; it marks the boundary between haunching and the upper side fill.

Related: haunching, pipe bedding, invert
backfill

Material placed in the trench above the pipe bedding and haunching to fill the excavation, usually placed in lifts and compacted to the required density.

Related: haunching, lift, compaction
lift

A layer of backfill or bedding material of controlled thickness that is placed and compacted before the next layer is added, keeping density uniform over the pipe.

Related: backfill, compaction, pipe bedding
compaction

Mechanical densification of soil by removing air voids, done in lifts with tampers or rollers to reach a specified percentage of maximum dry density.

Related: lift, backfill, density test
density test

A field test, such as a sand cone or nuclear gauge check, that measures the in-place compacted density of backfill against the project's required percentage.

Related: compaction, lift, backfill
invert

The lowest point of the inside of a pipe or channel at a given cross section; invert elevation is the reference used for setting sewer and drain grade.

Related: grade, flow line, springline
flow line

The inside bottom surface of a pipe or ditch along its length, which carries the water; its elevation is used to compute slope and verify fall between structures.

Related: invert, grade, laser level
grade

The elevation or slope at which a pipe is set, usually expressed as a percentage or as fall per unit length, so gravity carries flow in the intended direction.

Related: invert, flow line, laser level
laser level

A tool that projects a level or sloped reference beam along the trench, used with a target rod or pipe laser to set and check pipe invert elevations accurately.

Related: grade, invert, offset
offset

A measured horizontal or vertical distance from a fixed reference, such as a hub or laser line, to the point where the pipe is to be placed or checked.

Related: laser level, hub, batter board
hub

A short stake driven into the ground to mark a survey point such as a line or grade reference; a tack or nail in its top marks the exact location.

Related: batter board, offset, grade
batter board

A horizontal board fixed to stakes alongside the trench to carry line and grade marks, allowing the pipe crew to stretch a line and measure offsets.

Related: hub, offset, grade
over-excavation

Digging below the required trench bottom; the resulting void must be backfilled with approved compacted material rather than left to create an unsupported pipe span.

Related: pipe bedding, compaction, trench
bell and spigot

A joint design in which the enlarged end (bell) of one pipe receives the plain end (spigot) of the next, with the gap sealed by gasket, mortar, or sealant.

Related: gasket, push-on joint, joint
gasket

A rubber or elastomeric ring seated in a groove or on the spigot that is compressed when pipes are joined to form a watertight seal against infiltration and exfiltration.

Related: bell and spigot, push-on joint, lubricant
push-on joint

An assembly method where a lubricated gasket and spigot are pushed into the bell, often with a bar or jack, until the pipe is seated at the reference mark.

Related: gasket, bell and spigot, lubricant
mechanical joint

A bolted joint using a gland and follower ring to compress a gasket against the pipe end, allowing restrained or flexible connections between pipe sections and fittings.

Related: gasket, restrained joint, joint
restrained joint

A joint designed to resist longitudinal pullout forces from internal pressure or ground movement, using locks, rods, or clamped glands rather than friction alone.

Related: mechanical joint, thrust block, joint
thrust block

A concrete mass poured against a fitting or bend to absorb the unbalanced thrust from internal pressure, preventing the pipe from separating or shifting at changes in direction.

Related: restrained joint, bend, joint
solvent cement

A fluid that softens the surfaces of plastic pipe and fitting so they fuse together; applied to both surfaces before assembly to create a welded joint.

Related: primer, joint, bell and spigot
primer

A preparatory liquid applied to plastic pipe and fittings before solvent cement to clean and soften the surface, promoting a strong, uniform fused joint.

Related: solvent cement, joint
deflection

The amount a pipe bends or deviates from a straight line, either intentionally at joints to make a curve or unintentionally under load; limits are set by the pipe manufacturer.

Related: joint, alignment, springline
alignment

The horizontal position of a pipeline along its planned route, maintained by string line, laser, or survey so the pipe stays on the designed centerline.

Related: offset, deflection, grade
string line

A taut cord stretched between stakes or batter boards along the trench to show the pipe centerline or grade, used to check alignment as pipe is laid.

Related: batter board, alignment, offset
hydrostatic test

A pressure test in which a completed pipeline section is filled with water and held at a specified pressure to reveal leaks before the trench is backfilled.

Related: joint, thrust block, backfill