- Ohm's law
- Voltage equals current multiplied by resistance (V = I × R). Used to check conductor loading, calculate voltage drop, and confirm a circuit will operate within equipment ratings.
- Power formula
- Electrical power equals voltage times current (P = V × I), and also I²R or V²/R. It determines heat load, conductor ampacity needs, and equipment supply sizing.
- Decibel definition
- A logarithmic ratio comparing two power levels: dB = 10 log(P1/P2). Positive values mean gain, negative values mean loss, and 3 dB equals a doubling of power.
- Characteristic impedance
- The inherent AC resistance of a transmission line, set by conductor geometry and insulation. Twisted pair is near 100 Ω, video coax 75 Ω, and many RF runs 50 Ω.
- Horizontal cabling limit
- TIA-568 permits 90 m of permanent horizontal link plus up to 10 m of patch cords, giving a maximum 100 m channel. Exceeding it risks failing insertion loss and length tests.
- Single-mode fiber
- Fiber with an approximately 8–10 µm core carrying one propagation mode. Used with 1310 nm or 1550 nm sources for long-distance and high-bandwidth links with low attenuation.
- Multimode fiber
- Fiber with a 50 or 62.5 µm core supporting many light paths, used with 850 nm or 1300 nm sources. Suited to shorter building and campus runs; modal dispersion limits distance.
- T568B pinout
- Wiring order for an RJ45 jack: white-orange, orange, white-green, blue, white-blue, green, white-brown, brown. Both ends must use the same scheme for a straight-through link.
- Telecommunications bonding conductor
- The conductor that connects the telecommunications main grounding busbar to the telecommunications grounding busbar and to the building grounding electrode system, per TIA-607 and NEC.
- Split pair fault
- A wiring error where a conductor from one pair is paired with a conductor from another. Continuity passes but crosstalk rises sharply, causing NEXT failures.
- Velocity of propagation
- The speed of a signal in a cable expressed as a fraction of the speed of light, typically 0.6–0.8 for copper. Testers use NVP to convert reflection time into length.
- NEC Article 800
- The National Electrical Code article governing communications circuits, covering cable listing, protection, grounding, and separation from power conductors in buildings.
- Insertion loss
- Signal power lost as it travels through a link, expressed in decibels at a specified frequency. It rises with length, temperature, and poor connections or terminations.
- Near-end crosstalk
- NEXT measures signal coupled from one pair into another, measured at the same end as the transmitter. Higher NEXT values in dB mean better separation between pairs.
- Return loss
- The ratio of reflected signal to incident signal at an impedance mismatch, in dB. Poor terminations, kinks, and wrong connectors degrade return loss and raise bit errors.
- Fiber end-face inspection
- Examining a connector ferrule under a 200×–400× scope before mating. Scratches, pits, or debris cause high loss and must be cleaned and re-inspected.
- OTDR trace
- A time-domain reflectometry plot of backscattered light versus distance, showing splice and connector losses and reflective events. Correct index of refraction and pulse width are required.
- Optical loss budget
- The maximum allowable loss for a fiber link, calculated from source power, receiver sensitivity, connector and splice losses, and fiber attenuation. Measured loss must stay below it.
- Reference power measurement
- Recording the source output at the meter before testing a link. This reference is subtracted from the measured level to give link loss in dB.
- Ground resistance test
- Using a ground resistance tester to measure resistance from the telecommunications ground bar to earth. Low resistance confirms a safe fault-current path.
- Wire map test
- A continuity test verifying each pin connects to the correct pin at the far end. It detects opens, shorts, crossed pairs, and split pairs before other tests run.
- Certification tester calibration
- Verifying the field tester's calibration status and reference before testing. An out-of-calibration tester invalidates results and can cause false pass or fail reports.
- Link length test
- A tester measurement of cable length using TDR and the set NVP. Results over the 90 m permanent link limit fail the TIA-568 length requirement.
- Attenuation test
- A fiber or copper measurement of signal loss through the link at specified wavelengths or frequencies. Results are compared to the calculated loss budget for pass/fail.
- Cable labeling
- Marking both ends of every cable with the same unique identifier matching the as-built drawings, enabling traceability during moves, adds, and troubleshooting.
- Test report traceability
- Recording tester serial number, calibration due date, date, operator, and link ID with results so the certification report can be audited and reproduced later.
- Patch cord length rule
- Total patch cord length in a channel must not exceed 10 m when the permanent link is at its 90 m maximum, keeping the channel within 100 m.
- Index of refraction setting
- The fiber-specific value entered into an OTDR that converts time to distance. An incorrect value shifts reported event distances and can misplace faults.
- Launch and receive cable
- Fiber reference cables attached to both OTDR ports to measure the near and far connectors accurately. Without them, end connector loss is hidden in the dead zone.
- Continuity verification
- Confirming a conductor path is complete and unbroken using a meter or tester before energizing. It is the first check after termination and before certification.
- As-built documentation
- The final record of installed cable routes, labels, terminations, and test results reflecting actual field conditions. It supports maintenance and future upgrades.