ARCON PPCE: Contract Administration and Project Management

ARCON PPCE · Work through your exam, one topic at a time.

All guide sections

Contract Administration and Project Management

Procurement and the contract

Contract administration questions test the architect as impartial certifier and as the client's adviser. Know the procurement routes (traditional, design and build, management contracting), the tender sequence from prequalification to award, and the contract forms in use: the NIA form, JCT, FIDIC and the Federal Government standard form for building works. The contract documents are the agreement, conditions, drawings, specification, bills of quantities and programme; where they conflict, the stated order of precedence governs.

Administering the works

Issue instructions in writing and confirm oral ones promptly. Value variations before execution where possible. Certify interim valuations, deduct retention (commonly 5%, part-released at practical completion) and apply the contractual payment period. Grant extensions of time only on contractual grounds and notify accordingly. Distinguish practical completion, where the building is fit for purpose, a defects list is issued, the defects liability period begins and half the retention is released, from final completion, where making good is certified, the final account is agreed and the balance is paid.

Worked example

Contract sum 200 million, liquidated damages 0.5% per week capped at 10%. The works finish 8 weeks late. Five weeks of delay flow from late client instructions, so a 5-week extension is granted. LD applies to the remaining 3 weeks: 0.5% of 200 million is 1 million per week, so 3 million is deducted, well within the cap.

Traps

Certifying work not executed; granting an extension without notice or without a programme; releasing all retention at practical completion; letting the client instruct subcontractors directly and break the chain of responsibility.