CPE I flashcards
CPE I · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Factor of safety
- Ratio of a material's failure stress to the allowable working stress. It accounts for uncertainty in loads, material properties, analysis methods, and consequences of failure.
- Two-force member
- A body loaded only at two points with no applied moments. For equilibrium, the forces at both points must be equal, opposite, and collinear along the line joining them.
- Beam bending stress
- Normal stress from bending equals Mc/I, where M is the bending moment, c the distance from the neutral axis to the extreme fiber, and I the area moment of inertia.
- Reynolds number
- Dimensionless ratio of inertial to viscous forces, rho times velocity times diameter divided by viscosity. It predicts whether pipe flow is laminar or turbulent.
- Bernoulli equation
- Along a streamline in steady, incompressible, inviscid flow, pressure head plus velocity head plus elevation head is constant. It trades pressure against speed and height.
- Yield strength 0.2% offset
- For metals lacking a distinct yield point, draw a line parallel to the elastic slope offset by 0.2% strain; its intersection with the stress-strain curve defines yield strength.
- Three-phase real power
- Real power in a balanced three-phase circuit equals the square root of three times line-to-line voltage times line current times power factor.
- Verification versus validation
- Verification asks whether the design meets its stated requirements. Validation asks whether those requirements actually capture the user's real need. Both are required.
- Pugh matrix
- A concept screening tool scoring alternatives against a datum concept using better, same, or worse marks. It eliminates weak concepts rather than producing final weighted rankings.
- Worst-case tolerance stack
- Total variation equals the arithmetic sum of individual tolerances. It is conservative and appropriate when parts may assemble at opposing tolerance extremes.
- Statistical tolerance stack
- Total variation equals the square root of the sum of squared individual tolerances. Valid only when part dimensions are independent, centered, and roughly normally distributed.
- RPN in FMEA
- Risk priority number equals severity times occurrence times detection, each scored on a defined scale. High-severity failure modes warrant action regardless of the computed number.
- Design of experiments
- A structured set of runs varying factors together so main effects and interactions can be estimated. Randomization, replication, and blocking protect against confounding.
- Critical path
- The longest-duration chain of dependent activities through a project network. It determines the shortest possible project duration and has zero total float.
- Total float
- The amount an activity can be delayed without delaying the project finish. It equals late start minus early start, or late finish minus early finish.
- Cost performance index
- Earned value divided by actual cost. A value below one means each unit of completed work is costing more than budgeted, indicating a cost overrun.
- Schedule performance index
- Earned value divided by planned value. A value below one means less work has been completed than planned for the reporting date.
- Estimate at completion
- Forecast total project cost. Divide budget at completion by cost performance index if current cost efficiency persists; add actual cost to remaining budget if work returns to plan.
- Crashing versus fast-tracking
- Crashing adds resources to critical-path activities to shorten duration, usually raising cost. Fast-tracking overlaps sequential activities, saving time but increasing rework risk.
- Control chart signal
- A process is out of statistical control when a point falls beyond a control limit, or when a run of seven consecutive points sits on one side of the centerline.
- Process capability Cpk
- Cpk equals the smaller of the upper and lower specification distances from the process mean, divided by three sigma. It penalizes processes whose mean is off-center.
- Hierarchy of controls
- Effectiveness order for hazard control: elimination, substitution, engineering controls, administrative controls, then personal protective equipment. PPE is the least reliable measure.
- ISO 9001 scope
- An international standard specifying requirements for a quality management system, including documented processes, customer focus, and continual improvement. Certification comes from accredited registrars.
- OSHA fatality reporting
- US employers must report work-related fatalities to OSHA within eight hours, and in-patient hospitalizations, amputations, or losses of an eye within twenty-four hours.
- Root cause analysis
- A structured method such as 5 Whys, fishbone diagram, or fault tree analysis that identifies the underlying system cause of a problem rather than its immediate trigger.
- Paramount obligation
- The engineer's first duty is protecting public health, safety, and welfare. It takes precedence over obligations to clients, employers, and project schedules.
- Competence rule
- Engineers accept only work they are qualified to perform. If assigned outside their competence, they must disclose the limit and obtain qualified assistance before proceeding.
- Conflict of interest
- A financial or personal interest that could impair professional judgment. The ethical violation is failing to disclose it, not merely holding the interest.
- Sealing engineering work
- A licensed engineer signs and seals only documents they prepared or directly supervised. Sealing another's unreviewed work is misconduct in every US licensing jurisdiction.
- Whistleblower escalation
- Report a serious safety or legal concern internally first, then to the appropriate regulator. Public disclosure is a last resort when those channels fail and harm is imminent.
- RACI matrix
- A responsibility chart assigning each task exactly one accountable party, at least one responsible party, plus consulted and informed parties. It prevents gaps and duplicated ownership.
- Tuckman team stages
- Teams progress through forming, storming, norming, performing, and adjourning. Conflict peaks during storming and subsides as roles and working norms are clarified.