NICET HCI study materials
NICET HCI study resources

NICET HCI flashcards

NICET HCI · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Station 100+00
On highway plans, station 100+00 represents 1,000 feet from the baseline origin. One full station equals 100 feet, and stationing increases along the baseline direction.
Pipe invert elevation
The invert is the inside bottom, or flowline, elevation at a pipe end. Crown elevation equals invert elevation plus the pipe internal diameter.
Order of precedence
Contract clauses that establish which document governs when plans and specifications conflict. Special provisions generally outrank standard specifications, and written directives outrank field opinions.
Daily inspection report
A record of weather, contractor forces, equipment, work locations by station, pay quantities, tests, visitors, delays, and instructions. It supports payment and documents project events.
Approved equal submittal
A contractor request to use a product that differs from the specified item but is judged equivalent. The engineer's written approval is required before installation.
Average end-area formula
Volume formula V = L(A1 + A2)/2 for earthwork between two stations. Areas are in square feet; divide the result by 27 to convert cubic feet to cubic yards.
Swell factor
The percentage increase in volume when soil is excavated from its natural bank state to a loose condition. Swell percent equals loose volume minus bank volume, divided by bank volume, times 100.
Standard Proctor test
A laboratory compaction test that determines maximum dry density and optimum moisture content for a soil. Field density is reported as a percentage of that maximum.
Proofrolling
Passing a loaded truck or roller over prepared subgrade to reveal soft spots, pumping, or unstable areas. Defects are removed or repaired before embankment or pavement is placed.
Trench protective system
A shoring, shielding, or sloping system required for excavations 5 feet deep or more. A competent person inspects the excavation daily and after changes.
Maximum theoretical density
The laboratory density of an asphalt mixture with no air voids, used as the reference for field compaction. Field density is reported as a percentage of Gmm.
Tack coat
A light spray application of asphalt emulsion to an existing pavement or base surface. It promotes bonding between layers and must break before the next layer is placed.
Prime coat
Asphalt material applied to an untreated aggregate base to seal the surface and promote bonding. It is cured and blotted before asphalt paving.
Segregation
Separation of coarse aggregate from the asphalt mixture, producing dry, coarse patches. It results from improper loading, discharge, or paver operation and is not accepted.
Straightedge smoothness check
A 10-foot straightedge laid on the finished pavement surface to measure deviation. Deviations exceeding the specified tolerance, commonly 1/4 inch, are corrected.
Air content test
A field test using a pressure meter or volumetric apparatus to measure entrained air in concrete. Required air content depends on aggregate size and freeze-thaw exposure.
Saw-cut joint depth
Contraction joints are cut about one-quarter to one-third of the slab thickness. Timing is as soon as sawing does not ravel the concrete.
Dowel bar
A smooth steel bar placed across a transverse joint to transfer load between slabs. It allows joint opening and closing while keeping slab elevations aligned.
Tie bar
A deformed steel bar placed across a longitudinal joint to hold adjacent lanes together. It restrains lane separation and is not intended to permit joint movement.
Curing compound
A liquid membrane sprayed on fresh concrete to reduce moisture loss. It is applied at the specified coverage rate and typically protects the concrete for seven days.
Manning's equation
An open-channel flow formula: Q = (1.486/n) A R^(2/3) S^(1/2) in English units, where n is roughness, A is area, R is hydraulic radius, and S is slope.
Rational method
A peak storm flow formula Q = C i A, where C is runoff coefficient, i is rainfall intensity, and A is drainage area. Units must be consistent.
Catch basin sump
A depression below the outlet invert of a catch basin that traps sediment and debris. Sump depth is specified, commonly 6 to 12 inches.
Silt fence
A temporary sediment barrier made of geotextile supported by posts. It is installed on the contour with the fabric keyed into the ground and is not used in concentrated flow.
Concrete cover
The distance from the outer concrete surface to the nearest reinforcement. Typical values are 3 inches against earth and 2 inches for exposed surfaces, subject to exposure requirements.
Falsework inspection
Checking formwork and temporary support for alignment, elevation, bracing, and stability before concrete placement. It protects against deflection, collapse, and misalignment.
Turn-of-nut method
A bolted connection tightening method in which specified nut rotation after snugging develops tension. Inspection verifies rotation and proper bolt length.
Pile driving record
Documentation of hammer type, blows per foot, pile penetration, tip elevation, and bearing during driving. It is used to verify the required bearing capacity.
Merging taper length
For speeds of 40 mph or less, taper length L equals offset width W in feet times speed S in mph. For 45 mph and above, L equals W times S squared divided by 60.
Buffer space
A longitudinal or lateral area in a temporary traffic control zone kept free of workers and equipment. It separates traffic from the work space and provides recovery distance.
Activity area
The part of a temporary traffic control zone containing the work space, traffic space, and buffer space. It is where work occurs and where traffic is maintained.
Flagger station
The location where a flagger controls traffic with a STOP/SLOW paddle. It is placed before the work area with an escape route and adequate sight distance.