NICET ITFAS flashcards
NICET ITFAS · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- NFPA 72 Chapter 14
- Chapter covering inspection, testing, and maintenance of fire alarm systems; Table 14.4.3.2 lists minimum frequencies and test methods for each component type.
- Acceptance test
- Functional test of 100 percent of system devices performed after installation and before the system is placed in service; establishes the baseline for periodic testing.
- Inspection versus testing
- Inspection is a visual or mechanical check without applying a stimulus; testing applies a stimulus and verifies the device or system response. Reports must state which was done.
- Notification appliance test frequency
- Notification appliances are tested semiannually under Table 14.4.3.2, verifying audibility and intelligibility against the design criteria and recording sound pressure readings.
- Battery load test
- Annual test of secondary batteries under load; capacity must meet the calculated standby plus alarm demand with a 20 percent derating and end-of-life margin.
- Battery calculation basis
- Standby load for the required duration plus alarm load for the alarm duration, typically 24 hours standby plus 5 minutes alarm, with 20 percent derating applied.
- Smoke detector sensitivity test
- Verifies detector response falls within the manufacturer's listed sensitivity range; out-of-range results require cleaning, recalibration, or replacement, and values are recorded.
- Duct smoke detector test
- Annual test using smoke or aerosol to confirm alarm response, correct supervisory and trouble signaling, remote test station operation, and proper sampling tube airflow.
- Waterflow switch test
- Verifies the switch operates at the manufacturer's listed flow rate and annunciates within the required time, typically 90 seconds of flow at the alarm threshold.
- Valve tamper switch test
- Exercises the switch through its full travel to confirm a supervisory signal is produced when the valve moves from its normal open or closed position.
- Supervising station signal test
- Confirms the supervising station receives alarm, supervisory, trouble, and restoration signals and that receipt time meets the required performance for the transmission means.
- Record of completion
- Document identifying the system, its components, and acceptance test results; it is updated after modifications and retained for the life of the system.
- Reacceptance testing
- Testing required after modification, repair, or replacement of system components; covers the changed items plus verification that the remainder of the system still functions.
- Initiating device circuit test
- Each device is actuated individually and the resulting alarm annunciation is verified for correct address, zone, and location description at the control unit.
- Trouble condition test
- Introduces an open circuit, ground fault, or device removal and verifies the control unit annunciates the correct trouble signal within the required time.
- Ground fault investigation
- A ground fault indication must be located and corrected; clearing the indication without finding the fault does not constitute a passing test.
- Audibility measurement
- Sound pressure measured with a calibrated meter, A-weighted, at the specified distance or at the pillow in sleeping areas, and compared to design criteria above ambient.
- Intelligibility verification
- Confirms voice messages are understandable in the occupied areas served; measured or assessed per the design method and documented in the test record.
- Visual appliance inspection
- Checks candela rating, mounting height, and coverage against the design, and confirms the appliance is unobstructed and operating.
- Sequence of operations verification
- Confirms each initiating device activates the correct outputs, time delays, and priorities as designed; correct alarm with wrong output is a failed test.
- Interface testing
- Verifies emergency control functions such as HVAC shutdown, door release, elevator recall, and suppression system interfaces initiate and respond correctly.
- Impairment procedure
- When a system is out of service, the impairment is documented with start and end times, the owner and AHJ are notified, and approved mitigation such as a fire watch is provided.
- Fire watch
- Temporary human patrol or other approved mitigation used while a fire alarm system or portion of it is impaired and not providing detection or notification.
- Test equipment calibration
- Instruments such as sound level meters and test smoke or heat sources must be within calibration so recorded results are traceable and defensible.
- Failed device tracking
- Devices that fail testing are recorded as failed and tracked until repaired and successfully retested; they are not removed from the report or reported as passing.
- Untested device reporting
- Devices that were inaccessible, impaired, or deferred are reported as not tested rather than passed, so the record accurately reflects system condition.
- Test record contents
- Records identify device, location, test method, result, date, and the person and firm performing the work, and a copy is provided to the owner.
- Annual control unit test
- Control equipment is tested annually, including primary power, secondary power transfer, signal processing, annunciation, and correct response to all input conditions.
- Primary power test
- Verifies the control unit operates on primary power, that the dedicated circuit is correct, and that a primary power failure produces the required trouble signal.
- Secondary power test
- Confirms the system operates from batteries or another secondary source for the required duration and that the transfer and recharge functions work correctly.
- Magnet test
- Method of actuating magnetically operated initiating devices to verify the device reports the correct alarm at the control unit without introducing smoke or heat.
- Aerosol smoke test
- Method of introducing controlled smoke or aerosol into a smoke detector to verify alarm response and correct annunciation during periodic testing.