Question 1Codes, Standards, and Reference Documents
Which NFPA document is the primary standard for the inspection, testing, and maintenance of water-based fire protection systems?
- NFPA 25 Correct answer.
- NFPA 72
- NFPA 13
- NFPA 14
Explanation
NFPA 25, Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems, establishes minimum ITM requirements for sprinkler systems, standpipes, private service mains, fire pumps, tanks, and associated equipment once a system is in service.
Question 2Codes, Standards, and Reference Documents
Requirements for sprinkler spacing, pipe sizing, and hangers and bracing of a new automatic sprinkler system are found in which document?
- NFPA 13 Correct answer.
- NFPA 20
- NFPA 25
- NFPA 24
Explanation
NFPA 13, Standard for the Installation of Sprinkler Systems, contains the design, spacing, and installation requirements that apply when the system is built. NFPA 25 takes effect after acceptance and addresses inspection, testing, and maintenance.
Question 3Codes, Standards, and Reference Documents
In an NFPA code or standard, a provision that uses the word "shall" is:
- recommended
- mandatory Correct answer.
- advisory
- optional
Explanation
NFPA documents use "shall" to indicate a mandatory requirement, "should" to indicate a recommendation or advisory provision, and "may" to indicate something that is permitted but not required.
Question 4Codes, Standards, and Reference Documents
Within an NFPA standard, annex material is best described as:
- mandatory whenever it is labeled Annex A
- informational only, not mandatory Correct answer.
- enforceable once the AHJ adopts the standard
- equivalent to a numbered chapter
Explanation
Annexes in NFPA documents are explanatory and informational, and they are not part of the mandatory requirements. The enforceable requirements are found in the chapters and numbered sections of the body of the document.
Question 5Codes, Standards, and Reference Documents
Per NFPA 291, a hydrant whose flow test shows an available capacity of 1,200 gpm is classified and color-coded as:
- Class C, red
- Class B, orange
- Class A, green Correct answer.
- Class AA, blue
Explanation
NFPA 291 classifies hydrants by available flow: Class AA (blue) at 1,500 gpm or greater, Class A (green) at 1,000 to 1,499 gpm, Class B (orange) at 500 to 999 gpm, and Class C (red) below 500 gpm.
Question 6Codes, Standards, and Reference Documents
Which document contains the design and installation requirements for the fire alarm control unit and notification appliances that receive signals from a sprinkler system?
- NFPA 70
- NFPA 101
- NFPA 72 Correct answer.
- NFPA 25
Explanation
NFPA 72, National Fire Alarm and Signaling Code, governs the design, installation, testing, and maintenance of alarm control equipment and notification appliances, including circuits that monitor sprinkler waterflow and valve tamper switches.
Question 7Codes, Standards, and Reference Documents
Under NFPA 25, who is responsible for ensuring that required inspections, tests, and maintenance are performed?
- The property insurance carrier
- The authority having jurisdiction
- The owner or the owner's designee Correct answer.
- The contractor that installed the system
Explanation
NFPA 25 places the responsibility for inspection, testing, and maintenance on the owner or the owner's designated representative. The work must be done by qualified personnel, but the obligation remains with the owner.
Question 8Codes, Standards, and Reference Documents
Which document contains the requirements for the design and construction of water storage tanks used for private fire protection?
- NFPA 25
- NFPA 24
- NFPA 13
- NFPA 22 Correct answer.
Explanation
NFPA 22, Standard for Water Tanks for Private Fire Protection, covers the design, construction, and erection of fire protection water tanks. NFPA 25 addresses the inspection, testing, and maintenance of those tanks after they are in service.
Question 9Codes, Standards, and Reference Documents
Under NFPA 25, how often is a main drain flow test required on a wet pipe sprinkler system?
- Monthly
- Annually Correct answer.
- Weekly
- Quarterly
Explanation
NFPA 25 requires the main drain test annually at each system riser. The test verifies that the water supply is unobstructed and that control valves are open by comparing static and residual pressures with previous readings.
Question 10Codes, Standards, and Reference Documents
NFPA 25 requires a fire pump to be started and run at no-flow (churn) at which minimum frequency?
- Annually
- Quarterly
- Monthly
- Weekly Correct answer.
Explanation
Fire pumps must be started and run weekly at no flow to confirm automatic starting, proper pressure, and correct operation of the driver and controller. A flow test at the pump's rated points is required annually.
Question 11Codes, Standards, and Reference Documents
A new sprinkler system is hydrostatically tested at a minimum pressure and duration of:
- 100 psi for 1 hour
- 200 psi for 2 hours Correct answer.
- 250 psi for 4 hours
- 150 psi for 2 hours
Explanation
NFPA 13 requires the hydrostatic test to be conducted at not less than 200 psi for 2 hours, or at 50 psi above the normal working pressure where that value exceeds 200 psi.
Question 12Codes, Standards, and Reference Documents
A sprinkler system contains 800 sprinklers. What is the minimum number of spare sprinklers of each type and temperature rating that must be kept on the premises?
- 6
- 24
- 36
- 12 Correct answer.
Explanation
NFPA 13 requires at least 6 spare sprinklers for systems with 300 or fewer sprinklers, 12 for systems with 301 through 1,000 sprinklers, and 24 for systems with more than 1,000 sprinklers. A sprinkler wrench of the correct type must also be provided.
Question 13Codes, Standards, and Reference Documents
A glass-bulb sprinkler with a temperature rating of 286°F has a bulb color of:
- Red
- Blue
- Green Correct answer.
- Yellow
Explanation
The NFPA 13 color code for glass bulbs runs orange or red for 135-170°F, yellow for 175-225°F, green for 250-300°F, blue for 325-375°F, purple for 400-475°F, and black for 500-575°F.
Question 14Codes, Standards, and Reference Documents
How often does NFPA 25 require waterflow alarm devices on a wet pipe sprinkler system to be tested?
- Monthly
- Annually
- Quarterly Correct answer.
- Semiannually
Explanation
Waterflow alarm devices are tested quarterly by opening the inspector's test connection and confirming that the alarm activates and transmits the required signal. This interval applies to both mechanical and pressure-type devices.
Question 15Codes, Standards, and Reference Documents
During an inspection you find a sprinkler that has been painted over. What does NFPA 25 require?
- The sprinkler shall be tagged for review at the next inspection
- The sprinkler shall be cleaned and returned to service
- The sprinkler shall be replaced Correct answer.
- The sprinkler may stay in service if the heat-responsive element is clear
Explanation
NFPA 25 requires sprinklers that are painted, corroded, damaged, leaking, or that have lost bulb fluid to be replaced. Field cleaning or recoating cannot restore the original thermal response or discharge pattern.
Question 16Codes, Standards, and Reference Documents
For a standard spray sprinkler installed under a smooth, flat ceiling, NFPA 13 requires the deflector to be positioned:
- not less than 1 in. and not more than 16 in. below the ceiling
- not less than 2 in. and not more than 6 in. below the ceiling
- not less than 4 in. and not more than 18 in. below the ceiling
- not less than 1 in. and not more than 12 in. below the ceiling Correct answer.
Explanation
NFPA 13 sets the deflector position for standard spray sprinklers at a minimum of 1 in. and a maximum of 12 in. below the ceiling. This range allows the spray pattern to develop while limiting how far combustion products must travel to reach the element.
Question 17Codes, Standards, and Reference Documents
The inspector's test connection on a wet pipe sprinkler system is sized so that it simulates the flow of:
- One sprinkler Correct answer.
- Two sprinklers
- The four most remote sprinklers
- The system design flow
Explanation
The inspector's test connection is provided with an orifice equal to the smallest sprinkler orifice on the system, so flow through it represents a single sprinkler operating. This allows the alarm to be tested without opening a real sprinkler.
Question 18Codes, Standards, and Reference Documents
Which document specifies the standard screw thread dimensions for fire hose couplings used on standpipe outlets and hydrants?
- NFPA 291
- NFPA 24
- NFPA 1963 Correct answer.
- NFPA 14
Explanation
NFPA 1963, Standard for Fire Hose Connections, establishes the national standard hose thread used on fire department connections, hydrants, and standpipe outlets so that hose from any responding department will fit.
Question 19Codes, Standards, and Reference Documents
NFPA 25 requires a flow test of a standpipe system at intervals not exceeding:
- 2 years
- 5 years Correct answer.
- 3 years
- 1 year
Explanation
NFPA 25 requires standpipe systems to be flow tested every 5 years to confirm that the required pressure and flow are available at the hydraulically most remote outlet. This is separate from the annual inspection of hose valves, piping, and caps.
Question 20Codes, Standards, and Reference Documents
NFPA 291 is best described as:
- A guide for the design, testing, and acceptance of fire pumps
- A code for inspection, testing, and maintenance of water-based systems
- A standard for the installation of private fire service mains and appurtenances
- A recommended practice on fire flow testing Correct answer.
Explanation
NFPA 291, Recommended Practice for Fire Flow Testing and Marking of Hydrants, is issued as a recommended practice, so its provisions are advisory rather than mandatory unless they are adopted or referenced as requirements.
Question 21Codes, Standards, and Reference Documents
NFPA 20 requires that a fire pump be capable of delivering 150 percent of its rated flow at not less than:
- 100 percent of rated head
- 50 percent of rated head
- 125 percent of rated head
- 65 percent of rated head Correct answer.
Explanation
NFPA 20 requires the pump to produce not less than 150 percent of rated flow at not less than 65 percent of rated head, which defines the allowable shape of the pump curve. Shutoff (churn) pressure may not exceed 140 percent of rated pressure.
Question 22Codes, Standards, and Reference Documents
Before being placed in service, a new private fire service main must be hydrostatically tested at:
- 200 psi for 2 hours Correct answer.
- 150 psi for 4 hours
- 100 psi for 1 hour
- 50 psi above the working pressure for 1 hour
Explanation
NFPA 24 requires private fire service mains to be hydrostatically tested at not less than 200 psi for 2 hours. Where the normal working pressure exceeds 150 psi, the test pressure is increased to 50 psi above the working pressure.
Question 23Codes, Standards, and Reference Documents
For a Class I standpipe system, NFPA 14 requires a residual pressure of at least 100 psi at:
- The base of the standpipe riser
- The fire department connection
- The lowest 1½ in. outlet
- The most remote 2½ in. outlet Correct answer.
Explanation
NFPA 14 requires 100 psi residual pressure at the hydraulically most remote 2½ in. outlet of a Class I or Class III system while flowing the design number of outlets. Class II 1½ in. occupant outlets require 65 psi.
Question 24Codes, Standards, and Reference Documents
NFPA 25 requires a full-flow trip test of each dry pipe valve at intervals not exceeding:
- 1 year
- 3 years Correct answer.
- 5 years
- 10 years
Explanation
In addition to the annual trip test, a full-flow trip test is required at intervals not exceeding 3 years. It verifies that the valve trips and that water reaches the system within the required time while flowing at system demand.
Question 25Codes, Standards, and Reference Documents
A sprinkler system waterflow alarm must actuate within what maximum time after flow begins at the inspector's test connection?
- 60 seconds
- 120 seconds
- 30 seconds
- 90 seconds Correct answer.
Explanation
NFPA 72 requires the waterflow alarm to actuate within 90 seconds after flow begins at the inspector's test connection. Vane-type and pressure-type switches are tested against this limit during the quarterly device test.
Question 26Codes, Standards, and Reference Documents
Which NFPA document contains the installation requirements for private fire service mains and their appurtenances?
- NFPA 13
- NFPA 291
- NFPA 24 Correct answer.
- NFPA 25
Explanation
NFPA 24 is the Standard for the Installation of Private Fire Service Mains and Their Appurtenances; it covers the pipe, valves, hydrants, and testing of the yard main from the water supply to the base of the riser. NFPA 13 addresses sprinkler system design and installation above that point, while NFPA 25 governs in-service inspection, testing, and maintenance. NFPA 291 is a recommended practice for fire flow testing and marking of hydrants.
Question 27Codes, Standards, and Reference Documents
Which NFPA document governs the care, use, inspection, and service testing of fire hose after it has been placed in service?
- NFPA 1963
- NFPA 1901
- NFPA 1962 Correct answer.
- NFPA 1961
Explanation
NFPA 1962 is the standard for the care, use, inspection, service testing, and replacement of fire hose, including the periodic service tests performed on hose in the field. NFPA 1961 sets product requirements for new fire hose, NFPA 1963 fixes coupling screw threads, and NFPA 1901 covers automotive fire apparatus.
Question 28Codes, Standards, and Reference Documents
Under NFPA 25, how often must the gauges on a wet pipe sprinkler system be inspected to verify that normal water supply pressure is being maintained?
- Annually
- Monthly Correct answer.
- Weekly
- Quarterly
Explanation
The NFPA 25 inspection table for wet pipe systems calls for a monthly reading of the system gauges so that the normal water supply pressure can be confirmed and any unexplained drop investigated. Weekly and quarterly readings are not the baseline requirement, and an annual reading would leave a pressure loss undetected for too long.
Question 29Codes, Standards, and Reference Documents
A developer proposes protecting a residential building five stories in height with a sprinkler system designed to NFPA 13R. Which standard is the correct reference for this system?
- NFPA 13R, because the residential height limit does not apply to new construction
- NFPA 14, because any building exceeding four stories requires a standpipe system
- NFPA 13, because NFPA 13R is limited to four stories or fewer Correct answer.
- NFPA 13D, because the building contains dwelling units and sleeping rooms
Explanation
NFPA 13R applies only to residential occupancies up to and including four stories in height above grade, so a five-story building falls outside its scope and the system must meet NFPA 13. NFPA 13D is restricted to one- and two-family dwellings and manufactured homes, and NFPA 14 governs standpipe and hose systems rather than sprinkler design.
Question 30Safety and Jobsite Practices
On a roadway jobsite during daylight, what is the main purpose of wearing high-visibility apparel?
- To keep the worker warm during cold weather shifts
- To make the worker easier for drivers to notice Correct answer.
- To identify the worker's trade certification level
- To protect the worker from electrical contact hazards
Explanation
High-visibility apparel improves conspicuity so drivers and equipment operators can notice workers sooner. Its main purpose is visibility, not electrical protection, warmth, or job identification.
Question 31Safety and Jobsite Practices
When must a hard hat be worn on a construction jobsite?
- Where head injury from falling objects is possible Correct answer.
- Whenever the temperature drops below freezing
- Only while the worker is operating heavy equipment
- Only while visitors are being escorted on site
Explanation
Hard hats protect against head injury from falling or flying objects and from bumps. They are required wherever those hazards exist, not only during specific tasks or weather.
Question 32Safety and Jobsite Practices
Which glove type is most appropriate for handling sharp sheet metal by hand?
- Disposable latex exam gloves
- Cotton garden gloves
- Cut-resistant work gloves Correct answer.
- Rubber insulating gloves
Explanation
Cut-resistant gloves are designed to protect hands from sharp edges such as sheet metal. Other glove types may protect against chemicals, electricity, or contamination but not cuts.
Question 33Safety and Jobsite Practices
Which practice best reduces slip and trip hazards in a work area?
- Running extension cords across busy main walkways
- Leaving tools and cords in walkways so they are easy to find
- Cleaning spills promptly and keeping walkways clear Correct answer.
- Stacking materials beside exits for quick removal
Explanation
Good housekeeping removes slip and trip hazards by keeping walkways clear and cleaning spills promptly. Leaving tools, cords, or materials in paths increases the chance of falls.
Question 34Safety and Jobsite Practices
If the scene is safe, what should you do first for a coworker who has collapsed and is not moving?
- Give the coworker water to drink
- Check whether the coworker responds and is breathing Correct answer.
- Wait several minutes to see whether the coworker recovers
- Move the coworker to a vehicle
Explanation
After confirming the scene is safe, check responsiveness and breathing so you can decide what emergency care is needed. Do not give food or drink to an unresponsive person or move them unnecessarily.
Question 35Safety and Jobsite Practices
Why should a near miss on a jobsite be reported?
- Because it replaces the need for all daily site inspections
- Because it is only required after property damage
- Because it can reveal a hazard before an injury occurs Correct answer.
- Because it guarantees the worker will be disciplined
Explanation
A near miss shows that a hazard exists without yet causing injury, so reporting it allows controls to be put in place. It is not a disciplinary tool and does not replace inspections.
Question 36Safety and Jobsite Practices
What eye protection is appropriate when using a hand tool that can throw flying chips?
- Sunglasses with tinted lenses
- Prescription eyeglasses without side shields
- Safety glasses with side shields Correct answer.
- No eye protection if the task is brief
Explanation
Safety glasses with side shields protect the eyes from flying chips that can enter from the front or side. Regular prescription glasses and sunglasses generally do not meet impact protection requirements.
Question 37Safety and Jobsite Practices
Before attempting to use a portable fire extinguisher, what should a worker confirm?
- That the fire is spreading quickly
- That the fire is small and an exit is available Correct answer.
- That smoke has filled the area
- That the extinguisher is the largest model available on site
Explanation
Use an extinguisher only on a small, incipient fire and only when a clear escape route is available. If the fire is large, spreading, or producing heavy smoke, evacuate and call emergency responders.
Question 38Safety and Jobsite Practices
Before closing a lane on a public road, what should be done first?
- Place the work vehicles in the closed lane
- Begin work first and add cones only as traffic approaches
- Notify only the workers on the crew
- Set up traffic control according to an approved plan Correct answer.
Explanation
Lane closures must be set up according to an approved temporary traffic control plan before work begins. This gives drivers advance warning and separates them from the work area.
Question 39Safety and Jobsite Practices
Where should a flagger normally stand while controlling traffic?
- In the center of the active travel lane beside moving traffic
- On the shoulder where visible and with an escape path Correct answer.
- Inside the closed work area
- Behind the work vehicle
Explanation
A flagger should stand on the shoulder in a visible location with a planned escape path. Standing in the travel lane or behind equipment reduces visibility and escape options.
Question 40Safety and Jobsite Practices
What is the main purpose of buffer space in a temporary traffic control zone?
- To mark the exact beginning and end limits of the work
- To provide parking for inspectors
- To store materials and equipment
- To shield workers and allow driver recovery Correct answer.
Explanation
Buffer space separates traffic from the work area and gives an errant driver room to stop or recover. It is not storage, parking, or a work-limit marker.
Question 41Safety and Jobsite Practices
What mainly determines the spacing of channelizing devices along a taper?
- The color of the devices
- The number of workers on the crew
- The size of the work vehicles
- The posted speed limit Correct answer.
Explanation
Channelizing device spacing in a taper is based mainly on the posted speed limit and the resulting taper length. Higher speeds require longer tapers and different spacing.
Question 42Safety and Jobsite Practices
Before excavating for a new conduit, what is a required first step?
- Start digging carefully by hand
- Ask a coworker to watch for utility lines
- Call the utility locate service and wait for markings Correct answer.
- Assume no utilities exist if the ground surface looks clear
Explanation
Calling the utility locate service before digging allows underground utilities to be marked so the excavation can avoid them. Hand digging may still be required near marked lines, but it is not the first step.
Question 43Safety and Jobsite Practices
What is the purpose of lockout/tagout procedures?
- To mark equipment that is ready for use
- To record employee attendance
- To prevent unexpected release of hazardous energy Correct answer.
- To secure all hand tools at the end of each work shift
Explanation
Lockout/tagout controls hazardous energy so equipment cannot be started or release stored energy unexpectedly during service. It is not a tool-storage or attendance procedure.
Question 44Safety and Jobsite Practices
When using an extension ladder, how far should the base be from the wall for every 4 feet of height?
- 1 foot Correct answer.
- 3 feet
- 4 feet
- 2 feet
Explanation
The 4-to-1 rule places the ladder base 1 foot from the wall for every 4 feet of working height. This gives a stable climbing angle.
Question 45Safety and Jobsite Practices
What serious hazard can result from running a gasoline generator inside a closed work trailer?
- Damage to the generator from cold air
- Excessive noise exposure only
- Carbon monoxide poisoning Correct answer.
- Electrical shock from the generator frame
Explanation
Gasoline generators produce carbon monoxide, an odorless gas that can accumulate in enclosed spaces and cause poisoning. Generators should be run outdoors away from openings.
Question 46Safety and Jobsite Practices
Which technique is recommended when lifting a heavy box by hand?
- Twist the torso while lifting
- Keep the load close and lift with the legs Correct answer.
- Lift quickly to reduce strain
- Bend at the waist and keep both arms fully extended
Explanation
Keeping the load close and lifting with the legs reduces strain on the back. Bending at the waist, twisting, or lifting quickly increases injury risk.
Question 47Safety and Jobsite Practices
At what depth does an excavation normally require a protective system unless made in stable rock?
- 5 feet Correct answer.
- 15 feet
- 10 feet
- 2 feet
Explanation
OSHA generally requires a protective system for excavations 5 feet deep or more unless the excavation is made entirely in stable rock. Shallower excavations may also require protection if hazards are present.
Question 48Safety and Jobsite Practices
Before entering a permit-required confined space, what must be done?
- Open the hatch and enter quickly
- Use a flashlight as the only safety precaution before entry
- Ask another worker to check later
- Test the atmosphere and follow the entry permit Correct answer.
Explanation
Permit-required confined-space entry requires atmospheric testing, hazard control, an entry permit, and attendant monitoring as specified. Entering quickly or relying on a flashlight is unsafe.
Question 49Safety and Jobsite Practices
Which sign suggests a heat emergency rather than simple heat exhaustion?
- Muscle cramps that occur after finishing work
- Heavy sweating and thirst
- Confusion or altered mental status Correct answer.
- Cool, moist skin
Explanation
Altered mental status, confusion, or loss of consciousness suggests heat stroke, a life-threatening emergency requiring immediate cooling and emergency medical care. Heat exhaustion usually involves heavy sweating, weakness, and thirst without confusion.
Question 50Safety and Jobsite Practices
What is the primary function of positive protection such as temporary concrete barriers in a work zone?
- To physically prevent vehicles from entering the work area Correct answer.
- To replace all warning signs
- To guide pedestrians safely along the sidewalk beside the work area
- To reduce noise from construction equipment
Explanation
Positive protection physically separates traffic from the work area, such as with temporary concrete barriers. It is intended to stop or redirect errant vehicles before they reach workers.