NM Asbestos Abatement: Asbestos Abatement Licensing and Certification

NM Asbestos Abatement · Work through your exam, one topic at a time.

All guide sections

Asbestos Abatement Licensing and Certification

This domain tests how New Mexico regulates the people and businesses that perform asbestos abatement. The Environment Department's Asbestos Control Program administers firm licensing and individual certification under 20.11.64 NMAC, and exam questions usually turn on which credential applies, when it must be valid, and what must happen before work starts.

License versus certification

A license is issued to a business entity and authorizes the firm to contract for abatement. Certification is issued to a person after training and examination, and authorizes that individual to work in a defined category such as abatement worker or supervisor. A licensed firm must have a certified supervisor directing the project; a certified worker cannot substitute for the firm's license, and a firm cannot "borrow" another company's license.

Application and renewal

Applicants submit the program's form, fee, training documentation, and examination results. Certifications and licenses carry expiration dates; renewal is not automatic, and late renewal may require reapplication or retraining. Work performed while a credential is expired is treated as unlicensed activity, exposing the firm to penalties and stop-work orders.

Notification is separate

Before regulated abatement, the firm files a project notification with the program, generally at least 10 working days before start. Notification is not an approval or permit; it is a filing that must be accurate. Changed start dates or scope require an amended notification.

Worked example

A firm plans to start Monday, April 7, and mails notification on Friday, March 28. Counting back ten working days, excluding weekends and state holidays, gives Monday, March 24 as the latest acceptable filing date. The March 28 mailing is late, so the start must move to a date at least ten working days after receipt. The firm also confirms its license and the supervisor's certification are valid through the entire project, not just the start date.

Traps

  • Treating a training certificate as a state certification.
  • Assuming notification equals permission.
  • Letting a certification lapse mid-project.
  • Using an uncertified supervisor because the licensed owner is on site.