- NFPA 72 scope
- Defines the application, installation, location, performance, inspection, testing, and maintenance of fire detection and alarm systems, including initiating devices, notification appliances, and supervising station systems.
- Protected premises system
- A local fire alarm system that sounds notification appliances within the protected building only, with no automatic transmission of signals to an off-premises location.
- Central station system
- A system that transmits signals to a listed, privately operated supervising station that is staffed continuously and provides runner service under a contract with the subscriber.
- Addressable system
- A fire alarm system in which each initiating device and notification appliance has a unique address, allowing the control unit to identify the specific device in alarm or trouble.
- Spot smoke detector spacing
- On smooth ceilings, spot-type smoke detectors are spaced at their listed spacing (commonly 30 ft) and no point on the ceiling may be more than 21 ft from a detector.
- Ionization vs photoelectric
- Ionization detectors respond faster to flaming fires with small particles; photoelectric detectors respond faster to smoldering fires with larger particles. Combination units use both technologies.
- Duct smoke detector application
- Required where air handling systems exceed 2,000 cfm; used to supervise duct airflow and initiate equipment shutdown, not as a substitute for area smoke detection.
- Pull station mounting height
- Manual fire alarm pull stations must be mounted 42 to 48 inches above the finished floor, within 5 feet of the exit door, on the latch side of the door.
- NAC audibility requirement
- Public mode audible signals must be at least 15 dBA above ambient or 5 dBA above maximum ambient lasting over 60 seconds, measured at 60 inches above the floor.
- Visible appliance synchronization
- Visible notification appliances in the same viewing area must flash in synchronization to avoid triggering seizures; spacing follows candela rating and mounting height tables.
- Secondary power capacity
- Commercial fire alarm systems require 24 hours of standby followed by 5 minutes of alarm operation; central station systems require 24 hours plus 5 minutes.
- Battery sizing formula
- Required capacity equals standby current times standby hours plus alarm current times alarm hours, multiplied by a 1.20 derating factor to select the battery rating.
- Class A versus Class B
- Class A circuits return to the panel so a single open fault disables no devices; Class B circuits are two-wire with a single path where one open disables devices beyond the break.
- Notification voltage drop
- Voltage drop equals two times the one-way length times current times resistance per 1,000 ft; the drop must leave at least the minimum operating voltage at the last appliance.
- Dedicated branch circuit
- The fire alarm primary power source must be a dedicated branch circuit connected ahead of other loads, with a red, marked disconnecting means protected from accidental operation.
- Article 760 coverage
- NEC Article 760 covers fire alarm system wiring, including non-power-limited circuits in 760.41 and power-limited circuits in 760.121, plus cable types and separation rules.
- FPL cable types
- FPL is general-purpose fire alarm cable, FPLR is riser-rated for vertical shafts, and FPLP is plenum-rated for environmental air spaces; selection depends on installation location.
- NPLFA conductor minimum
- Non-power-limited fire alarm circuit conductors must be at least 14 AWG copper or 12 AWG aluminum and installed in raceway or a listed cable assembly.
- Fire alarm circuit separation
- Fire alarm conductors may not share raceway, cable, or boxes with other systems unless separated by a barrier or permitted by 760.139 and 300.8.
- Record of completion
- A document signed by the installing contractor and owner's representative confirming the system was installed and tested per the design and NFPA 72 requirements.
- Annual detector testing
- Smoke detectors and duct detectors must be tested annually, with duct detectors tested while the air handling system is operating to verify airflow and shutdown.
- Battery load test
- Batteries must be load tested at the calculated alarm load, or discharged for 30 minutes annually, and replaced when capacity falls below 80 percent of rating.
- Impairment procedure
- When a required system is out of service more than 4 hours, the AHJ, owner, and monitoring agency must be notified and a fire watch implemented.
- Trouble signal timing
- Trouble signals must be distinctive and must annunciate within 200 seconds of the fault; supervisory signals must annunciate within 90 seconds.
- Signal priority
- Alarm signals take priority over supervisory and trouble signals; a subsequent alarm on another zone must still be annunciated even when a prior alarm is active.
- DACT transmission
- Digital alarm communicator transmitters must use two separate telephone lines or one line plus an alternate path, and the panel must detect line faults and switch paths.
- Central station retransmission
- Alarm signals must be transmitted within 90 seconds of activation, and the central station must retransmit to the fire department within 90 seconds of receipt.
- Elevator recall phases
- Smoke detectors in lobbies, machine rooms, and hoistways initiate Phase I recall; a detector in the elevator pit or car initiates Phase II recall.
- Sprinkler interface signals
- Waterflow switches must initiate an alarm signal and valve tamper switches must initiate a supervisory signal; both are monitored by the fire alarm control unit.
- HVAC shutdown interface
- Duct smoke detectors must shut down the air handling unit upon alarm and be supervised for power and airflow, without disabling the fire alarm system.
- High-rise fire alarm
- Buildings generally over 75 feet require a fire alarm system with voice evacuation, elevator recall, and sprinkler monitoring, capable of manual and automatic operation.
- New Mexico contractor license
- The Construction Industries Division requires a Fire Protection Systems Contractor license to bid, contract, or install fire alarm systems in New Mexico.