NM Landscape study materials
NM Landscape study resources

NM Landscape flashcards

NM Landscape · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

ALTA/NSPS survey
A boundary and title survey standard that defines minimum accuracy and shows easements, utilities, improvements, and encumbrances; commonly required for real estate and development transactions.
Contour interval
The vertical distance between adjacent contour lines; selected so no more than about five to ten contours cross a feature, often one or two feet for site design.
Critical root zone
The soil area around a tree that contains roots essential for stability and uptake; a common rule is one foot of radius per inch of trunk diameter at breast height.
Hydrologic soil group
An NRCS classification from A to D describing infiltration capacity; group A sands infiltrate rapidly, while group D clays produce the most runoff.
Solar altitude
The angle of the sun above the horizon; summer solstice altitude equals 90 degrees minus latitude plus 23.4 degrees, and winter solstice subtracts 23.4 degrees.
Wind rose
A graphic showing wind frequency and speed by compass direction; used to place shelterbelts, orient outdoor spaces, and plan natural ventilation.
Overlay mapping
A site analysis method that stacks constraint layers such as slopes, soils, floodplains, and utilities; a weighted suitability score is the sum of weight times rating.
Adjacency matrix
A grid that scores the desired proximity or separation between program elements; results inform bubble diagrams and block plans.
Critical path
The longest chain of dependent activities in a schedule; it sets the minimum project duration and its activities have zero total float.
Total float
The amount of time an activity can slip without delaying project completion; calculated as late start minus early start or late finish minus early finish.
Design-build
A delivery method in which one entity holds a single contract for both design and construction, allowing overlap and faster delivery but less owner control.
Accessible route slope
Under ADA standards, running slope must not exceed 1:20 (5 percent) and cross slope must not exceed 1:48 (2.08 percent), with a clear width of at least 36 inches.
Sight triangle
A triangular area at driveways and intersections kept clear of walls, vegetation, and signs so drivers can see approaching traffic; leg length depends on approach speed.
Floor area ratio
Gross floor area divided by lot area, used in zoning to regulate building bulk and density independently of lot coverage.
CPTED
Crime Prevention Through Environmental Design; a set of principles including natural surveillance, access control, territorial reinforcement, and maintenance to reduce opportunities for crime.
Planting layer
A design technique using canopy, understory, shrub, and groundcover strata to create depth, habitat, and visual interest while matching plants to site conditions.
MasterFormat
A CSI standard that organizes construction work into numbered divisions and sections; it structures specifications and is often used for cost codes.
Three-part specification
A specification section format with Part 1 General, Part 2 Products, and Part 3 Execution; it separates administrative requirements, materials, and installation procedures.
Addendum
A written modification to bidding documents issued before bid opening; it becomes part of the contract documents and must be acknowledged by bidders.
RFI
A request for information submitted by the contractor during construction; the designer's written response clarifies documents but does not change the contract unless a change order follows.
Substantial completion
The stage when work is sufficiently complete for the owner's intended use; it triggers warranties, the punch list, and often a reduction in retainage.
Record drawings
Drawings revised to show actual constructed conditions, based on contractor markup and field observation; they document the project for future maintenance and renovations.
Contour line
A line on a plan connecting points of equal elevation; close spacing indicates steep slopes, and V shapes point upstream along drainageways.
Spot elevation
A point elevation noted on a grading plan at critical locations such as inlets, building entrances, and corners to control drainage and construction.
Cut and fill
Earthwork calculation comparing excavated volume to placed fill; balancing the two minimizes haul, with shrinkage and swell factors adjusting volumes.
Building pad slope
Finished grade should slope at least 2 percent away from foundations for roughly 6 to 10 feet; walks should not exceed 5 percent.
Swale longitudinal slope
The grade along a drainage swale, typically 1 to 5 percent; steeper grades require check dams, riprap, or other erosion protection.
Rational method
A peak runoff formula, Q = CiA, where Q is cubic feet per second, C is the runoff coefficient, i is rainfall intensity in inches per hour, and A is area in acres.
Time of concentration
The travel time for runoff from the hydraulically most distant point to the outlet; it selects the rainfall intensity from an intensity-duration-frequency curve.
Curve number
An NRCS TR-55 parameter from 0 to 100 based on land use and hydrologic soil group; higher values indicate greater runoff potential.
Detention basin
A facility that temporarily stores stormwater and releases it at a controlled rate; a retention basin holds water permanently through infiltration or evaporation.
Manning equation
An open-channel flow formula, Q = (1.486/n) A R^(2/3) S^(1/2), where n is roughness, A is area, R is hydraulic radius, and S is slope.