Inventory, Analysis, and Project Management
What this domain tests
The Inventory, Analysis, and Project Management domain covers how you assemble reliable site data, turn it into defensible analysis, and run a landscape architecture project on scope, schedule, and budget. Expect questions on base-map sources, site constraints, slope and suitability mapping, work breakdown structures, critical-path scheduling, and earned-value tracking.
Inventory
- An ALTA/NSPS land title survey is the boundary and easement base; USGS 7.5-minute quadrangles are 1:24,000 (about 1 in = 2,000 ft) and are regional context, not design-grade.
- Pull zoning, setbacks, easements, utilities, FEMA flood zones, NWI wetlands, NRCS soils, vegetation, views, noise, and solar/wind data. Wetland jurisdictional boundaries are confirmed by the USACE; cultural resources trigger Section 106 review.
Analysis
- Convert inventory into opportunities and constraints. Slope classes are commonly 0–3% (easily developed), 3–8% (graded), 8–15% (terraced/retaining), and over 15% (severe constraint).
- Overlay maps and a weighted suitability matrix make the recommendation traceable; watershed and viewshed delineation turn topography into design evidence.
Project management
- Decompose scope with a WBS, sequence with a Gantt or CPM network, and manage the critical path where float equals zero. Fast-tracking overlaps design and construction; crashing adds resources.
- Earned value: CPI = EV/AC and SPI = EV/PV; a CPI below 1.0 means over budget.
Worked example
A site falls from elevation 108 ft to 96 ft over a 300-ft run. Average slope = (108 − 96) / 300 × 100 = 4.0%. A proposed accessible route at that grade is under the 5% running-slope limit, but the designer must still check cross slope (2% max) and landings. If the same plan is printed at 1:2,400 and a boundary measures 62 mm, ground distance = 62 mm × 2,400 = 148,800 mm = 148.8 m.
Traps
- Treating GIS or a USGS quadrangle as a boundary survey.
- Reading a PDF at 100% after it has been rescaled.
- Calling the longest-duration activity the critical path when float, not duration, defines it.