GM and Free Surface on a Timber-Laden Coaster

Norway Deck Officer Class 5 · Put your knowledge to work in context.

All case studies

GM and Free Surface on a Timber-Laden Coaster

M/V Fjordlast, 3,200 GT, is completing loading sawn timber in Kristiansund for a UK port. From the loading computer: displacement 4,600 t, KM 6.80 m, KG 6.35 m (solid), giving GM 0.45 m. For trimming, No. 2 double-bottom tank (12 m long × 7 m wide × 1.6 m deep) is 60% full of ballast and No. 3 (same dimensions) is 45% full; neither tank has wash bulkheads. The deck cargo is 380 t of timber, stowed 2.2 m high, with lashings and uprights checked. The forecast for the passage is SW 8–9 with 6 m seas. The load line is not exceeded, the ship floats at her marks, but she has a 3° list to starboard. Ballast density is 1.025 t/m³.

1. Calculate the free surface correction and the fluid GM, and assess the condition against the IS Code 2008 intact stability criteria.

Read the worked answer

Free surface correction.

  • Transverse moment of inertia of one tank: i = l·b³/12 = 12 × 7³/12 = 343 m⁴.
  • Free surface moment per tank: FSM = ρ·i = 1.025 × 343 = 351.6 t·m. Two slack tanks: 703.2 t·m.
  • FSC = ΣFSM/Δ = 703.2 / 4,600 = 0.153 m.
  • Fluid GM = 0.45 − 0.15 = 0.30 m.

Assessment. The IS Code 2008 minimum initial GM of 0.15 m is met, but only just - the criterion is a floor, not a safe target. With 380 t of timber 2.2 m high on deck the GZ curve will be flat: maximum GZ will be small and will occur at a large angle, and the area criteria (0.055 m·rad to 30°, 0.09 m·rad to 40°, 0.03 m·rad between 30° and 40°) must be checked on the loading computer's GZ curve for this exact condition, with free surface included. Timber absorbs water and, in a Norwegian November, ice can accrete on the stow, both raising KG. A 0.30 m fluid GM leaves no margin for that, so the condition should be treated as unacceptable for the forecast.

2. Explain how you would remove the 3° starboard list with the least additional free surface, and what you would check after each step.

Read the worked answer

Correcting the list.

  • The 3° list is a transverse weight moment, not a stability failure by itself, but with GM 0.30 m it takes very little to produce it.
  • Do not fill a starboard (low-side) tank to correct a starboard list; that increases it and adds free surface.
  • Fill one port-side double-bottom tank completely - No. 2 port first, being nearer the centre of flotation and adding least trim - then recheck the list on the inclinometer and the loading computer.
  • If still listed, fill No. 3 port in stages, but press each tank up to the top (or empty it completely). The two slack tanks were the source of the 0.153 m FSC; the aim is to finish with no slack tanks except one small tank used for fine adjustment.
  • After each step check: fluid GM, list, trim, draughts and freeboard, load line, and the GZ curve. Record soundings.
  • Watch the overflow and tank vents, and never press up a tank without checking the air pipe and high-level alarm. Correcting list by ballast takes time; do it alongside, not after departure.

3. The forecast is SW 8–9. State your decision on sailing and the measures you would require before departure.

Read the worked answer

Decision: do not sail as loaded into SW 8–9. Before departure I would require:

  1. All double-bottom tanks either full or empty, so the FSC is reduced to near zero, and the loading computer re-run with the final condition.
  2. The GZ curve verified against all IS Code 2008 criteria, including water absorbed by the timber and a realistic ice allowance for the season.
  3. If the GZ curve still fails or is marginal, either reduce or lower the deck cargo or add low ballast to raise GM - checking that the load line, freeboard and timber load line (if applicable) are still satisfied and that the extra draught still gives adequate UKC for the passage.
  4. Cargo securing checked against the CSS Code and timber deck cargo provisions: compact stow, uprights, lashings, no interference with freeing ports or crew access.
  5. The company informed of the delay and the reason. The master's authority on seaworthiness is not overridden by the sailing schedule.