NV Journeyman Plumber study materials
NV Journeyman Plumber study resources

NV Journeyman Plumber study plan

NV Journeyman Plumber · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Sanitary Drainage, Vents, and Storm Drainage & Plumbing Terminology, Definitions, and Code Administration

  • Define the terms slope, fall, crown, invert, grade, developed length, and fixture unit, and state where each appears in a drainage design calculation.

  • Compute pipe slope from rise and run in both percent and inches per foot, and convert between the two for at least ten practice pairs.

  • Identify the maximum allowable trap-to-vent distance and the horizontal drain slope requirements by pipe size, and record them in a one-page reference sheet.

  • Trace a soil stack from fixture to building drain and label every fitting, cleanout, and transition on a hand sketch.

Your checkpoint

A single-page slope and terminology reference sheet plus ten solved slope-conversion problems with work shown.

Week 2

Sanitary Drainage, Vents, and Storm Drainage & Traps, Interceptors, and Special Wastes

  • Size a horizontal branch and a building drain using fixture units, and justify each step of the table lookup.

  • Explain the difference between a trap arm, a vent stack, a stack vent, and a yoke vent, and sketch where each is permitted.

  • Determine vent sizing for a given stack and fixture load, and identify at least three prohibited vent configurations.

  • Compare the trap seal requirements, vent distance limits, and prohibited trap types for sinks, floor drains, and lavatories.

Your checkpoint

A completed drainage and vent sizing worksheet for a two-bathroom, one-kitchen dwelling, with every fixture unit count and vent size annotated.

Week 3

Water Supply and Distribution Systems & Potable Water Protection, Backflow, and Cross-Connection Control

  • Size water service and distribution piping from fixture units and pressure loss, and state the assumed residual pressure at each step.

  • Calculate developed length including fittings and elevation, and explain how each affects pipe sizing.

  • Identify the conditions that create a cross-connection and list at least five backflow prevention assemblies or devices with their approved applications.

  • Explain the difference between backpressure and backsiphonage, and select the correct protection for each of five described scenarios.

  • Describe the required testing and inspection intervals for a reduced-pressure principle assembly.

Your checkpoint

A water sizing calculation for one dwelling plus a five-scenario backflow selection table naming the device and the reason for the choice.

Week 4

Fixtures, Fixture Fittings, and Water Heaters & Water Supply and Distribution Systems

  • State the clearance, relief valve, and drain pan requirements for a residential water heater and explain the consequence of each omission.

  • Match fixture types to their minimum trap size, water supply requirements, and required clearances.

  • Explain thermal expansion, temperature and pressure relief discharge termination, and the approved piping material for the relief line.

  • Verify water heater venting and combustion air requirements against the installation instructions for one common appliance type.

Your checkpoint

A water heater installation checklist covering clearances, relief valve, discharge termination, pan, and venting, with a short written justification for each line.

Week 5

Gas Piping and Fuel Gas Systems & General Regulations, Permits, and Inspections

  • Size a natural gas branch line from appliance input ratings and length, and state the assumed pressure drop and specific gravity.

  • Explain the bonding, clearance, and prohibited location requirements for gas piping, and identify at least four prohibited installations.

  • Describe the sequence of a rough-in inspection and a final inspection, and list what an inspector typically verifies at each stage.

  • Identify when a permit is required and when it is not, and describe the consequences of working without one.

Your checkpoint

A gas pipe sizing table for a three-appliance dwelling plus a written permit-and-inspection timeline for a sample remodel.

Week 6

Nevada Plumbing Statutes, Regulations, and Licensing & Safety, Tools, and Jobsite Practices

  • Summarize the licensing structure for plumbers in Nevada, including the classifications, renewal cycle, and continuing education obligation, and cite the governing authority for each.

  • Explain the role of the state contractors board versus the local jurisdiction for permits and inspections in a Nevada project.

  • List the required safety practices for confined space entry, trenching and shoring, and soldering or brazing with open flame.

  • Select the correct tool and safety precaution for five described field tasks, and state one common misuse for each.

Your checkpoint

A two-part study card set: Nevada licensing and regulatory facts on one side, jobsite safety rules on the other, each fact with its source noted.

Week 7

Isometric Drawings, Plans, and Material Takeoffs & Traps, Interceptors, and Special Wastes

  • Read a plumbing isometric and identify the drainage, vent, and water lines by symbol and line weight.

  • Convert an isometric into a material takeoff listing pipe, fittings, and fixtures with quantities and sizes.

  • Describe the purpose and sizing approach for grease interceptors, sand traps, and oil separators, and identify which wastes require each.

  • Explain the venting and cleaning requirements for interceptors and the restrictions on discharging special wastes to the sanitary system.

Your checkpoint

A material takeoff from a provided isometric, with a quantity list and a one-paragraph explanation of how fittings and waste were counted.

Week 8

Plumbing Terminology, Definitions, and Code Administration & General Regulations, Permits, and Inspections & Fixtures, Fixture Fittings, and Water Heaters & Water Supply and Distribution Systems & Sanitary Drainage, Vents, and Storm Drainage & Traps, Interceptors, and Special Wastes & Gas Piping and Fuel Gas Systems & Potable Water Protection, Backflow, and Cross-Connection Control & Isometric Drawings, Plans, and Material Takeoffs & Safety, Tools, and Jobsite Practices & Nevada Plumbing Statutes, Regulations, and Licensing

  • Complete a full-length timed practice exam under exam conditions and score it by domain.

  • Review every missed question and write the governing rule or calculation in your own words.

  • Re-drill the two lowest-scoring domains until each reaches your target accuracy.

  • Recite the key code thresholds, clearances, and licensing facts from memory without notes.

Your checkpoint

A scored practice exam with a domain-by-domain error log and a written remediation note for every missed item.

Milestones

Week 2: Score at least 75 percent on a 20-question drainage and vent quiz, and correctly size a building drain from fixture units without reference to a worked example.

Week 4: Score at least 75 percent on a 25-question mixed quiz covering water supply, fixtures, and backflow, and correctly select the backflow device for four of five scenarios.

Week 6: Score at least 80 percent on a 30-question mixed quiz across the first eight domains, and state the Nevada licensing and permit facts from memory with no more than two errors.

Week 8: Score at least 80 percent overall on the full-length timed practice exam with no single domain below 70 percent.