OK Plumber study materials
OK Plumber study resources

OK Plumber cheat sheet

OK Plumber · Keep the key ideas within reach.

Quick reference

Plumbing Code, Rules, and Licensing Requirements

  • Oklahoma issues apprentice, journeyman, and master plumber credentials through the Construction Industries Board; plumbing contracting must be performed by or under a licensed plumbing contractor.

  • The Oklahoma Uniform Plumbing Code is the statewide adopted code built on the International Plumbing Code; local amendments may be stricter, but not weaker, than the state minimum.

  • A permit is required before work starts: rough-in inspection happens before piping is covered, and final inspection happens after fixtures and appliances are set and tested.

  • The authority having jurisdiction (code official) may approve alternate materials and methods, require tests, and issue written interpretations that control on the job.

  • Developed length is the pipe length measured along the centerline plus the equivalent length of fittings and valves, and it drives both drain and water pipe sizing.

  • A drainage fixture unit (DFU) is a load value assigned by fixture type; a water closet is typically 3 DFU and a lavatory 1 DFU.

  • All pipe, fittings, and fixtures must be listed and marked to a recognized standard (ASTM, NSF, CSA); unlisted or unmarked material cannot be installed.

  • Work without a required permit or license is subject to stop-work orders, fines, and discipline of the credential.

Quick reference

Water Supply and Distribution

  • Static pressure at fixtures must not exceed 80 psi; where the building supply is higher, a pressure-reducing valve is required.

  • Water service pipe is buried at least 12 inches below grade and below local frost depth, and must be protected from freezing and mechanical damage.

  • Water distribution piping is tested with water at working pressure before concealment and must hold with no visible leaks.

  • Water hammer arrestors, listed to a recognized standard, are required at quick-closing valves such as those serving dishwashers, washing machines, and flush valves.

  • A water heater temperature and pressure relief valve is set at 210 degrees F / 150 psi maximum and discharges full size, by gravity, unthreaded, ending not more than 6 inches above the floor or outside the building.

  • Where a check valve, pressure-reducing valve, or backflow preventer creates a closed system, thermal expansion control such as an expansion tank is required.

  • An air gap provides the highest degree of backflow protection; hose bibbs and sillcocks need an approved vacuum breaker.

  • Size water piping from water supply fixture units, developed length, and available pressure; design velocities are commonly held near 8 fps cold and 5 fps hot to limit noise and erosion.

Quick reference

Sanitary Drainage, Waste, and Venting

  • Trap seal depth must be at least 2 inches and not more than 4 inches.

  • The developed length from the fixture outlet to the trap weir may not exceed 24 inches vertically or 30 inches horizontally.

  • Building drain slope: 1/4 inch per foot for pipe 2-1/2 inches and smaller, and 1/8 inch per foot for 3-inch and larger pipe.

  • Cleanouts are required at the base of each stack, at the building sewer, at changes of direction greater than 45 degrees, and at each 100 feet of aggregate horizontal run.

  • A vent must be at least 1-1/4 inches in diameter and not smaller than one-half the diameter of the drain it serves.

  • A vent stack terminates outdoors at least 6 inches above the roof surface and at least 10 feet horizontally from any lot line.

  • Each fixture gets its own trap: double trapping, S-traps, and unvented trap arms are prohibited.

  • PVC DWV pipe is supported horizontally at intervals not exceeding 4 feet, and vertical stacks are supported at the base and at each story.

Quick reference

Fixtures, Fixture Fittings, and Appliance Connections

  • Water closets must not exceed 1.6 gallons per flush and urinals must not exceed 1.0 gallon per flush; fixtures must be listed to those volumes.

  • Faucet flow limits: lavatory and kitchen faucets 2.2 gpm at 60 psi; showerheads 2.5 gpm at 80 psi.

  • A clothes washer standpipe is at least 2 inches in diameter and terminates between 18 and 42 inches above the trap weir.

  • Dishwasher discharge connects upstream of the trap through an air gap or high loop to prevent backflow into the appliance.

  • Floor drains require a trap, and seldom-used floor drains require an automatic trap primer to maintain the seal.

  • An air gap is the unobstructed vertical distance between the supply outlet and the flood level rim, and must be at least twice the effective opening of the outlet.

  • Fixtures must be accessible, level, securely fastened, and sealed watertight to the drain with an approved gasket or sealant.

  • A water heater needs a T&P valve, a drain pan where leakage would cause damage, and a drain line run to an approved location.

Quick reference

Fuel Gas Piping

  • Approved gas materials include schedule 40 black steel, listed copper, listed corrugated stainless steel tubing (CSST), and listed plastic; all must be marked and listed.

  • Gas pipe is sized from the total connected Btu/h load and the longest run length using the code sizing tables.

  • A listed manual shutoff valve is installed ahead of each appliance, with a sediment trap (dirt leg) downstream of the shutoff.

  • Flexible appliance connectors are limited to 6 feet, may not be concealed, and only one connector may serve each appliance.

  • Support intervals for horizontal steel gas piping: 1/2 inch at 6 feet, 3/4 inch and 1 inch at 8 feet, larger sizes at 10 feet.

  • Gas piping is prohibited in return-air plenums and elevator shafts; concealed runs avoid unions, and piping through masonry or concrete is sleeved.

  • Gas-fired appliances with an ignition source in a garage must have the ignition source at least 18 inches above the floor unless listed as flammable-vapor ignition resistant.

  • The system is pressure-tested with air or inert gas, gauge visible to the inspector, before gas is turned on; leaks are found with soap solution, never a flame.

Quick reference

Safety, and Job-Site Practices

  • Call 811 before any excavation; Oklahoma One-Call marks buried utilities, and lines near the marks must be exposed by hand digging.

  • Excavations 5 feet deep or more require a protective system (slope, bench, or shore) plus a ladder or ramp within 25 feet of lateral travel.

  • Before entering a confined space, test for oxygen, flammable gas, carbon monoxide, and hydrogen sulfide; ventilate and use an attendant.

  • Hot work such as soldering or brazing requires a fire watch during the work and at least 30 minutes afterward, with an extinguisher on hand.

  • PPE for plumbing work includes eye protection, gloves, hearing protection, and respiratory protection when cutting cast iron or using solvents and fluxes.

  • Gas piping and water piping must never be used as an electrical ground; use GFCI-protected cords on wet job sites.

  • Fall protection is required when working 6 feet or more above a lower level in construction.

  • Relief valve discharge piping must not be capped, trapped, or reduced in size, and must terminate where discharge cannot injure anyone or cause damage.