Well Construction and Compliance

  • Oregon requires a minimum annular seal of 6 inches of neat cement or bentonite from the top of the screen or perforated interval to land surface, or to a depth of at least 18 inches below land surface where a pitless adapter is used.

  • Casing must extend at least 12 inches above finished grade and be firmly anchored; in areas subject to flooding, the top must be at least 24 inches above the 100-year flood level.

  • The annular space must be sealed with a low-permeability grout (neat cement or bentonite) placed by tremie or positive displacement method; free-falling grout is prohibited.

  • Well development must continue until the water is clear and sand-free; minimum development time is typically until turbidity is below 10 NTU or stabilizes.

  • A well must be disinfected with a chlorine solution of at least 50 mg/L for 24 hours, or 100 mg/L for 12 hours, before being placed into service.

  • The wellhead must be capped with a sanitary seal that is watertight and vermin-proof; a vent pipe with a screen is required if the casing is sealed.

  • Abandoned wells must be filled with grout from bottom to top using a tremie pipe; the top 5 feet may be filled with compacted bentonite or concrete.

  • Oregon requires a minimum horizontal distance of 50 feet between a well and a septic tank or sewer line, and 100 feet from a drainfield or livestock enclosure.

Quick reference

Water Rights

  • Oregon water rights are administered by the Oregon Water Resources Department (OWRD) under the prior appropriation doctrine: first in time, first in right.

  • A water right permit authorizes construction and use but does not confer a vested right until a certificate of water right is issued after proof of beneficial use.

  • Beneficial use must be completed within the time specified in the permit (typically 5 years for domestic, 10 years for irrigation) unless an extension is granted.

  • The rate and duty of water are specified in the permit; for irrigation, typical duty is 1/80 cubic foot per second per acre (cfs/acre) in eastern Oregon.

  • Groundwater rights are subject to the same priority system; a junior right may be regulated (shut off) in favor of a senior right during shortages.

  • Exempt uses (e.g., domestic use up to 15,000 gallons per day) do not require a permit but must still be registered and are subject to regulation.

  • A water right certificate confirms the priority date, amount, point of diversion, and place of use; any change requires a transfer application.

  • The public interest review and the “no injury to other water rights” standard apply to all new permits and transfers.

Quick reference

Groundwater and Well Hydraulics

  • Darcy's law: Q = K × i × A, where Q is discharge, K is hydraulic conductivity, i is hydraulic gradient, and A is cross-sectional area.

  • Transmissivity (T) = K × b, where b is saturated thickness; storativity (S) = specific yield + specific retention for unconfined aquifers.

  • The Theis equation: s = (Q / (4πT)) × W(u), where u = (r²S) / (4Tt); used for transient drawdown in confined aquifers.

  • Cooper-Jacob approximation: s = (2.303Q / (4πT)) × log10(2.25Tt / (r²S)), valid for u < 0.01.

  • Specific capacity = pumping rate / drawdown; it decreases with pumping time and indicates well efficiency when compared to theoretical drawdown.

  • Well efficiency = (theoretical drawdown / actual drawdown) × 100%; typical values range from 60% to 80% for properly developed wells.

  • Radius of influence for a confined aquifer can be estimated as R = 3000 × s × √K (empirical), where s is drawdown in feet and K in ft/day.

  • Pumping water level must be measured at least 24 hours after pumping begins and before pumping stops to establish static and dynamic levels.

Quick reference

Regulatory Requirements and Reporting

  • Oregon requires a Water Well Report (OWRD Form WW-1) to be submitted within 30 days of well completion, modification, or abandonment.

  • The report must include: location, depth, diameter, casing material, screen settings, grout type and quantity, static water level, yield test data, and driller's signature.

  • A copy of the well report must be provided to the well owner within 30 days of completion.

  • Well contractors must be licensed by the Oregon Construction Contractors Board (CCB) and hold a Water Well Contractor license from OWRD.

  • All water wells must be constructed by a licensed water well driller or under direct supervision of one; the driller is responsible for compliance.

  • Land use compatibility and well siting setbacks (e.g., 50 feet from septic tanks, 100 feet from drainfields) are enforced by OWRD and local health departments.

  • Records of well construction, alteration, and abandonment must be kept for at least 5 years by the contractor and made available for inspection.

  • Failure to submit a well report or comply with construction standards may result in civil penalties up to $5,000 per violation per day.