Split Award for a Precision Component Under Cost and Capacity Pressure

Oracle Cloud SCM · Put your knowledge to work in context.

All case studies

Split Award for a Precision Component Under Cost and Capacity Pressure

A manufacturer is awarding a one-year contract for a precision component. Three suppliers submitted quotes: Supplier A at $42 per unit for 100,000 units, 4-week lead time, 99.2% quality history, capacity 8,000 per month; Supplier B at $39 per unit for 150,000 units, 6-week lead time, 97.5% quality, capacity 12,000 per month; Supplier C at $45 per unit for 50,000 units, 3-week lead time, 99.8% quality, capacity 5,000 per month. Annual demand is 120,000 units with a 10% volume swing. The current approved supplier list includes A and B; C is not approved but has a quality certification. The sourcing rule is set to '100% to lowest price' and the buyer wants to split the award to reduce risk. Finance requires a 3% annual cost reduction.

1. Recommend an award strategy and show whether it meets the 3% cost-reduction requirement.

Read the worked answer

A 100% award to B is the lowest-price option: 120,000 x $39 = $4,680,000. If the current baseline is A at $42, that is a 7.1% reduction. However, a single source with a 6-week lead time and 97.5% quality creates delivery and quality risk, especially with a 10% volume swing that can push demand to 132,000 against B's 144,000 annual capacity.

A split award is more defensible. One workable split is B 70% and A 30%: 84,000 x $39 = $3,276,000 plus 36,000 x $42 = $1,512,000, total $4,788,000. Against the $5,040,000 A baseline, that is a 5.0% reduction, which clears the 3% target. It also keeps both approved suppliers active and uses B's capacity without exhausting it.

A 60/40 split gives $4,752,000? No: 72,000 x $39 = $2,808,000 plus 48,000 x $42 = $2,016,000, total $4,824,000, a 4.3% reduction. That is also acceptable but less cost-effective. The judgment is to choose the split that balances savings, capacity, and quality. B at 70% and A at 30% is a reasonable starting point; C should be qualified as a second source for the 3-week lead time, not awarded volume yet.

2. How should the sourcing rule and approved supplier list be configured to support the split?

Read the worked answer

The current rule '100% to lowest price' will always pick B and ignore the risk objective. The buyer should replace it with a split-award sourcing rule that assigns percentages or quantities by supplier and rank.

Configuration points:

  • Rank B first with a 70% allocation and A second with 30%. If the rule supports capacity constraints, cap B at its monthly capacity so the plan does not overload it during the volume swing.
  • Keep C off the awarded rule until qualification is complete. The quality certification is a good start, but the approved supplier list should require the remaining qualification steps, such as audit, insurance, and sample approval.
  • Set the blanket agreement or contract with the split percentages and a mechanism for reallocation if B misses delivery or quality targets.
  • Review the price-break tiers. B's $39 may depend on 150,000 units; at 84,000 units the price could change. The buyer should confirm the price at the awarded volume before finalizing.

The judgment is that a sourcing rule is a control, not just a default. If the rule cannot express split awards, the buyer should use a sourcing strategy or contract award that does, rather than manually overriding every PO.

3. What risks remain after the split award, and what should the buyer monitor?

Read the worked answer

The split reduces single-source risk but does not eliminate it.

  • Lead-time risk: B's 6-week lead time is the longest. A 10% demand swing may require expediting or safety stock. The buyer should monitor B's on-time delivery weekly and keep A's 4-week lead time as a fallback.
  • Quality risk: B's 97.5% quality is below A's 99.2%. The buyer should set an incoming inspection or quality gate for B's first shipments and track defect rates against the 97.5% history.
  • Capacity risk: B's 12,000 per month is enough for 120,000 annually but tight at 132,000. The split should include a capacity review at the volume swing upper bound, not just the base demand.
  • Price-risk: B's $39 may be volume-dependent. If the actual award is 84,000 units, confirm the price holds; otherwise the 5% savings estimate is overstated.
  • Supplier C: qualify C for the 3-week lead time, but do not award volume until qualification is complete. C's $45 price would erode savings if used for a large share.

The buyer should report monthly on cost against the 3% target, B's delivery and quality, and the status of C's qualification. A split award that is not monitored becomes a manual allocation problem.