PCI Plant Quality study materials
PCI Plant Quality study resources

PCI Plant Quality flashcards

PCI Plant Quality · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

PCI plant certification
An audit-based certification of a precast plant's quality management system, covering documented procedures, records, testing, and product-specific requirements rather than certifying individual members.
Corrective action closure
A corrective action is closed only after root cause is identified and the implemented fix is verified effective; containment alone does not satisfy closure.
Document control
The system ensuring only current approved procedures and drawings are used, with obsolete documents removed from points of use and changes recorded.
Internal audit independence
Internal quality audits are performed on a planned schedule by personnel who do not have direct responsibility for the activity being audited.
Calibration traceability
Scales, load cells, pressure gauges, and test equipment must be calibrated against standards traceable to a national metrology institute, with records retained.
Free moisture
The water in an aggregate above the saturated-surface-dry condition; only free moisture adds to the effective mixing water and must be subtracted from batch water.
Nominal maximum aggregate size
The largest sieve on which the specified percentage of coarse aggregate is retained; it limits section depth and reinforcement spacing for proper placement.
Admixture dispensing record
Each batch record must show admixture type, dose, and time; a failed or partial dose stops the batch and triggers nonconformance review.
Strand storage protection
Prestressing strand is stored off the ground, protected from corrosion and mechanical damage, and traceable by lot to mill certificates.
Water-cementitious ratio
Total water divided by total cementitious material by weight; it controls strength and durability and is not inferred from slump.
Absolute volume method
A mixture proportioning method in which the volumes of cement, water, air, and aggregates sum to one cubic meter or cubic yard.
Batch yield
Total batch weight divided by measured fresh unit weight; deviation outside tolerance indicates a batching or aggregate moisture error.
Mixer uniformity test
Samples taken from different positions in the mixer are compared for unit weight, air content, slump, and strength to verify mixing adequacy.
Trial mixture qualification
An approved trial mix establishes the design; a change in material source, admixture, or proportions requires re-qualification before production.
Vibration spacing
Internal vibrators are inserted at regular spacing, commonly not more than about 600 mm apart, and withdrawn slowly to avoid voids.
Over-vibration effect
Excessive vibration causes segregation and bleeding, while insufficient vibration leaves honeycomb and bug holes; both are nonconformances.
Steam curing limits
Accelerated curing follows a documented temperature-time curve with limited rates of rise and fall and a capped peak temperature to control cracking.
Stripping strength
The concrete strength at which forms may be removed, verified by test or maturity method to resist damage and construction loads.
Form dimensional check
Forms are verified for dimensions, squareness, and camber before casting, and form wear is compared against product tolerance limits.
Stressing force from pressure
The applied force equals gauge pressure multiplied by ram area, corrected by the system calibration; gauge and ram are calibrated together.
Elongation check
Measured strand elongation is compared to calculated elongation within the approved tolerance and is the primary verification of stressing force.
Seating loss
The strand slip at the anchorage when force transfers to the anchor; it is measured and compared with the design assumption.
Transfer strength
The concrete strength at transfer of prestress must meet the design requirement, verified by cylinder testing or an approved maturity method.
Strand damage rejection
Arc strikes, kinks, and mechanical damage to strand are cause for rejection; strand must be protected from weld current and sparks.
Air content test
Fresh concrete air content is measured by pressure meter or volumetric method with calibrated equipment at the specified frequency.
Test frequency nonconformance
A missed required test is a nonconformance requiring documented disposition; it is not a waived requirement.
Maturity method
An estimate of in-place strength from the temperature-time history of the concrete, calibrated to the specific mixture by a strength-maturity relationship.
Cylinder handling
Compressive strength specimens are molded, protected, and transported without damage, then tested per the applicable standard method.
Camber tolerance
Measured camber is compared with design camber at a defined reference condition and time after transfer, within the specified tolerance.
Embedded item position
Embedded plates, inserts, and strand projections are checked against approved shop drawings within the stated position tolerance.
Nonconformance disposition
Nonconforming product is identified, segregated, and dispositioned as repair, rework, or reject, with engineering approval where required.
Lifting plan
A documented plan matching lifting insert capacity, sling geometry, and equipment rating to the member weight and handling loads.