PE Petroleum · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Production and Facilities Engineering

  • Draw from memory a complete well-to-sales production system (reservoir, tubing, choke, separator, meter, sales line) and label where each major pressure loss occurs.

  • Work 15 nodal-analysis problems that combine inflow performance (Vogel and straight-line IPR) with vertical lift, solving for the operating point and for tubing-size and wellhead-pressure sensitivity.

  • Build a one-page artificial-lift selection matrix comparing gas lift, ESP, rod pump, and progressing-cavity pump on depth capability, rate, solids tolerance, free gas, viscosity, and power demand.

  • Size a two-stage horizontal separator on 10 practice problems using both liquid retention time and gas capacity (Souders-Brown) constraints, and state which constraint governs in each case.

  • Convert a set of separator and meter readings into daily oil, gas, and water rates and check the result against a shrinkage and meter-factor correction.

Your checkpoint

Closed-book artificial-lift selection matrix (one page, no notes) plus a 15-problem nodal-analysis set scored at 80% or better.

Week 2

Production and Facilities Engineering

  • Diagnose 12 flow-assurance scenarios (hydrate, wax, scale, asphaltene, severe slugging, emulsions) and prescribe a specific mitigation for each.

  • Estimate hydrate-forming conditions from gas gravity and composition data in 8 problems, then specify whether thermodynamic inhibition, insulation, or dehydration is the appropriate control.

  • Design a produced-water treating train to meet a stated oil-in-water specification, sizing a skim tank and a corrugated-plate interceptor from retention time and Stokes-law rise velocity.

  • Match 10 given corrosion or integrity conditions (CO2, H2S, erosion, galvanic, bacterial) to the mechanism and to a mitigation choice among inhibitor, CRA, coating, and cathodic protection.

  • Sketch a gas dehydration and dew-point control scheme and compute the water removal required to hit a stated pipeline dew point.

Your checkpoint

A one-page flow-assurance troubleshooting flowchart plus a written diagnosis-and-mitigation sheet for all 12 scenarios, self-graded against reference methods.

Week 3

Reservoir Engineering

  • Compute original oil and gas in place volumetrically for 12 problems spanning oil, dry gas, and retrograde systems, carrying units through consistently.

  • Apply material balance (MBE and p/z plots) to 8 problems to estimate initial hydrocarbons and to detect water influx or gas-cap expansion.

  • Interpret relative permeability and capillary pressure curves to explain fractional flow, water breakthrough timing, and remaining oil saturation in 6 exercises.

  • Classify drive mechanism (solution gas, gas cap, water drive, gravity drainage, compaction) for 10 production-and-pressure histories and justify each call with two quantitative indicators.

  • Construct a recovery-factor estimate for a waterflood using displacement efficiency, areal sweep, and vertical sweep, stating each assumption.

Your checkpoint

A worked problem notebook of 30 solved reservoir problems (volumetrics, material balance, relative permeability) with unit-consistent solutions and a one-page drive-mechanism identification key.

Week 4

Reservoir Engineering

  • Analyze decline curves for 10 well histories, selecting exponential, hyperbolic, or harmonic behavior and reporting EUR with the assumed economic limit stated explicitly.

  • Interpret a build-up or drawdown test on 6 problems to obtain permeability, skin, and wellbore storage effects, and explain what each result implies for the completion.

  • Screen 10 candidate reservoirs for waterflood or EOR suitability using mobility ratio, depth, oil gravity, and remaining-oil criteria, and rank them.

  • Reconcile volumetrics, material balance, and decline-based estimates for a single field and explain the spread between them.

  • Classify reserves by certainty category and produce a reserves booking statement for one worked example with stated assumptions.

Your checkpoint

A timed 40-question Domain 1 practice set completed in one sitting, scored at 70% or better, with every miss rewritten as a corrected note card.

Week 5

Drilling and Completion Engineering

  • Design a casing string on 5 practice problems: select weights and grades against burst, collapse, and tension with design factors applied and the governing load identified.

  • Compute hydrostatic pressure, equivalent mud weight, pore pressure, and fracture gradient for 10 wellbore scenarios and state the safe mud-weight window in each.

  • Work 12 well-control problems on kick detection, shut-in drillpipe and casing pressures, kill mud weight, and the wait-and-weight versus driller's method sequence.

  • Calculate annular velocity, equivalent circulating density, and bit hydraulic horsepower for 8 mud-hydraulics cases and identify where hole cleaning fails.

  • Compare water-based, oil-based, and synthetic-based mud systems on shale inhibition, temperature, and environmental limits for 6 given well conditions.

Your checkpoint

A completed casing-design and well-control problem set (25 problems) with the governing failure mode or safe mud window written out for every item.

Week 6

Drilling and Completion Engineering

  • Plan a directional or horizontal well trajectory on 5 problems, computing build rate, dogleg severity, and measured depth to target, and flagging where tortuosity or torque limits bite.

  • Design a primary cement job for 4 cases: specify slurry volume with excess, displacement, plug placement, and the test that verifies top of cement.

  • Select completion type (open hole, slotted liner, casing and perforating, sand screen, gravel pack) for 8 reservoir and wellbore conditions and defend each choice in one sentence.

  • Size a hydraulic fracture or matrix acid treatment at a screening level for 5 wells, stating the design variable that most limits the result.

  • Identify annular-pressure and well-integrity failure modes on 10 scenarios and state the diagnostic test and remediation for each.

Your checkpoint

A written well-construction plan for one hypothetical vertical well covering casing design, mud program, cementing, and completion selection, with calculations shown and assumptions listed.

Week 7

Reservoir Engineering & Production and Facilities Engineering

  • Re-solve every previously missed item from Domains 1 and 3 without notes, and log the underlying concept behind each error rather than the specific number.

  • Complete two 30-question mixed sets across Domains 1 and 3 under a strict time limit and tabulate accuracy by subtopic to rank remaining weak areas.

  • Practice locating and applying the governing equation for 20 problems using only an allowed reference handbook, timing each lookup.

  • Rebuild the three weakest subtopics from first principles into a single condensed formula-and-assumption sheet.

Your checkpoint

An error log with 100% of Domain 1 and Domain 3 misses reworked, plus a subtopic accuracy table showing every weak area at 75% or better on retest.

Week 8

Reservoir Engineering & Drilling and Completion Engineering & Production and Facilities Engineering

  • Sit two full-length timed mock exams covering all three domains with exam-day pacing and no interruptions.

  • Review every mock-exam miss and assign it to one of three buckets: knowledge gap, calculation error, or misread question, then act only on the largest bucket.

  • Re-drill the 25 highest-risk formulas across all three domains from memory in under 30 minutes.

  • Finalize exam-day logistics: allowed references, calculator, timing per question, and the rule for when to guess and move on.

Your checkpoint

Two completed full-length mocks with a written score-by-domain summary and a dated one-page final review sheet covering only the remaining weak points.

Milestones

Week 2: Score at least 75% on a self-made 25-question Domain 3 quiz on artificial lift, nodal analysis, separators, and flow assurance, closed book.

Week 4: Score at least 70% on a timed 40-question Domain 1 set and show a written explanation for every missed item.

Week 6: Finish the hypothetical well-construction plan end to end and score at least 70% on a 30-question Domain 2 set under time pressure.

Week 7: Every subtopic on the accuracy table reads 75% or higher after retest, and the condensed formula sheet fits on one page.

Week 8: Both full-length mocks completed within the time limit, with at least 70% overall and no single domain below 65%.