PECB Certified Management Systems Internal Auditor flashcards
PECB Certified Management Systems Internal Auditor · Build recall with a focused review session.
33 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Management system definition
- A set of interrelated or interacting elements of an organization used to establish policies and objectives, and processes to achieve those objectives.
- PDCA clause mapping
- Plan covers clauses 4, 5 and 6; Do covers 7 and 8; Check covers 9; Act covers 10. Auditors use this to trace where a requirement sits in the standard.
- Documented information
- Information required to be controlled and maintained by an organization and the medium on which it is contained. Combines the former concepts of documents and records.
- Process approach
- Management by interrelated processes, where inputs are converted into outputs. Auditors examine process inputs, outputs, sequence, interaction, controls and performance indicators.
- Risk-based thinking
- The approach in ISO 9001:2015 and ISO 14001:2015 clause 6.1 requiring the organization to determine risks and opportunities and plan actions to address them.
- Outsourced process responsibility
- Outsourced processes remain the organization's responsibility. The organization must control them, and the type and extent of control must be defined in the management system.
- Audit definition
- A systematic, independent and documented process for obtaining objective evidence and evaluating it objectively to determine the extent to which the audit criteria are fulfilled.
- Objective evidence
- Records, statements of fact or other information that are verifiable and based on observation, measurement, test or other means. It is evaluated against the audit criteria.
- Audit criteria
- The set of requirements used as a reference against which objective evidence is compared. Examples include standard clauses, internal procedures, legal requirements and contracts.
- Audit finding
- The result of evaluating collected audit evidence against the audit criteria. Findings indicate conformity or nonconformity and may indicate risks or opportunities for improvement.
- First-party audit
- An internal audit performed by, or on behalf of, the organization itself for management review and other internal purposes. It may support a self-declaration of conformity.
- Auditing principles
- Integrity, fair presentation, due professional care, confidentiality, independence, evidence-based approach and risk-based approach. These seven principles guide auditors under ISO 19011:2018.
- Independence for internal auditors
- Internal auditors need not be external to the organization, but must not audit their own work and must be free from bias and conflict of interest.
- Audit programme
- Arrangements for a set of one or more audits planned for a specific time frame, directed at a specific purpose, including all activities needed to plan and organize them.
- Audit plan
- A description of the activities and arrangements for a specific audit, including objectives, scope, criteria, dates, locations, team roles and time allocation.
- Audit programme indicators
- Measures of programme performance such as conformity of audits to plans, conformity of audit teams to competence requirements, auditee feedback, and effectiveness of programme implementation.
- Initiating the audit
- Determining feasibility of the audit, establishing contact with the auditee, confirming authority to conduct the audit, and obtaining information about the auditee's activities and processes.
- Audit objectives vs scope
- Objectives state what the audit intends to accomplish; scope states the boundaries covered, such as sites, functions, processes, and the time period.
- Audit sampling
- Selecting less than the total population of evidence, based on risk and significance. The sampling plan should be documented; ISO 19011 does not mandate statistical sampling.
- Audit plan versus checklist
- The audit plan is a required arrangement document describing the specific audit. A checklist is an optional auditor tool; ISO 19011 does not require or prescribe checklists.
- Opening meeting purpose
- To confirm the audit plan, explain how activities will be carried out, confirm communication channels, confirm resources, and clarify that the audit is sampling-based.
- Information sources in audit
- Interviews with auditees, observation of activities and conditions, and review of documents and records. Evidence from one source should be verified against another.
- Triangulation of evidence
- Verifying a statement from an interview against records or direct observation before treating it as objective evidence. This reduces reliance on unverified assertion.
- Open versus leading questions
- Open questions invite description and cannot be answered yes or no. Leading questions suggest the expected answer and should be avoided in audit interviews.
- Major nonconformity
- A nonconformity where a requirement is not addressed, or where the situation would cause the management system to fail to achieve its intended results.
- Minor nonconformity
- An isolated lapse or single observed departure from a requirement that does not indicate a systemic failure of the management system to meet requirements.
- Closing meeting purpose
- To present findings and conclusions, explain the sampling basis, agree on timeframes for corrective action, and inform the auditee that the audit report will follow.
- Audit conclusions
- Conclusions prepared before the closing meeting that address achievement of audit objectives, conformity of the management system, effectiveness of implementation, and opportunities for improvement.
- Audit report content
- Objectives, scope, client, audit team, auditee, dates, locations, criteria, findings, conclusions, and any deviations from the audit plan. The report is dated and approved.
- Correction versus corrective action
- Correction eliminates the detected nonconformity itself. Corrective action eliminates the root cause so the nonconformity does not recur elsewhere or later.
- Finding structure
- State the requirement (criteria), the objective evidence observed, and the nonconformity statement. Adding the risk or consequence strengthens the finding.
- Follow-up on audit
- Verification of the implementation and effectiveness of corrective actions. The audit is not closed until follow-up is completed and the results are recorded.
- Escalation of findings
- If corrective action is not taken or is ineffective, the finding is escalated to top management and may become input to management review under ISO 9001:2015 clause 9.3.