- Energy performance
- Measurable results related to energy efficiency, energy use, and energy consumption, determined by comparison against the energy baseline. Improvement means better measured results, not just completed projects.
- Energy baseline (EnB)
- Quantitative reference providing a basis for comparison of energy performance over a defined period, adjusted using relevant variables so comparisons remain valid when conditions change.
- Energy performance indicator
- Measurable or modelled value of energy performance defined by the organization. It may be a ratio or normalized value and need not be expressed in energy units.
- Significant energy use
- Energy use accounting for substantial energy consumption or offering considerable potential for improvement, identified through the energy review using defined criteria.
- Relevant variable
- Quantifiable factor that significantly affects energy performance and changes routinely, such as production output or weather, used to normalize the baseline and EnPIs.
- Static factor
- Quantifiable factor that significantly affects energy performance but does not routinely change, such as facility size or installed capacity, so it is not used for routine normalization.
- Normalization
- Adjustment of energy data and baselines using relevant variables to compare energy performance under changed conditions such as different output levels or occupancy.
- Continual improvement (EnMS)
- Recurring activity to enhance energy performance and the energy management system. It requires demonstrable improvement in results, not only in documentation or procedures.
- Energy review
- Analysis of energy use and consumption based on measurement and other data, leading to identification of significant energy uses, current performance, and improvement opportunities.
- Energy policy
- Top management statement committing the organization to continual improvement of energy performance, availability of information and resources, and fulfilment of applicable requirements.
- Energy objectives and targets
- Objectives are overall energy performance goals; targets are detailed, measurable requirements set to achieve them, consistent with the energy policy and significant energy uses.
- Operational control
- Controls for operations and maintenance that affect significant energy uses, including criteria for processes and control of outsourced activities, to ensure energy performance is achieved.
- Procurement for energy
- Requirement to consider energy performance improvement when procuring energy-using products, equipment, services, and energy supply, and to define specifications accordingly.
- Design for energy performance
- Requirement to consider energy performance improvement in the design of new, modified, or renovated facilities, equipment, systems, and processes that can affect energy performance.
- Management review inputs
- Required inputs include status of actions, changes in issues and interested parties, energy performance and EnPI results, nonconformities, audit results, and resource adequacy.
- Audit criteria
- Set of requirements used as a reference against which objective evidence is compared, such as ISO 50001, legal requirements, and the organization's own EnMS documents.
- Objective evidence
- Verifiable records, statements of fact, or other information relevant to the audit criteria. It is the only basis on which audit findings may be concluded.
- Third-party audit
- Audit performed by an independent external organization, typically a certification body, to determine conformity with a standard and support a certification decision.
- Audit sampling
- Selection of a representative subset of information or activities for verification. Sampling must be planned and its basis recorded, and conclusions apply only to the sample.
- Independence in audit
- Freedom from bias and conflict of interest; auditors must not audit their own work, and internal auditors must be organizationally separate from the activity audited.
- Risk-based auditing
- Approach allocating audit effort and sampling intensity to areas where failure would most affect EnMS effectiveness and energy performance outcomes.
- Stage 1 audit
- Readiness assessment evaluating documented information, scope, energy review approach, EnPI and baseline approach, and internal audit and management review status before stage 2.
- Audit plan
- Description of activities and arrangements for an audit, covering objectives, criteria, scope, dates, sites, team roles, time allocation, and sampling approach.
- Audit team leader
- Auditor responsible for managing the audit, preparing the plan, leading the team, presenting findings, and producing the audit report.
- Opening meeting
- Formal meeting confirming the audit plan, communication arrangements, availability of evidence, sampling approach, and confidentiality and safety requirements with auditees.
- Audit time determination
- Calculation of audit duration based on effective personnel, complexity of energy sources and SEUs, number of sites, and prior performance, within certification scheme rules.
- Energy data verification
- Testing whether measurement systems, meters, and data collection provide accurate, traceable, and complete energy data used in the energy review and EnPI calculation.
- Nonconformity
- Non-fulfilment of a requirement, supported by objective evidence and citing the specific requirement. It is classified by scheme rules, typically as major or minor.
- Baseline adjustment check
- Audit activity verifying that documented adjustments to the energy baseline are justified, methodologically sound, and applied consistently when relevant variables change.
- Audit report
- Documented record of the audit containing objectives, scope, criteria, dates, sites, team, findings, and conclusions, owned by the audit team leader.
- Corrective action verification
- Confirmation that correction was made and actions to eliminate the cause were implemented and effective, evidenced by records or follow-up audit before closure.
- Audit program
- Set of one or more audits planned for a specific time frame and purpose, managed with defined objectives, risks, resources, competence, and monitoring.
- Auditor competence
- Demonstrated ability to apply knowledge and skills, verified through education, experience, training, and ongoing performance evaluation such as witnessing and report review.