- Recovery Time Objective (RTO)
- Related: Recovery Point Objective (RPO), Maximum Tolerable Period of Disruption (MTPD), Business Impact Analysis (BIA)
The maximum acceptable elapsed time to restore a process, system, or service after a disruption before the impact becomes unacceptable. It sets the target speed for recovery and drives strategy selection and testing criteria.
- Recovery Point Objective (RPO)
- Related: Recovery Time Objective (RTO), Data Replication, Backup and Restore
The maximum acceptable amount of data loss measured in time before a disruption, expressed as how far back the last usable copy may be. It determines backup frequency and replication design.
- Maximum Tolerable Period of Disruption (MTPD)
- Related: Recovery Time Objective (RTO), Business Impact Analysis (BIA)
The longest time a disruption of an activity can last before its impacts become unacceptable to the organization. It is derived from impact analysis and caps the RTO that a recovery strategy may accept.
- Business Impact Analysis (BIA)
- Related: Maximum Tolerable Period of Disruption (MTPD), Critical Activity, Risk Assessment
A structured process that identifies time-critical activities and quantifies how disruption affects them over time, across financial, legal, regulatory, operational, and reputational dimensions. It produces recovery priorities, RTOs, RPOs, and minimum resource requirements.
- Risk Assessment
- Related: Business Impact Analysis (BIA), Threat, Risk Treatment
The process of identifying threats and vulnerabilities relevant to the organization, then analyzing and evaluating the resulting risk against defined criteria. In disaster recovery it determines which scenarios the program must plan for and how strategies are prioritized.
- Risk Treatment
- Related: Risk Assessment, Residual Risk
The selection and application of options to modify risk, such as avoiding, reducing, transferring, or accepting it. Disaster recovery strategies are one form of treatment aimed at reducing the likelihood or consequence of disruptive events.
- Residual Risk
- Related: Risk Treatment, Risk Appetite
The risk that remains after controls and recovery capabilities have been applied. It must be compared with the organization's risk acceptance criteria and formally accepted by an accountable owner.
- Business Continuity Management (BCM)
- Related: Disaster Recovery, Business Continuity Plan (BCP), Resilience
A holistic management process that builds organizational resilience to disruptions through capability for prevention, response, and recovery. Disaster recovery is the part of BCM focused on restoring technology and supporting infrastructure.
- Disaster Recovery (DR)
- Related: Business Continuity Management (BCM), Disaster Recovery Plan (DRP), Recovery Time Objective (RTO)
The capability and set of arrangements used to restore critical technology services, data, and supporting infrastructure after a major disruption within agreed time and data-loss targets. It focuses on IT and dependent facilities rather than the whole business.
- Business Continuity Plan (BCP)
- Related: Disaster Recovery Plan (DRP), Crisis Management, Incident Response
Documented procedures that guide an organization in responding to and continuing or restoring business activities during and after a disruption. It coordinates people, communications, facilities, and processes, of which the IT recovery plan is one component.
- Disaster Recovery Plan (DRP)
- Related: Business Continuity Plan (BCP), Runbook, Disaster Recovery Strategy
A documented set of procedures, roles, and resources for recovering critical IT systems, data, and infrastructure after a disruption. It translates recovery strategies into sequenced, executable actions with owners and dependencies.
- Disaster Recovery Strategy
- Related: Recovery Site, Disaster Recovery Plan (DRP), Recovery Time Objective (RTO)
The chosen approach for recovering prioritized services, such as backup and restore, warm standby, or active-active, selected by weighing recovery targets against cost, risk, and feasibility. It defines the architecture and arrangements that the plan later operationalizes.
- Disaster Recovery Program
- Related: Disaster Recovery Policy, Program Sponsor, Disaster Recovery Maturity
The ongoing organizational structure of governance, resources, processes, and improvement activities that keeps recovery capability effective over time. It spans initiation, risk analysis, strategy, planning, testing, and maintenance rather than a single project.
- Disaster Recovery Policy
- Related: Disaster Recovery Program, Program Sponsor, Recovery Time Objective (RTO)
A top-management statement defining the organization's commitment, objectives, scope, principles, and accountability for disaster recovery. It authorizes the program and provides the criteria against which recovery capability is governed and reviewed.
- Program Sponsor
- Related: Disaster Recovery Policy, Steering Committee, Risk Appetite
A senior executive who provides authority, funding, and visible support for the disaster recovery program and removes organizational obstacles. The sponsor holds ultimate accountability for accepting residual risk and approving recovery targets.
- Steering Committee
- Related: Program Sponsor, Disaster Recovery Program, Disaster Recovery Maturity
A cross-functional governance body that oversees the disaster recovery program, resolves prioritization conflicts, approves strategies and budgets, and monitors progress. It typically includes business, IT, risk, and compliance representation.
- Risk Appetite
- Related: Residual Risk, Risk Treatment, Program Sponsor
The amount and type of risk an organization is willing to accept in pursuit of its objectives. It guides how much investment in recovery capability is justified and which recovery targets are acceptable.
- Critical Activity
- Related: Business Impact Analysis (BIA), Maximum Tolerable Period of Disruption (MTPD), Dependency Mapping
A business process or supporting service whose disruption would cause unacceptable impact within a defined time, based on BIA findings. Critical activities receive priority in recovery sequencing and resource allocation.
- Dependency Mapping
- Related: Critical Activity, Configuration Management Database (CMDB), Single Point of Failure
The identification and documentation of relationships between business activities, applications, data, infrastructure, suppliers, and people that recovery relies upon. It reveals hidden single points of failure and determines correct recovery sequencing.
- Single Point of Failure
- Related: Redundancy, Dependency Mapping, Risk Assessment
A component, resource, or supplier whose failure alone can disrupt a critical service because no redundancy or alternative exists. Identifying these drives targeted resilience investment and recovery strategy design.
- Recovery Site
- Related: Hot Site, Warm Site, Cold Site
A designated alternate location or environment where critical systems and operations can be restored after a disaster. Options range from cold and warm sites to hot sites and cloud-based regions, each with different cost and recovery speed.
- Hot Site
- Related: Warm Site, Recovery Site, Recovery Time Objective (RTO)
A fully equipped alternate facility or environment with hardware, software, data, and network ready to take over operations with minimal delay. It supports very short recovery times but carries the highest ongoing cost.
- Warm Site
- Related: Hot Site, Cold Site, Recovery Site
An alternate environment with some pre-installed infrastructure and partial data that requires configuration and data restoration before operations resume. It balances cost against moderate recovery times.
- Cold Site
- Related: Warm Site, Hot Site, Recovery Time Objective (RTO)
A basic alternate facility providing space, power, and connectivity but no pre-installed systems or current data. Recovery requires substantial setup time, making it suitable only for activities with long tolerable disruption periods.
- Backup and Restore
- Related: Recovery Point Objective (RPO), Data Replication, Immutable Backup
A recovery strategy that copies data and systems to separate media so they can be reinstated after loss or corruption. Its achievable RTO and RPO depend on backup frequency, retention, restoration speed, and tested integrity.
- Data Replication
- Related: Recovery Point Objective (RPO), Backup and Restore, Active-Active
The continuous copying of data from one location or system to another so a usable copy exists if the primary fails. Synchronous replication minimizes data loss while asynchronous replication tolerates latency over distance.
- Active-Active
- Related: Active-Passive, Redundancy, Data Replication
A resilient architecture in which two or more sites or systems process workload simultaneously, so failure of one shifts traffic to the others with little or no interruption. It offers the fastest recovery but demands significant cost and operational maturity.
- Active-Passive
- Related: Active-Active, Failover, Warm Site
A resilient architecture in which a standby site or system remains idle or partially loaded until the primary fails, then takes over. It costs less than active-active but requires a tested failover process and tolerates some interruption.
- Failover
- Related: Failback, Active-Passive, Redundancy
The process of transferring operations from a failed or degraded component or site to a redundant one. It must be automated or rehearsed, and its duration contributes directly to the achieved recovery time.
- Failback
- Related: Failover, Disaster Recovery Plan (DRP), Recovery Site
The planned return of operations from the recovery environment to the restored primary environment. It requires reconciliation of data and configuration, and is often more complex and risky than the original failover.
- Redundancy
- Related: Single Point of Failure, Failover, Active-Active
The deliberate duplication of components, paths, data, or capacity so that a single failure does not interrupt service. It is a core design principle for meeting aggressive recovery objectives.
- Crisis Management
- Related: Incident Response, Emergency Operations Center, Business Continuity Plan (BCP)
The arrangements for leading and coordinating the organization during a major disruption, including decision-making, escalation, and stakeholder communication. It complements technical recovery by managing the wider organizational response.
- Incident Response
- Related: Crisis Management, Disaster Recovery Plan (DRP), Recovery Time Objective (RTO)
The structured process for detecting, containing, eradicating, and recovering from security or operational incidents. It may trigger disaster recovery when impact exceeds defined thresholds.
- Emergency Operations Center
- Related: Crisis Management, Disaster Recovery Plan (DRP), Tabletop Exercise
A designated physical or virtual location where the response team assembles to coordinate decisions, communications, and recovery activities during a disruption. It centralizes information flow and authority.
- Runbook
- Related: Disaster Recovery Plan (DRP), Recovery Time Objective (RTO), Failover
A detailed, step-by-step operational guide for executing a specific recovery procedure, including prerequisites, commands, validation checks, and escalation contacts. Runbooks make plans executable by staff under pressure.
- Tabletop Exercise
- Related: Disaster Recovery Testing, Simulation Test, Lessons Learned
A discussion-based test in which participants walk through a simulated disruption scenario to validate plans, roles, and decision-making without activating systems. It is low cost and effective for revealing gaps in coordination and assumptions.
- Disaster Recovery Testing
- Related: Tabletop Exercise, Full Interruption Test, Lessons Learned
Planned activities that verify recovery plans, strategies, and resources actually work and meet defined targets. Testing ranges from plan reviews and tabletops to full failover exercises and should follow a documented schedule.
- Full Interruption Test
- Related: Disaster Recovery Testing, Failover, Failback
The most rigorous form of DR testing, in which production operations are actually moved to the recovery environment and back. It provides the strongest evidence of capability but carries the highest risk and requires careful controls.
- Lessons Learned
- Related: Disaster Recovery Testing, Corrective Action, Disaster Recovery Maturity
The structured review after a test or real incident that identifies what worked, what failed, and what must change. Findings feed corrective actions into plan updates and program improvement.
- Corrective Action
- Related: Lessons Learned, Disaster Recovery Maturity, Disaster Recovery Plan (DRP)
A documented change made to eliminate the cause of a detected deficiency in plans, capabilities, or controls. Each action should have an owner, a due date, and verification of completion.
- Disaster Recovery Maturity
- Related: Disaster Recovery Program, Lessons Learned, Steering Committee
The measured level of sophistication and effectiveness of an organization's recovery capability, typically assessed against a staged model. It reflects governance, planning, testing frequency, and continuous improvement rather than document existence alone.
- Resilience
- Related: Business Continuity Management (BCM), Redundancy, Disaster Recovery (DR)
The ability of an organization and its systems to anticipate, absorb, adapt to, and recover from disruption. It combines preventive design, continuity arrangements, and recovery capability.